HIGH COURT OF AUSTRALIA
GLEESON CJ,
GAUDRON, McHUGH, GUMMOW, KIRBY, HAYNE AND CALLINAN JJMELVILLE ROBERT MARSHALL APPELLANT
AND
DIRECTOR-GENERAL, RESPONDENT
DEPARTMENT OF TRANSPORTMarshall v Director-General, Department of Transport
[2001] HCA 37
21 June 2001
B52/2000ORDER
1. Appeal allowed with costs including reserved costs.
2.Set aside the orders made by the Court of Appeal of the Supreme Court of Queensland on 22 October 1999, and in place thereof, order that:
(a) the appeal to that Court be allowed with costs;
(b)the order of the Land Appeal Court made on 24 July 1998 be set aside;
(c)the application dismissed by the Land Appeal Court be remitted to that Court to be dealt with in accordance with law.
On appeal from the Supreme Court of Queensland
Representation:
D F Jackson QC with D A Kelly for the appellant (instructed by James Conomos Lawyers)
P A Keane QC, Solicitor-General for the State of Queensland with R S Jones for the respondent (instructed by Crown Solicitor for Queensland)
Notice: This copy of the Court's Reasons for Judgment is subject to formal revision prior to publication in the Commonwealth Law Reports.
The issue in this appeal is whether compensation for injurious affection payable to a dispossessed landowner pursuant to s 20 of the Acquisition of Land Act 1967 (Q) ("the Act") is restricted to compensation for the impact of the work done on the actual land taken, and the precise use to which that land is put.
Decision of the Queensland Land Court
The issue arises in this way. The appellant owned a large area of land immediately to the west of the Bruce Highway near Nambour in Queensland. Until 1985, the highway consisted of two lanes. In that year, a constructing authority within the meaning of s 4 of the Act[1], acquired about 5500 square metres of the appellant's land for "road purposes". Section 12(5) of the Act relevantly applied as follows to the resumed land:
"… the estate and interest of every person entitled to the whole or any part of the land shall thereby be converted into a right to claim compensation under this Act. …"
The appellant sought compensation under the Act. Included in his application for compensation was a claim as follows:
"Damages Due to Injurious Affection
As a direct consequence of the construction of the road on the land resumed by the respondent Authority, the claimant has suffered loss, damage and a diminution in the value of the balance lands in that as at the date of resumption such lands could reasonably have been foreseen to be rendered more susceptible to flooding. The claimant's claim for compensation is calculated by reference to the cost of flood mitigation works already carried out and remaining to be carried out on the balance lands sufficient to return the said lands to the same degree of susceptibility to/immunity from flooding as was the case at the date of resumption for rainfall events in the Eudlo Creek catchment.
$651,325.00"
[1]"Meaning…
Keep reading for free
Create a free CaseChat account to read Marshall v Director General, Department of Transport and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2001] HCA 37
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the High Court was to determine the scope of compensation for injurious affection under the Act. Specifically, the court had to consider whether a landowner could claim compensation for a diminution in the value of their retained land due to the construction of a public work on resumed land, even if that resumed land had not yet been physically incorporated into the completed public work. This involved interpreting the meaning of "injurious affection" in the context of land resumption and the causal link required between the public work and the alleged damage to the landowner's remaining property.
The High Court allowed the appeal, setting aside the orders of the Court of Appeal of the Supreme Court of Queensland. The court reasoned that compensation for injurious affection under section 20 of the Act was not confined to the physical impact on the resumed land itself or its immediate use. Instead, it encompassed the consequences of the construction of the public work on the landowner's retained land, irrespective of whether the resumed land had been physically used for the statutory purpose at the time of the claim. The court found that the construction of the new northbound lanes of the Bruce Highway, which necessitated the resumption of Mr Marshall's land, had altered the drainage patterns and led to increased flooding on his remaining property. This alteration constituted injurious affection for which compensation was payable. The case was remitted to the Land Appeal Court for determination in accordance with law.
Orders
Orders of the court
1. Appeal allowed with costs including reserved costs.
2. Set aside the orders made by the Court of Appeal of the Supreme Court of Queensland on 22 October 1999, and in place thereof, order that:
(a) the appeal to that Court be allowed with costs;
(b) the order of the Land Appeal Court made on 24 July 1998 be set aside;
(c) the application dismissed by the Land Appeal Court be remitted to that Court to be dealt with in accordance with law.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: GLEESON CJ, GUMMOW, KIRBY AND CALLINAN JJ, GAUDRON J, HUGH J, HAYNE J