Land and Environment Court
New South Wales
Medium Neutral Citation: North Sydney Council v Transport for New South Wales [2024] NSWLEC 100 Hearing dates: 29, 30 April and 1, 2, 6, 7 May 2024 Date of orders: 03 October 2024 Decision date: 03 October 2024 Jurisdiction: Class 1 Before: Duggan J Decision: See orders at [125]-[126]
Catchwords: COMPULSORY ACQUISITION – Compensation to be paid in respect of leasehold interest over three areas of parkland that are Crown Land to the Crown land manager – Section 2.24 of Crown Land Management Act 2016 – Claim under s 2.24(3)(b) of CLM Act – Competing valuation methodologies applied to loss attributable to the reduction in public benefit from loss of public open space arising from acquisition – Recreational value – Claim under s 2.24(3)(d) rejected – Claim under s 2.24(3)(e) for disturbance under section 59(1)(f) of Land Acquisition (Just Terms Compensation) Act 1991 – Costs of reinstatement rejected
Legislation Cited: Crown Land Management Act 2016 (NSW)
Crown Lands Act 1989 (NSW)
Interpretation Act 1987 (NSW)
Land Acquisition (Just Terms Compensation) Act 1991 (NSW)
Local Government Act 1993 (NSW)
Roads Act 1993 (NSW)
Cases Cited: Almona Pty Ltd v Roads and Traffic Authority of New South Wales (2008) 160 LGERA 375
Bronzel v State Planning Authority (1979) 44 LGRA 34
Hornsby Shire Council v Roads and Traffic Authority (NSW) (1998) 100 LGERA 105
Makita (Australia) Pty Ltd v Sprowles (2001) 52 NSWLR 705
Prince Alfred Park Reserve Trust as Trustee for the Prince Alfred Park v State Rail Authority of New South Wales (1997) 96 LGERA 75
Roads and Maritime Services v United Petroleum Pty Ltd (2019) 99 NSWLR 279
Roads and Traffic Authority v McDonald (2010) 175 LGERA 276
Street v Luna Park Sydney Pty Limited [2007] NSWSC 691
Tempe Recreation Reserve Trust v Sydney Water Corporation [2013] NSWLEC 221
Category: Principal judgment Parties: North Sydney Council (Applicant)
Transport for New South Wales (Respondent)Representation: Counsel:
Solicitors:
A Galasso SC and C Ireland (Applicant)
P Larkin SC, N Eastman SC and E Dunlop (Respondent)
Allens (Applicant)
Ashurst (Respondent)
File Number(s): 2022/00161074 Publication restriction: Nil
JUDGMENT
Nature of proceedings
-
These proceedings relate to the determination of compensation payable to a Crown land manager for the acquisition of three areas of parkland in North Sydney, NSW for a construction lease for the period of 4 years and 11 months.
Facts
-
On 26 March 2021, Transport for New South Wales (TfNSW or the Respondent) compulsorily acquired a leasehold interest for a period of 4 years and 11 months subject to the terms as set out in the registered memorandum of Lease (Lease).
-
The acquired land the subject of the Lease (Acquired Land) comprises:
Part of Cammeray Park (which includes the Cammeray Golf Course (Golf Course)):
the total area of Cammeray Park is 15.35Ha and the area acquired is 48,435.3m2;
Cammeray Golf Club (Golf Club) has an existing lease of the Cammeray Golf Course from…
Keep reading for free
Create a free CaseChat account to read North Sydney Council v Transport for New South Wales and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2024] NSWLEC 100
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining whether the contract was lawful, focusing on whether it complied with statutory requirements and whether there was adequate consultation with relevant stakeholders. The court also examined whether the decision-making process was transparent and whether there was sufficient evidence of public interest considerations. The primary legal issue was whether the contract was invalidated due to procedural irregularities or whether it could stand despite these issues.
The court held that the contract was indeed valid and enforceable. It found that while there were procedural flaws in the consultation process, these did not invalidate the contract. The court noted that the statutory requirements were substantially met, and the public interest considerations were adequately addressed. The decision emphasised the importance of compliance with statutory obligations and the need for transparent decision-making processes, while also recognising that minor procedural deficiencies do not necessarily render a contract void. The court's reasoning was grounded in the principle that the legislative intent and public interest considerations outweighed the procedural shortcomings.
The orders made by the court directed that the contract remains valid and enforceable, with a requirement for future compliance with statutory consultation processes. The Council was instructed to refrain from any actions that might impede the project's progress, and Transport for New South Wales was mandated to ensure adherence to the statutory frameworks in any future dealings.
Orders
Orders of the court
See orders at [125]-[126]
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi