Port of Newcastle Operations Pty Ltd v Glencore Coal Assets Australia Pty Ltd

Link copied
Case Copied 61 min read

HIGH COURT OF AUSTRALIA

KIEFEL CJ,
GAGELER, GORDON, STEWARD AND GLEESON JJ

PORT OF NEWCASTLE OPERATIONS PTY

LIMITED  APPELLANT

AND

GLENCORE COAL ASSETS AUSTRALIA

PTY LTD & ORS  RESPONDENTS

Port of Newcastle Operations Pty Limited v Glencore Coal Assets Australia Pty Ltd

[2021] HCA 39

Date of Hearing: 7 September 2021

Date of Judgment: 8 December 2021

S33/2021

ORDER

1. Vary the orders of the Full Court of the Federal Court of Australia made on 24 August 2020 by inserting a new order 5: "The determination according to law by the Tribunal on remitter pursuant to order 1 be confined to redetermining the scope of the Navigation Service Charge."

2.Appeal otherwise dismissed.

On appeal from the Federal Court of Australia

Representation

C A Moore SC with D J Roche for the appellant (instructed by Clayton Utz)

N J Young QC with N P De Young QC and M P Costello for the first respondent (instructed by Clifford Chance)

S B Lloyd SC with C M Dermody for the third respondent (instructed by DLA Piper)

Submitting appearance for the second respondent

Notice:  This copy of the Court's Reasons for Judgment is subject to formal revision prior to publication in the Commonwealth Law Reports.

  1. KIEFEL CJ, GAGELER, GORDON, STEWARD AND GLEESON JJ.   This is an appeal by special leave from a decision of the Full Court of the Federal Court (Allsop CJ, Beach and Colvin JJ)[1] given on an appeal on questions of law from a decision of the Australian Competition Tribunal[2]. The appeal raises issues of statutory construction central to the operation of Pt IIIA of the Competition and Consumer Act 2010 (Cth) ("the Act").

  2. The appellant is Port of Newcastle Operations Pty Limited ("PNO"). Since 2014, PNO has been the lessee from the State of New South Wales of the Port of Newcastle and has been the "operator" of the Port under the Ports and Maritime Administration Act 1995 (NSW) ("the PMA Act").

  3. The Port is one of the largest coal exporting ports in the world. The Port is the only commercially viable means of exporting coal from more than 30 operating coal mines in the Hunter Valley.

  4. PNO, in its capacity as operator of the Port, relevantly controls use by those involved in the export of coal of two categories of facility at the Port. One is the loading berths, located at the three terminals at the Port, at which ships are loaded with coal for export. The other is the shipping channels, through which ships entering the Port must pass to reach the loading berths and through which ships once loaded must again pass to exit the Port. The shipping channels were constructed by dredging and associated public works undertaken by the State of New South Wales at various times over the course of more than a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Port of Newcastle Operations Pty Ltd v Glencore Coal Assets... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2021] HCA 39
Decision Date

CaseChat Overview and Summary

The High Court of Australia considered an appeal by Port of Newcastle Operations Pty Ltd (PNO) against Glencore Coal Assets Australia Pty Ltd concerning access disputes relating to infrastructure at the Port of Newcastle. The dispute centred on the amount and applicability of a navigation service charge and a wharfage charge, which PNO sought to levy on Glencore for the use of port infrastructure. These charges were fixed under New South Wales legislation, but the dispute arose in the context of a declared service under Part IIIA of the *Competition and Consumer Act 2010* (Cth).

The legal issues before the High Court included whether the Australian Competition Tribunal erred in its determination of the range of circumstances in which the navigation service charge was payable, and whether it erred in its calculation of the amount of that charge. The Court was required to interpret the meaning of "access" within Part IIIA of the Act and consider the application of the pricing principles set out in section 44ZZCA of the Act.

The High Court varied the orders of the Full Court of the Federal Court, confining the remittal to the Tribunal to redetermining the scope of the Navigation Service Charge. The Court otherwise dismissed the appeal. This outcome indicates that while the Tribunal's original determination on the scope of the charge was subject to further review, the broader appeal by PNO was unsuccessful.

Orders

Orders of the court

1. Vary the orders of the Full Court of the Federal Court of Australia made on 24 August 2020 by inserting a new order 5: "The determination according to law by the Tribunal on remitter pursuant to order 1 be confined to redetermining the scope of the Navigation Service Charge."

2. Appeal otherwise dismissed.

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

KIEFEL CJ, GAGELER, GORDON, STEWARD AND GLEESON JJ
Glencore and PNO have made clear that it is common ground that the revocation of the Declaration in 2017 has had no effect on the arbitration of the access dispute which Glencore notified to the ACCC in 2016[65]. It appears to be common ground that the revocation of the Declaration will have no effect on the operation or enforcement of the final determination of that access dispute that will result either from the Tribunal Decision being restored (if this appeal is allowed and the Full Court Decision is set aside) or from a decision to be made by the Tribunal in the future (if this appeal is dismissed and the order remitting the matter to the Tribunal made by the Full Court is left to stand)[66]. The appeal can therefore be taken to continue to bear on the rights of the parties.[65]See s 44I(4)(a) of the Act.[66]See s 44I(4)(b) of the Act.Tribunal Decision The Final Determination, which resulted from the Tribunal Decision, was expressed to govern both the wharfage charge and the navigation service charge payable by Glencore to PNO for a period commencing in 2018 and expiring in 2031. The wharfage charge as determined in the Final Determination will be referred to in these reasons as "the Wharfage Charge". The navigation service charge as determined in the Final Determination will be referred to as "the Navigation Service Charge". The Wharfage Charge was uncontroversial at the time of the Tribunal Decision and remains uncontroversial. The Wharfage Charge was the subject of agreement between Glencore and PNO reached in the course of the arbitration and was not in dispute in the re-arbitration before the Tribunal. The Navigation Service Charge was controversial at the time of the Tribunal Decision in two respects. The first concerned the range of circumstances in which the Navigation Service Charge was to be payable by Glencore to PNO. The second concerned the calculation of the amount of the Navigation Service Charge.Scope of the Navigation Service Charge In the final determination reviewed by the Tribunal, the ACCC had determined that the navigation service charge was to be payable by Glencore to PNO in either of two circumstances. One was where Glencore, either directly or by an agent, chartered a ship to enter the Port and load its coal. The other was where Glencore brought itself within the extended meaning of "owner" in s 48(4)(b) of the PMA Act by representing to PNO that it had the functions of the owner, or accepted the obligation to exercise those functions, in order for a ship to enter the Port and load its coal. In the Final Determination, the Tribunal confined the scope of the Navigation Service Charge to the circumstance where Glencore owns or, either directly or by an agent, charters a ship to enter the Port and load its coal. The Final Determination thereby extended the Navigation Service Charge to circumstances where Glencore sold its coal CIF but excluded the Navigation Service Charge from circumstances where Glencore sold its coal FOB.

Ratio Decidendi

Legal principle established

Established by: KIEFEL CJ, GAGELER, GORDON, STEWARD AND GLEESON JJ