JKC Australia LNG Pty Ltd v CH2M Hill Companies Ltd [No 2]

Link copied
Case Copied 69 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

TITLE OF COURT  :   THE COURT OF APPEAL (WA)

CITATION:   JKC AUSTRALIA LNG PTY LTD -v- CH2M HILL COMPANIES LTD  [No 2] [2020] WASCA 112

CORAM:   BUSS P

BEECH JA

VAUGHAN JA

HEARD:   27 & 30 MARCH 2020

DELIVERED          :   22 JULY 2020

FILE NO/S:   CACV 70 of 2019

BETWEEN:   JKC AUSTRALIA LNG PTY LTD

Appellant

AND

CH2M HILL COMPANIES LTD

First Respondent

UGL PTY LIMITED (FORMERLY KNOWN AS UGL LIMITED)

Second Respondent

GENERAL ELECTRIC COMPANY 

Third Respondent

ON APPEAL FROM:

Jurisdiction              :   SUPREME COURT OF WESTERN AUSTRALIA

Coram:   QUINLAN CJ

File Number            :   CIV 2584 of 2018


Catchwords:

Contract - Construction - Parent company guarantees provided by respondents in respect of performance of subcontractor's obligations under subcontract with appellant - Whether primary judge erred in holding that parent company guarantees did not require respondents to meet 'pay now, argue later' liability on the formation of a reasonable opinion that subcontractor failed to discharge liability under subcontract - Whether cl 3 of parent company guarantees provided provisional remedy or evinced purpose of risk allocation not subject to any defence, set‑off or counterclaim by respondents - Whether cl 3 of parent company guarantees covered payment obligations - Whether obligations of respondents under cl 3 of parent company guarantees ceased upon termination of subcontract - Turns on own facts

Legislation:

Nil

Result:

Appeal dismissed

Category:    B

Representation:

Counsel:

Appellant : S K Dharmananda SC, J Garas SC & R Collins
First Respondent : J Gleeson QC & P Thiagarajan
Second Respondent : J Gleeson QC & P Thiagarajan
Third Respondent : J Gleeson QC & P Thiagarajan

Solicitors:

Appellant : Clyde & Co (Perth Office)
First Respondent : Corrs Chambers Westgarth
Second Respondent : Corrs Chambers Westgarth
Third Respondent : Corrs Chambers Westgarth

Case(s) referred to in decision(s):

Andar Transport Pty Ltd v Brambles Ltd [2004] HCA 28; (2004) 217 CLR 424

Australian Broadcasting Commission v Australasian Performing Right Association Ltd [1973] HCA 36; (1973) 129 CLR 99

Bachmann Pty Ltd v BHP Power New Zealand Ltd [1998] VSCA 40; [1999] 1 VR 420

Black Box Control Pty Ltd v TerraVision Pty Ltd [2016] WASCA 219

Bofinger v Kingsway Group Ltd [2009] HCA 44; (2009) 239 CLR 269

Bowesco Pty Ltd v Westpoint Management Ltd [2015] WASCA 184; (2015) 109 ACSR 1

Clough Engineering Ltd v Oil and Natural Gas Corporation Ltd [2008] FCAFC 136; (2008) 249 ALR 458

CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd [No 2] [2017] WASCA 123

Dedert Corporation v United Dalby Bio-Refinery Pty Ltd [2017] VSCA 368

Dicom AWT Operations Pty Ltd v City of Stirling [2019] WASCA 117

Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd [2017] HCA 12; (2017) 261 CLR 544

EDWF Holdings 1 Pty Ltd v EDWF Holdings 2 Pty Ltd [2010] WASCA 78; (2010) 41 WAR 23

Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 251 CLR…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read JKC Australia LNG Pty Ltd v CH2M Hill Companies Ltd [No 2] and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2020] WASCA 112
Decision Date

CaseChat Overview and Summary

JKC Australia LNG Pty Ltd was the appellant and CH2M Hill Companies Ltd was the respondent in this case before the Full Court of the Federal Court of Australia. The dispute arose from the interpretation of parent company guarantees provided by the respondents in relation to the performance of a subcontractor's obligations under a subcontract with the appellant. The primary issue before the court was whether the parent company guarantees required the respondents to assume "pay now, argue later" liability upon forming a reasonable opinion that the subcontractor had failed to meet their obligations under the subcontract. The court also had to determine whether clause 3 of the parent company guarantees provided a provisional remedy, if it evinced a purpose of risk allocation not subject to any defence, set-off or counterclaim by the respondents, if it covered payment obligations, and whether the respondents' obligations under clause 3 ceased upon termination of the subcontract.

The court found that the purpose and object of the contractual provisions could be ascertained by considering the contractual provisions read as a whole and by understanding the surrounding circumstances. The court held that the purpose or object of contractual provisions is revealed by their text and structure and should be derived from what the contract says and not from any assumption about the desired or desirable reach of the operation of the relevant provisions. The court also held that the primary judge's approach to interpreting the parent company guarantees was incorrect, as the primary judge had adopted a narrow and pedantic approach to construction. The court held that a contract should be construed practically so as to give better effect to its commercial purpose, and the law seeks to uphold commercial contractual obligations and the expectations that derive from them.

The court found that the parent company guarantees did not require the respondents to meet "pay now, argue later" liability upon forming a reasonable opinion that the subcontractor had failed to meet their obligations under the subcontract. The court also found that clause 3 of the parent company guarantees did not provide a provisional remedy, did not evince a purpose of risk allocation not subject to any defence, set-off or counterclaim by the respondents, and did not cover payment obligations. Finally, the court held that the respondents' obligations under clause 3 ceased upon termination of the subcontract.

The court allowed the appeal, set aside the primary judge's decision, and remitted the matter to the primary judge for further consideration in light of the court's reasons. The court also ordered that the appellant pay the respondents' costs of the appeal.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established

Identification of the purposes or objects intended to be secured by a commercial contract will usually be inferred from the express or implied terms of the contractual instrument and any admissible evidence as to the surrounding circumstances.[92] Often it will be apparent from a consideration of the contractual provisions read as a whole. [93] In any case the purpose and object of a transaction is ascertained objectively by considering what a reasonable observer, in the situation of the parties, would conclude was the purpose and object.[94] Thus the purpose or object of contractual provisions is revealed by their text and structure. It should be derived from what the contract says and not from any assumption about the desired or desirable reach of the operation of the relevant provisions. However, extrinsic evidence may assist where the task is facilitated by an understanding of the genesis of the transaction, its background, the context and the market in which the parties are operating.[95][92] Olympic Holdings Pty Ltd v Windslow Corporation Pty Ltd (in liq) [2008] WASCA 80; (2008) 36 WAR 342 [41].[93] Black Box Control Pty Ltd v TerraVision Pty Ltd [42(3)].[94] Ryledar Pty Ltd v Euphoric Pty Ltd [2007] NSWCA 65; (2007) 69 NSWLR 603 [264]. See also at [265].[95] Electricity Generation Corporation v Woodside Energy Ltd [35]. In acknowledging the accepted wisdom that a commercial contract must be construed so as to avoid it making commercial nonsense or working commercial inconvenience it must also be kept in mind that reasonable minds might differ on business common sense.[96] Nevertheless it is accepted that: [I]f the language is open to two constructions, that will be preferred which will avoid consequences which appear to be capricious, unreasonable, inconvenient or unjust, 'even though the construction adopted is not the most obvious, or the most grammatically accurate' …[97][96] Black Box Control Pty Ltd v TerraVision Pty Ltd [42(9)].[97] Australian Broadcasting Commission v Australasian Performing Right Association Ltd (109). Where constructional choice is available it is important to consider what a reasonable business person reading the relevant clause or agreement would understand it to mean.[98] It is from that perspective that the court considers the circumstances surrounding the contract and the commercial purposes and objects to be achieved by it.[99][98] Sino Iron Pty Ltd v Mineralogy Pty Ltd [298].[99] Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [47]; Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd [16]. A contract should be construed practically so as to give better effect to its commercial purpose. The law seeks to uphold commercial contractual obligations and the expectations that derive from them. The court should not adopt a narrow or pedantic approach to construction, particularly in the case of commercial arrangements.[100] Before the primary judge, and again before this court, the parties referred to a number of decisions concerning the construction of specific performance bonds and guarantees, and also contracts providing for the recourse to such instruments. While the principles to be drawn from those authorities should be mentioned, none of the authorities are determinative. There are two general reasons why this is the case.