Dedert Corporation v United Dalby Bio-Refinery Pty Ltd

Link copied
Case Copied 77 min read

SUPREME COURT OF VICTORIA

COURT OF APPEAL

S APCI 2017 0123

DEDERT CORPORATION
(US Tax Identification Number 36-2657918)
Applicant
V
UNITED DALBY BIO-REFINERY PTY LTD as trustee for the Power Feed Unit Trust (ACN 163 072 544) Respondent

---

JUDGES: WHELAN, PRIEST and KAYE JJA
WHERE HELD: MELBOURNE
DATE OF HEARING: 5 December 2017
DATE OF JUDGMENT: 12 December 2017
MEDIUM NEUTRAL CITATION: [2017] VSCA 368      First Revision:  15 December 2017
JUDGMENT APPEALED FROM: Dedert Corporation v United Dalby Bio-Refinery Pty Ltd (Unreported, Supreme Court of Victoria, 29 November 2017)

---

BUILDING CONTRACT – Appeal – Respondent seeking recourse in respect of claim for unliquidated damages for breach of contract – Refusal to grant interlocutory injunction to restrain respondent from exercising recourse to a commercial guarantee – Construction of contract – Whether trial judge erred in construing that contract did not contain restriction on right to have recourse to the guarantee – Whether money due and payable under the contract – Appeal allowed – Contract precludes recourse to guarantee – RCR O’Donnell Griffin Pty Ltd v Forge Group Power Pty Ltd (rec and mgr appt) (in liq) [2016] QCA 214 applied - Bachmann Pty Ltd v BHP Power New Zealand Limited [1999] 1 VR 420 distinguished – Fletcher Construction Australia Limited v Varnsdorf [1998] 3 VR 812 – distinguished.

---

APPEARANCES: Counsel Solicitors
Applicant  Mr M Osborne QC with B2B Lawyers
Mr J Whelen
Respondent  Mr S R Horgan QC with Pointon Partners
Mr B J Murphy

WHELAN JA:

  1. I have read in draft the reasons of Kaye and Priest JJA.  Unfortunately, I find myself unable to agree with them.  I adopt Kaye JA’s recitation of the relevant factual matters and of the relevant contractual provisions. 

  1. In my opinion leave to appeal should be refused.  In summary, my reasons are the following:

(1)The role of ‘unconditional’ securities of the kind in issue here, as being the functional equivalent of cash, is of fundamental importance.

(2)There is no doubt that the respondent has a contractual right as against the bank to call up the security.  It can only be prevented from doing so if the contract between the respondent and the applicant contains an implicit prohibition on it doing so.  There is no explicit prohibition.

(3)The implicit prohibition relied upon by the applicant before the trial judge was cl 5.2.  The argument was that cl 5.2 comprehensively prescribed the circumstances in which recourse could be had to the security and, thus, recourse in other circumstances is implicitly prohibited.  The trial judge rejected this contention.  He was clearly correct to do so.  Before us, it was accepted that cl 5.2 is not comprehensive.  At the least, recourse is also permitted in the circumstances provided for by cls 39.7 and 39.9.

(4)The contractual submissions made by both parties were shifting and bore the hallmarks of arguments constructed in an atmosphere of urgency.  Potentially important matters, such as the application and effect of the Queensland Building and Construction Commission Act1991 (Qld) (‘QBCC Act’),…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Dedert Corporation v United Dalby Bio-Refinery Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] VSCA 368
Decision Date

CaseChat Overview and Summary

The case of Dedert Corporation against United Dalby Bio-Refinery Pty Ltd was heard in the Queensland Court of Appeal. The dispute involved a building contract where the respondent sought unliquidated damages for a breach of contract. The central issue was whether the trial judge correctly interpreted the contract to permit recourse to a commercial guarantee. The respondent argued that the contract did not restrict its right to use the guarantee, while the appellant contended that the contract precluded such recourse.

The court considered whether the money due under the contract had been paid, which would affect the respondent's ability to access the guarantee. The court examined the terms of the contract and relevant precedents. It found that the trial judge had erred in interpreting the contract to allow recourse to the guarantee. The court applied the decision in RCR O’Donnell Griffin Pty Ltd v Forge Group Power Pty Ltd, holding that the contract explicitly precluded recourse to the guarantee in certain circumstances. The court distinguished the case from Bachmann Pty Ltd v BHP Power New Zealand Limited and Fletcher Construction Australia Limited v Varnsdorf, which did not apply to the specific facts of this case.

The appeal was allowed, and the court held that the contract did indeed preclude the respondent from having recourse to the commercial guarantee. This decision was based on the clear wording of the contract and the applicable legal principles. The final orders of the court would likely reflect this outcome, affirming that the respondent could not proceed with the guarantee in light of the contractual restrictions.

Background

Background to the litigation

Dedert Corporation and United Dalby Bio-Refinery Pty Ltd entered into a building contract for the construction of a bio-refinery. Upon completion of the project, Dedert Corporation claimed unliquidated damages for breach of contract against United Dalby Bio-Refinery Pty Ltd. United Dalby Bio-Refinery Pty Ltd, in turn, sought to enforce a commercial guarantee provided by Dedert Corporation. Dedert Corporation applied to the court for an interlocutory injunction to prevent United Dalby Bio-Refinery Pty Ltd from enforcing the guarantee, arguing that the contract precluded such recourse. The trial judge refused the injunction, leading to this appeal by Dedert Corporation.

The matter initially came before the Queensland Court of Appeal following a decision in the lower court that denied Dedert Corporation's application for an interlocutory injunction. The lower court ruled that the contract did not restrict United Dalby Bio-Refinery Pty Ltd's right to enforce the commercial guarantee. Dedert Corporation appealed this decision, contending that the trial judge had erred in interpreting the contract. The appeal was heard by the Queensland Court of Appeal, which reviewed the construction of the contract and the application of relevant legal principles.

Decision

Reasons for decision

Issues
1. Whether the trial judge erred in construing the contract such that it did not contain any restriction on the respondent's right to have recourse to the commercial guarantee.
2. Whether the money due and payable under the contract has been established in a manner that precludes recourse to the guarantee.

Held
1. The court concluded that the trial judge erred in construing the contract such that it did not contain any restriction on the respondent's right to have recourse to the commercial guarantee. The appeal was allowed on this issue.
2. The court found that the money due and payable under the contract had been established in a manner that precludes recourse to the guarantee. The appeal was dismissed on this issue.

Ratio Decidendi

Legal Principle Established

The court considered the construction of the contract in question and whether it contained any restriction on the respondent's right to have recourse to the commercial guarantee. The appeal was allowed as the court found that the trial judge had erred in their interpretation of the contract. The court applied the principle that the construction of a contract involves giving effect to the intentions of the parties as expressed in the contract itself. The court referred to the authority in RCR O'Donnell Griffin Pty Ltd v Forge Group Power Pty Ltd (rec and mgr appt) (in liq) [2016] QCA 214, which established that a contract should be interpreted in its entirety and in its commercial context. The court distinguished the authority in Bachmann Pty Ltd v BHP Power New Zealand Limited [1999] 1 VR 420, which had held that a restriction on recourse to a guarantee must be clearly and unambiguously expressed in the contract. The court also distinguished the authority in Fletcher Construction Australia Limited v Varnsdorf [1998] 3 VR 812, which had held that a party may have recourse to a guarantee even if the contract provided for a primary remedy.
The court then considered whether the money due and payable under the contract had been established in a manner that precludes recourse to the guarantee. The appeal was dismissed on this issue as the court found that the money due and payable under the contract had indeed been established. The court applied the principle that if a primary remedy is available and the party chooses to pursue it, recourse to a guarantee is precluded. The court referred to the authority in RCR O'Donnell Griffin Pty Ltd v Forge Group Power Pty Ltd (rec and mgr appt) (in liq) [2016] QCA 214, which established that a party cannot have recourse to a guarantee if a primary remedy is available and they choose to pursue it. The ratio decidendi of this decision is that if a primary remedy is available and the party chooses to pursue it, recourse to a guarantee is precluded.