| IN THE SUPREME COURT OF VICTORIA AT MELBOURNE COMMERCIAL COURT | Not Restricted |
S ECI 2019 4613
BETWEEN:
| SIEMENS GAMESA RENEWABLE ENERGY PTY LTD (ACN 614 784 575) | Plaintiff |
| v | |
| BULGANA WIND FARM PTY LTD (ACN 162 201 569) and NEOEN AUSTRALIA PTY LTD (ACN 160 905 706) | Defendants |
---
JUDGE: | Digby J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 17 October 2019 |
DATE OF JUDGMENT: | 27 November 2019 |
CASE MAY BE CITED AS: | Siemens v Bulgana |
MEDIUM NEUTRAL CITATION: | [2019] VSC 771 |
---
PRACTICE AND PROCEDURE – Injunctive relief – Building and Engineering Contract – Application to restrain beneficiary of performance guarantee from calling on two unconditional bank guarantees – Serious issue to be tried – Consideration of whether appropriate to decide contract interpretation question as if on a final basis – Proper approach – Balance of convenience – Application for injunction dismissed.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr M Darke SC with Ms C Van Proctor | Clayton Utz |
| For the Defendants | Mr H Foxcroft QC with Mr J Gurr | White & Case |
HIS HONOUR:
Outline of SGRE’s Application
The plaintiff, Siemens Gamesa Renewable Energy Pty Ltd (SGRE) applies to restrain the first defendant, Bulgana Wind Farm Pty Ltd (BWF), from calling upon two unconditional bank guarantees (Performance Securities) issued in favour of BWF, in connection with an Engineering, Procurement and Construction Contract (EPC Contract) between the parties, pursuant to which SGRE is constructing a large wind farm for BWF in Victoria.
By Amended Originating Motion and Amended Summons, both dated 18 October 2019, SGRE seeks:
(a) an interlocutory injunction restraining BWF from making any demand under or pursuant to the Performance Securities pending any arbitral reference or until further order; and
(b) an order pursuant to s 8 of the Commercial Arbitration Act 2011 (Vic) that so much of these proceedings as involves the determination of a claim for final relief be stayed pending any arbitral reference between the parties.
Further, by its Amended Originating Motion, SGRE also claims alternative relief in the nature of a permanent injunction restraining BWF, via its employees, agents or otherwise, from making any demand, in relation to a disputed claim to Delay Liquidated Damages (DLDs) under the EPC Contract, under or pursuant to the Performance Securities.
SGRE has not pressed its claim for an order pursuant to s 8 of the Commercial Arbitration Act 2011 (Vic) save to argue that such relief remains available, even if no arbitral tribunal is relevantly in place[1] and has in relation to SGRE’s claim for an interlocutory injunction, taken the position that SGRE’s application should be tested on the basis of the identification of a serious question to be tried, and not finally determined as to the contract interpretation questions in issue on the basis that the court moves to make a determination, ‘as if’ on a final basis, in relation to the contract construction issues.
[1]Disposal of ancillary matters relating to ‘circularity’ (T54.1-15) and an order under s 8 of the Commercial Arbitration Act 2011
Continue reading Siemens v Bulgana
Sign in free to access the full text
- AGLC
- Siemens v Bulgana [2019] VSC 771
- Case
- [2019] VSC 771
- Decision Date
CaseChat Overview and Summary
The court found that it was not appropriate to decide the contract interpretation question on an interlocutory basis as if it were a final decision. The court held that it was necessary to consider the balance of convenience, which weighed in favour of the respondent, as there was a significant risk of prejudice to the respondent if the injunction were granted. The court noted that the proper approach required a careful consideration of the contract terms and the circumstances surrounding the provision of the bank guarantees. The court concluded that the balance of convenience did not favour granting the injunction.
The application for injunctive relief was dismissed. The court found that the applicant had not demonstrated a serious issue to be tried and that the balance of convenience did not favour the granting of the injunction. The court also held that it was not appropriate to decide the contract interpretation question on an interlocutory basis as if it were a final decision. This decision highlights the importance of considering the balance of convenience and the proper approach when deciding whether to grant injunctive relief in cases involving building and engineering contracts.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.