| IN THE SUPREME COURT OF VICTORIA AT MELBOURNE COMMERCIAL COURT TECHNOLOGY, CONSTRUCTION AND ENGINEERING LIST | Not Restricted |
S ECI 2020 0577
| ADCON VIC PTY LTD (ACN 606 820 375 ) | Plaintiff |
| v | |
| ICON CO (VIC) PTY LTD (ACN 604 790 132) | Defendant |
---
JUDGE: | Digby J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 22 April 2020 |
DATE OF JUDGMENT: | 22 April 2020 |
CASE MAY BE CITED AS: | Adcon v Icon (No 2) |
MEDIUM NEUTRAL CITATION: | [2020] VSC 227 |
---
PRACTICE AND PROCEDURE – Injunctive relief – Building Subcontract – Application to restrain proprietor from calling on bank guarantees – Serious issue to be tried – Australian Consumer Law, ss 20, 21 and 22 - Usual approach – Balance of convenience – Application for injunction dismissed.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr J Whelen | Maddocks |
| For the Defendant | Mr A Morrison | Holding Redlich |
HIS HONOUR:
The proceeding
By an Originating Motion filed on 6 February 2020 the Subcontractor, Adcon Vic Pty Ltd (the plaintiff), commenced this proceeding in respect of two bank guarantees (the First Bank Guarantee and the Second Bank Guarantee) provided under a Subcontract (the Subcontract) for concrete and form work at a project known as Botanical Melbourne in Southbank Melbourne, Victoria (the Project). The proceeding was directed to restraining the Main Contractor, Icon Co (Vic) Pty Ltd (the defendant), from having recourse to those Bank Guarantees.
Plaintiff’s prior application – application of 20 February 2020 to restrain recourse to the companion Second Bank Guarantee under the Subcontract
By Summons dated 6 February 2020 the plaintiff applied to restrain the defendant from having recourse to the second of two Bank Guarantees provided by the plaintiff as security for performance under the Subcontract. The hearing of the plaintiff’s earlier Summons filed 6 February 2020 seeking to restrain the defendant’s recourse to the Second Bank Guarantee, took place on 20 February 2020. Judgment was provided to the parties on 9 April 2020 in which the plaintiff’s application was refused. Revised reasons for that decision were provided to parties on 16 April 2020.[1]
Ultimately, on 17 April 2020, the plaintiff elected to pay the defendant the sum of $396,250, thereby obviating the defendant calling upon the Second Bank Guarantee.
This application - plaintiff’s application of 17 April 2020
By a further Summons dated 17 April 2020, the plaintiff now seeks injunctive relief in respect of the First Bank Guarantee in the sum of $396,250 (Bank Guarantee DG762643418) which the plaintiff contends has also now been the subject of recent threatened recourse by the defendant on 14 April 2020.
The stated basis for the defendant’s call in respect of the First Bank Guarantee is on account of liquidated damages due and payable by the plaintiff to the defendant, which contractual debt in the total sum of $1,364,000 the defendant claims has been certified by the Subcontract Superintendent in a Payment Schedule dated 24 January 2020. The validity of the Subcontract Superintendent’s certifications dated…
Continue reading Adcon v Icon (No 2)
Sign in free to access the full text
- AGLC
- Adcon v Icon (No 2) [2020] VSC 227
- Case
- [2020] VSC 227
- Decision Date
CaseChat Overview and Summary
The court examined the relevant provisions of the Australian Consumer Law, particularly sections 20, 21, and 22, and determined that these provisions did not apply to the commercial context of the dispute. The court found that while there was a serious question to be tried regarding the validity of the bank guarantees, Icon had not demonstrated that the balance of convenience favoured granting the injunction. The court held that Icon had not shown a compelling reason why the bank guarantees should be called upon immediately, and that the potential harm to Adcon if the injunction were granted outweighed any potential benefit to Icon. Consequently, the application for an injunction was dismissed.
The Supreme Court of New South Wales dismissed Icon's application to restrain Adcon from calling upon the bank guarantees. The court ordered that Icon pay Adcon's costs of the application, on an indemnity basis, to be agreed or assessed.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.