CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd [No 2]

Link copied
Case Copied 65 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

TITLE OF COURT  :   THE COURT OF APPEAL (WA)

CITATION:   CPB CONTRACTORS PTY LTD -v- JKC AUSTRALIA LNG PTY LTD [No 2] [2017] WASCA 123

CORAM:   BUSS P

MURPHY JA
BEECH JA

HEARD:   25 MAY 2017

DELIVERED          :   30 JUNE 2017

FILE NO/S:   CACV 45 of 2017

BETWEEN:   CPB CONTRACTORS PTY LTD

Appellant

AND

JKC AUSTRALIA LNG PTY LTD
Respondent

ON APPEAL FROM:

Jurisdiction              :  SUPREME COURT OF WESTERN AUSTRALIA

Coram  :LE MIERE J

Citation  :CPB CONTRACTORS PTY LTD -v- JKC AUSTRALIA LNG PTY LTD [2017] WASC 112

File No  :CIV 1453 of 2017

Catchwords:

Building and construction - Provision for performance bonds - Party entitled to have recourse to performance bonds to recover amounts that are payable by other party - Whether recourse not permitted when other party disputes that it is obliged to pay the amount - Proper construction of contract - Whether injunction should be granted restraining recourse

Words and phrases - Payable - Due and payable

Legislation:

Nil

Result:

Appeal dismissed

Category:    A

Representation:

Counsel:

Appellant:     Mr J A Thomson SC & Mr M R Collins

Respondent:     Mr S K Dharmananda SC & Mr T J Palmer & Mr T N Owen

Solicitors:

Appellant:     King & Wood Mallesons

Respondent:     DLA Piper Australia

Case(s) referred to in judgment(s):

Alcatel Australia Ltd v Scarcella [1998] NSWSC 483; (1998) 44 NSWLR 349

Amev‑UDC Finance Ltd v Austin [1986] HCA 63; (1986) 162 CLR 170

Anaconda Operations Pty Ltd v Fluor Daniel Pty Ltd [1999] VSCA 214

Australasian Conference Association Ltd v Mainline Constructions Pty Ltd (in liq) [1978] HCA 45; (1978) 141 CLR 335

Australis Media Holdings Pty Ltd v Telstra Corporation Ltd (1998) 43 NSWLR 104

Bachmann Pty Ltd v BHP Power New Zealand Ltd [1998] VSCA 40; [1999] 1 VR 420

Bateman Project Engineering Pty Ltd v Resolute Ltd [2000] WASC 284; (2000) 23 WAR 493

Beaufort Developments (NI) Ltd v Gilbert‑Ash NI Ltd [1998] 2 WLR 860

Brooks v Burns Philp Trustee Co Ltd [1969] HCA 4; (1969) 121 CLR 432

Clough Engineering Ltd v Oil & Natural Gas Corporation Ltd [2008] FCAFC 136; (2008) 249 ALR 458

Clyne v Deputy Commissioner of Taxation [1981] HCA 40; (1981) 150 CLR 1

EGL Management Services Pty Ltd v Northern SEQ Distributor-Retailer Authority [2011] NSWSC 1234

Fletcher Construction Australia Ltd v Varnsdorf Pty Ltd [1998] 3 VR 812

Geldof Metaalconstructie NV v Simon Carves Ltd [2010] EWCA Civ 667; (2010) 4 All ER 847

George 218 Pty Ltd v Bank of Queensland Ltd (No 2) [2016] WASCA 182

Griffin Energy Group Pty Ltd v ICICI Bank Ltd [2015] NSWCA 29; (2015) 317 ALR 395

Helou v Mulligan Pty Ltd [2003] NSWCA 92; (2003) 57 NSWLR 74

HJ Wigmore & Co Ltd v Rundle [1930] HCA 27; (1930) 44 CLR 222

Laing O'Rourke Australia Construction Pty Ltd v Kawasaki Heavy Industries Ltd [2017] NSWSC 541

Lucas Drilling…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd [No 2] and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] WASCA 123
Decision Date

CaseChat Overview and Summary

The case of CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd [No 2] involved a dispute between a subcontractor and a contractor regarding the interpretation of a performance bond clause in their contract. The subcontractor sought an injunction to prevent the contractor from calling on the performance bonds until the dispute between the parties was resolved. The matter was heard in the Federal Court of Australia.

The legal issue before the court was whether the subcontractor's right to have recourse to the performance bonds was conditional on the objective fact that an amount was payable on demand, or whether the contractor could call on the bonds without such a condition. The court also needed to determine whether an injunction should be granted to prevent the contractor from calling on the bonds until the dispute was resolved.

The court held that the subcontractor's right to call on the performance bonds was not conditional on the objective fact that an amount was payable on demand. The court reasoned that the structure of the subcontract, the language of the guarantee clause, and the nature of the guarantee itself all supported the view that the contractor's entitlement to call on the bonds was not subject to such a condition. The court also found that an injunction should not be granted because it would interfere with the contractor's right to seek security under the performance bonds.

The court's decision was based on a careful analysis of the language and structure of the guarantee clause, as well as the nature of performance bonds in the construction industry. The court rejected the subcontractor's argument that the guarantee clause was subject to a condition that an amount be payable on demand, finding instead that the clause provided for unconditional guarantees that could be called upon by the contractor without the need for a determination that an amount was actually and indisputably payable. The court also found that an injunction would be an inappropriate remedy in this case, as it would interfere with the contractor's right to seek security under the performance bonds.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

His Honour outlined the approaches taken in Clough Engineering Ltd v Oil & Natural Gas Corporation Ltd,[28] and in Lucas Stuart Pty Ltd v Hemmes Hermitage Pty Ltd.[29] The primary judge observed that in Lucas Stuart, the court took as a starting point the existence of only the purpose of providing security in the event of insolvency of the contractor and looked for indications that might support the possible second purpose, namely to be a risk allocation device pending determination of the dispute between the parties. In Clough Engineering, the court gave weight to the nature of performance bonds as an unconditional undertaking and the importance of such bonds in the construction industry, and presumed that both purposes were intended unless expressly qualified.[30][28] Clough Engineering Ltd v Oil & Natural Gas Corporation Ltd [2008] FCAFC 136; (2008) 249 ALR 458.[29] Lucas Stuart Pty Ltd v Hemmes Hermitage Pty Ltd [2010] NSWCA 283; (2010) 5 BFRA 76.[30] Primary reasons [72]. On appeal, the subcontractor does not criticise his Honour's analysis of the cases, but points out, correctly, that his Honour did not identify which of the two approaches he preferred. His Honour then turned to the central question of the proper construction of GC 35.3(a). His Honour gave the following reasons for rejecting the subcontractor's contention that the contractor's right to call on the Bank Guarantees is conditioned upon the objective fact that an amount is payable on demand. First, the structure of the Subcontract is inconsistent with the contractor only having the right to demand payment of an amount if the amount is actually and indisputably payable. GC 35 is found in ch V, the subject matter of which is Financial Conditions of the Subcontract. The settlement of disputes is dealt with in GC 57, found in ch XI.[31][31] Primary reasons [74]. Secondly, GC 35 provides, in its introductory component, that the subcontractor agrees to provide irrevocable guarantees 'payable on first demand of Contractor'. The primary judge found that a first demand guarantee is, by its nature, a guarantee that must be honoured by the guarantor and upon the beneficiary's demand. The purpose of such a guarantee would be defeated if the beneficiary were required to establish by an arbitration award or court judgment or some other means that the amount demanded was actually and indisputably payable.[32][32] Primary reasons [75]. Next, his Honour found that the form of the guarantee militates against the subcontractor's construction. The bank's obligation is unconditional. It arises without proof of any breach and notwithstanding any contest or dispute by the subcontractor. Thus, both parties know that the bank's obligation is to pay despite any disputes between the parties. Further, the contractor is not required to notify the subcontractor before making demand to the bank and the bank may not notify the subcontractor before satisfying the demand. The primary judge found that the essence of such notice provisions reinforced the conclusion that the contractor's entitlement to call on the Bank Guarantees was not conditional upon it being established that the amount demanded is actually and indisputably payable.[33][33] Primary reasons [76].