CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd [No 3]

Link copied
Case Copied 22 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

TITLE OF COURT :   THE COURT OF APPEAL (WA)

CITATION:   CPB CONTRACTORS PTY LTD -v- JKC AUSTRALIA LNG PTY LTD [No 3] [2017] WASCA 132

CORAM:   BUSS P

MURPHY JA
BEECH JA

HEARD:   6 JULY 2017

DELIVERED          :   6 JULY 2017

PUBLISHED           :  11 JULY 2017

FILE NO/S:   CACV 45 of 2017

BETWEEN:   CPB CONTRACTORS PTY LTD

Appellant

AND

JKC AUSTRALIA LNG PTY LTD
Respondent

ON APPEAL FROM:

Jurisdiction              :  SUPREME COURT OF WESTERN AUSTRALIA

Coram  :LE MIERE J

Citation  :CPB CONTRACTORS PTY LTD -v- JKC AUSTRALIA LNG PTY LTD [2017] WASC 112

File No  :CIV 1453 of 2017

Catchwords:

Practice and procedure - Appeals - Application for injunction pending application for special leave to appeal - Turns on own facts

Legislation:

Nil

Result:

Application dismissed

Category:    B

Representation:

Counsel:

Appellant:     Mr J A Thomson SC & Mr M R Collins

Respondent:     Mr S K Dharmananda SC & Mr T J Palmer

Solicitors:

Appellant:     King & Wood Mallesons

Respondent:     DLA Piper Australia

Case(s) referred to in judgment(s):

Anaconda Operations Pty Ltd v Fluor Daniel Pty Ltd [1999] VSCA 214

Apple and Pear Australia Ltd v Pink Lady America LLC (No 2) [2017] VSCA 10

Bachmann Pty Ltd v BHP Power New Zealand Ltd [1998] VSCA 40; [1999] 1 VR 420

Black Box Control Pty Ltd v Terravision Pty Ltd [2016] WASCA 219

Clough Engineering Ltd v Oil & Natural Gas Corporation Ltd [2008] FCAFC 136; (2008) 249 ALR 458

CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd [2017] WASCA 85

CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd [No 2] [2017] WASCA 123

Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd [2017] HCA 12; (2017) 91 ALJR 486

Erinford Properties Ltd v Cheshire County Council [1974] 1 Ch 261

Fletcher Construction Australia Ltd v Varnsdorf Pty Ltd [1998] 3 VR 812

Jennings Construction Ltd v Burgundy Royale Investments Pty Ltd (No 1) [1986] HCA 84; (1986) 161 CLR 681

Mercanti v Mercanti [2017] HCA 1; (2017) 91 ALJR 258

Nugawela v Deputy Commissioner of Taxation [No 2] [2017] WASCA 66

Obeid v The Queen [2016] HCA 9; (2016) 90 ALJR 447

Odzic v Commonwealth of Australia (as represented by the Department of Infrastructure and Regional Development) [2017] FCA 439

Paringa Mining & Exploration Company PLC v North Flinders Mines Ltd [1988] HCA 53; (1988) 165 CLR 452

Rinehart v Welker [2012] NSWCA 1; (2012) 83 NSWLR 347

Smith Kline & French Laboratories (Australia) Ltd v Secretary to the Department of Community Services and Health [1991] HCA 13; (1991) 65 ALJR 360

Tey v Michael Mischin MLC, Attorney General for Western Australia [No 2] [2015] WASCA 243

REASONS OF THE COURT: 

Introduction

  1. On 30 June 2017, this court dismissed CPB's appeal from the decision of the primary judge dismissing its application for an interlocutory injunction restraining JKC from demanding payment under the performance bonds…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd [No 3] and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] WASCA 132
Decision Date

CaseChat Overview and Summary

In the case of CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd, the court was presented with an appeal concerning the interpretation of contractual provisions within a Subcontract. The central issue revolved around the interpretation of certain clauses in the Subcontract and their interaction, particularly focusing on the enforceability of an arbitration clause in the context of a performance bond. CPB Contractors, the appellant, argued that the court had erred in its interpretation of the clauses and that the court should not have considered certain provisions in its analysis. The legal issues included the proper construction of the contractual clauses, the relevance of the performance bond in interpreting the Subcontract, and the court's consideration of provisions found to be contrary to public policy.

The court, in its decision, clarified that while GC 35.3(b) was found to be contrary to public policy, it was permissible to consider it in the context of interpreting GC 35.3(a). The court noted that the interpretation of GC 35.3(a) remained consistent whether or not GC 35.3(b) was taken into account. The court rejected CPB Contractors' argument that the consideration of GC 35.3(b) in interpreting GC 35.3(a) was erroneous, pointing to existing appellate authority supporting this approach. The court also addressed CPB Contractors' concern regarding the weight given to the performance bond in interpreting the Subcontract, noting that the performance bond's terms were appropriately considered given the Subcontract's approval of its form. The court concluded that CPB Contractors' arguments on appeal did not provide a basis for granting special leave to appeal.

The court ultimately dismissed the appeal, reaffirming the correctness of its earlier interpretation of the Subcontract provisions. The court found no basis for special leave to appeal, as CPB Contractors' arguments did not sufficiently demonstrate error in the court's interpretation or the necessity for broader appellate guidance. The court's decision stood as it did not find any material error in the construction of the contractual provisions, nor did it consider the arguments sufficient to warrant further appellate review.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

CPB's first point is that this court erred in having regard to GC 35.3(b) in construing GC 35.3(a), in circumstances where the primary judge had found that GC 35.3(b) was contrary to public policy and this court did not conclude otherwise. CPB's case on appeal would be that this court erred in finding that if GC 35.3(b) is unenforceable as an ouster of the jurisdiction of the court, it is nevertheless permissible to take it into account in construing GC 35.3(a).[21] CPB accepts that the approach taken by this court is supported by appellate authority: Anaconda Operations Pty Ltd v Fluor Daniel Pty Ltd.[22] CPB did not suggest that there are any authorities taking a contrary approach. In any event, as CPB accepted,[23] and as we explained in our reasons,[24] if the construction task is undertaken without regard to GC 35.3(b), we construe GC 35.3(a) in the same fashion as we do having regard to GC 35.3(b). Consequently, success on the part of CPB in relation to its proposed first special leave question would not alter the result, unless CPB also succeeded in relation to its proposed second special leave question. [21] Appeal reasons [94] - [97].[22] Anaconda Operations Pty Ltd v Fluor Daniel Pty Ltd [1999] VSCA 214 [15].[23] CPB's submissions [19], appeal ts 159.[24] Appeal reasons [93], [98]. Counsel for CPB accepted that this was so. He said that it would be necessary for CPB to succeed either on both its special leave questions, or on the proposed second special leave question standing alone.[25] We would venture to suggest that it would be necessary for CPB to succeed in respect of both its proposed special leave questions. It would seem difficult to contemplate CPB succeeding in relation to the construction of GC 35.3(a) without demonstrating that GC 35.3(b) must be disregarded. That is because, as we observed in our reasons,[26] par (b) of GC 35.3 would serve no discernible purpose if GC 35.3(a) were construed as CPB contends, a point accepted by CPB.[27][25] Appeal ts 159.[26] Appeal reasons [91].[27] Appeal ts 99 - 100. We turn to CPB's second point in relation to the prospects of the grant of special leave.[28] In oral submissions, CPB clarified that this point was subsidiary to and fed into CPB's second proposed special leave question; it was not said to raise a special leave question in itself.[29] As we explained in our reasons,[30] we did not consider this appeal was an occasion to attempt to state general principles of broad application or to resolve any apparent differences in emphasis in other appellate decisions. Rather, the resolution of the appeal lay in the proper construction of the provisions of the Subcontract. CPB accepted that when, as was the case here, the Subcontract annexes and approves the form of the performance bond, in construing the terms of the Subcontract, the unconditional nature of the performance bond, and its terms generally can be taken into account.[31] The passage of our reasons to which CPB points is expressed in terms that the agreed proforma document 'tends to confirm' the construction which we adopted. CPB's submissions did not explain how or why that involved giving excessive or impermissible weight to the terms of the performance bond. [28] See [5(2)(b)].[29] Appeal ts 162.[30] Appeal reasons [88].[31] Appeal ts 61, 68.