IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2024-404-273
[2024] NZHC 561
BETWEEN HAWKINS LIMITED
Plaintiff
AND
ELIZABETH PROPERTIES LIMITED
Defendant
Hearing: 28 February 2024 Appearances:
D J Cooper KC and J P Bell-Connell for the Plaintiff J Carlyon and Y Fu for the Defendant
Judgment:
15 March 2024
JUDGMENT OF GAULT J
(Application for interim injunction)
This judgment was delivered by me on 15 March 2024 at 4:00 /pm pursuant to r 11.5 of the High Court Rules 2016.
Registrar/Deputy Registrar
……………………………………
Solicitors / Counsel:
Mr D Cooper KC, Barrister, Auckland
Ms K Van Houtte and Mr J Bell-Connell, Dentons Kensington Swan, Auckland and Wellington Ms J Carlyon and Ms Y Fu, Meredith Connell, Auckland
HAWKINS LTD v ELIZABETH PROPERTIES LTD [2024] NZHC 561 [15 March 2024]
[1] Hawkins Ltd (Hawkins) seeks an interim injunction to restrain Elizabeth Properties Ltd (EPL) from calling on a $3 million contractor’s bond provided by ANZ Bank New Zealand Ltd (ANZ) as surety for Hawkins (the Bond1) pending determination of a liquidated damages (LDs) dispute due in April in a current Construction Contracts Act 2002 (CCA) adjudication.
Factual background
[2] The Elizabeth Street Development in Tauranga (the development) is a mixed commercial and residential site comprising retail, a food and beverage dining precinct, 97 apartments and 23 luxury townhouses.
[3] On 23 August 2019, EPL and Hawkins entered into a construction contract for construction of the development (the contract). The contract was based on NZS3910:2013 with special conditions added. The contract was for a fixed lump sum amount of $148,921,526.45 (plus GST, if applicable), subject to any adjustment in accordance with the contract. The contract divided the work into seven separable portions (SPs).
[4] Key components of the contract (which I address in more detail below) included:
(a)the appointment of an Engineer to the contract (the Engineer) (cl 6);
(b)for LDs to be paid if an access date or date of practical completion “is achieved later than the corresponding due date” (cl 10.5.1);
(c)the Bond (cl 3); and
(d)a disputes regime (cl 13), supplemented by the CCA adjudication regime.
1 Date of Issue 9 October 2019, Guarantee Number GO376731166.
[5] By early 2021, the development was significantly delayed. On 25 March 2021, the parties entered into a programme reset settlement agreement (reset agreement) to give both parties a clear understanding of programme and financial positions to see the project to a successful completion.
[6] However, there were further delays. In addition, following the reset agreement a dispute arose in relation to the validity and applicability of LDs under the contract.
[7] On 15 November 2022, Hawkins issued a notice of adjudication under the CCA. The adjudication proceedings relate to the LDs applied by EPL as a deduction to payment claim 48 in October 2022. In the adjudication proceedings, Hawkins seeks the following determinations:
(a)EPL’s claims for LDs fail for uncertainty following the reset agreement because the reset agreement does not address LDs, such…
Keep reading for free
Create a free CaseChat account to read Hawkins Limited v Elizabeth Properties Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NZHC 561
- Decision Date
CaseChat Overview and Summary
Hawkins commenced this proceeding, applying for an interim injunction to restrain EPL from calling on the bond pending resolution of the adjudication. The key legal issues were whether there was a serious question to be tried that EPL was not entitled to call on the bond and, if so, whether the balance of convenience favoured granting interim relief. The court considered that the contract terms and the actions of EPL and the Engineer gave rise to a serious question to be tried that EPL was not lawfully entitled to call upon the bond. The combination of the contract terms, the actions of EPL and the Engineer, and the Engineer’s certificate raised questions about the reasonableness of the certificate and whether EPL ensured that the Engineer acted reasonably. As for the balance of convenience, the court found that damages would not be an adequate remedy for Hawkins due to the potential reputational harm of a call on the bond, and interim relief was necessary to preserve the status quo pending the adjudicator’s determination of the LDs dispute in April 2024.
In conclusion, the court made an interim order restraining EPL from calling on the bond pending the adjudicator’s determination of the LDs dispute in April 2024, irrespective of the outcome of that determination.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi