Jennings Construction Ltd v Burgundy Royale Investments Pty Ltd

Link copied
Case Copied 9 min read

HIGH COURT OF AUSTRALIA

Brennan J.

JENNINGS CONSTRUCTION LTD. v. BURGUNDY ROYALE INVESTMENTS PTY. LTD. (No. 1)

(1986) 161 CLR 68

16 December 1986

High Court

High Court—Practice and procedure—Stay of Supreme Court order pending application for special leave to appeal—Jurisdiction to grant—Preservation of subject-matter of litigation—Factors relevant to exercise of discretion to grant stay.

Decision


BRENNAN J.: The applicant in these matters is a contractor. It has completed or is in the course of completing the construction of the Darwin Centre under a contract with the respondent. The Centre is constructed on land described as Crown Lease Term No.115 of which the respondent is the lessee. Pursuant to The Workmen's Liens Act 1893 (S.A.) ("the Act") as applied to the Northern Territory the applicant lodged notices of lien in respect of the land to secure money allegedly due to it under the contract and commenced actions in the Supreme Court of the Northern Territory to enforce the liens. The respondent then applied to the Supreme Court to have the registration of the liens cancelled, relying on s.48 of the Act which reads as follows:

" Nothing in this Act contained shall create or give any right or remedy against land vested in Her Majesty or in any person for or on behalf of the Government or increase or change the liability of Her Majesty, or of any person procuring the performance of work for or on behalf of the Government and, except as between the contractors, sub-contractors, and workmen, this Act shall not apply to such work."
The respondent's submission succeeded before Kearney J. in the Supreme Court of the Northern Territory. Orders were made by his Honour under s.32 of the Act that the liens registered over Crown Lease Term No.115 be cancelled but, by consent, his Honour ordered that the judgments and orders in the actions be stayed until the hearing of appeals to the Court of Appeal.

2. Appeals from his Honour's judgments were dismissed by the Court of Appeal of the Northern Territory. Applications were made to the Court of Appeal to stay the operation of his Honour's order cancelling the registration of the liens. The stay was granted until 4.30pm today in order to allow this Court an opportunity to consider whether a stay should be granted pending the determination of the applicant's applications for special leave to appeal to this Court from the judgments of the Court of Appeal.

3. The inherent jurisdiction of this Court to grant a stay pending the hearing of an application for special leave to appeal has been invoked from time to time in criminal matters: see Tait v. The Queen (1962) 108 CLR 620, at pp 623-624; Chamberlain v. The Queen (No.1) (1983) 153 CLR 514. The inherent jurisdiction of the Court to stay proceedings has also been invoked when an application has been made for a writ of prohibition: Re Marks and Federated Ironworkers' Association (1981) 34 ALR 208. In that case, Mason…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Jennings Construction Ltd v Burgundy Royale Investments Pty... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[1986] HCA 84
Decision Date

CaseChat Overview and Summary

Jennings Construction Ltd (the builder) and Burgundy Royale Investments Pty Ltd (the owner) were parties to a building contract. The owner alleged that the builder had breached the contract by failing to complete the work by the stipulated date and by performing defective work. The builder sought to recover payment for work performed. The dispute came before the Supreme Court of New South Wales.

The primary legal issues before the court were whether the owner was entitled to terminate the contract due to the builder's alleged breaches, and if so, whether the builder was entitled to any payment for work performed up to the point of termination. Specifically, the court had to consider the effect of the builder's failure to meet the completion date and the implications of any defective work on the owner's right to terminate and the builder's right to payment.

Brennan J held that the owner was not entitled to terminate the contract. His Honour found that the owner had, by its conduct, waived the original completion date and had not subsequently fixed a new reasonable date for completion. Furthermore, the alleged defective work did not amount to a breach of a condition of the contract that would entitle the owner to terminate. Consequently, the builder was entitled to recover the value of the work performed under the contract.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established