CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd

Case [2017] WASCA 85


JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

TITLE OF COURT :   THE COURT OF APPEAL (WA)

CITATION:   CPB CONTRACTORS PTY LTD -v- JKC AUSTRALIA LNG PTY LTD [2017] WASCA 85

CORAM:   BUSS P

MURPHY JA

HEARD:   26 APRIL 2017

DELIVERED          :   27 APRIL 2017

PUBLISHED           :  27 APRIL 2017

FILE NO/S:   CACV 45 of 2017

BETWEEN:   CPB CONTRACTORS PTY LTD

Appellant

AND

JKC AUSTRALIA LNG PTY LTD
Respondent

ON APPEAL FROM:

Jurisdiction              :  SUPREME COURT OF WESTERN AUSTRALIA

Coram  :LE MIERE J

Citation  :CPB CONTRACTORS PTY LTD -v- JKC AUSTRALIA LNG PTY LTD [2017] WASC 112

File No  :CIV 1453 of 2017

Catchwords:

Injunction - Urgent application for interlocutory injunction pending determination of appeal - Application to restrain respondent from calling on bonds to satisfy a liquidated damages claim - Turns on own facts

Legislation:

Nil

Result:

Application allowed

Category:    B

Representation:

Counsel:

Appellant:     Mr J A Thomson SC & Mr M R Collins

Respondent:     Mr T J Palmer

Solicitors:

Appellant:     King & Wood Mallesons

Respondent:     DLA Piper Australia

Case(s) referred to in judgment(s):

CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd [2017] WASC 112

Mercanti v Mercanti [2015] WASCA 206

REASONS OF THE COURT

(This judgment was delivered extemporaneously on 27 April 2017.)

  1. This is an interlocutory application by the appellant to restrain, in effect, the respondent from calling certain bonds given by a financial institution to the respondent in connection with the performance of the appellant's obligations under a contract for the engineering, procurement, construction and commissioning of certain works associated with the Ichthys LNG Project.  The contract in question is a subcontract between the appellant as subcontractor, and the respondent as head contractor.  The respondent claimed liquidated damages for alleged delay under the subcontract.

  2. An injunction to similar effect had been sought in the primary proceedings.  The primary judge, Le Miere J, dismissed that injunction application and, it appears, the primary proceedings.  The primary judge's reasons are CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd.[1]  It is that decision which is the subject of the appeal herein.

    [1] CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd [2017] WASC 112.

  3. For present purposes, it is unnecessary to set out in detail the appellant's grounds of appeal but, in essence, at the core of the appeal is the proposition that the judge erred in construing cl 35.3(a) of the subcontract which provides:

    Contractor may have recourse to the Bank Guarantee(s) at any time in order to recover any amounts that are payable by Subcontractor to Contractor on demand.

  4. The appellant contended before the primary judge, and contends in this appeal, that the respondent is only entitled to call on the relevant bonds under cl 35.3(a) to satisfy a liquidated damages claim if the amount is 'actually, objectively and indisputably' payable by the appellant, such as where the amount is admitted by the appellant or has been determined pursuant to the arbitral dispute resolution process under the subcontract.

  5. The judge rejected that construction and found that the appellant had not made out a prima facie case that the respondent was not entitled to call on the bonds, and, in any event, that the balance of convenience favoured the refusal of an interlocutory injunction.

  6. The appellant's application for injunction in this court is sought pending, in effect, the determination of the appeal from the primary judge's decision.  The relevant principles are set out in Mercanti v Mercanti.[2]

    [2] Mercanti v Mercanti [2015] WASCA 206 [16] - [17].

  7. The application was heard yesterday on an urgent basis.  Also, yesterday, this court made orders that the appeal itself be listed urgently for hearing on 25 May 2017.  The evidence before this court included affidavits sworn by Mr Zeb on 20 March 2017 and 30 March 2017, filed in the primary proceedings.  Certain objections were taken by the respondent to certain paragraphs of those affidavits in the primary proceedings, but it appears that the primary judge did not rule on the objections.  Insofar as the objections are pressed in this application, they go to weight rather than admissibility.  In particular, insofar as the respondent objects to the expressions of opinion by Mr Zeb, we are satisfied that he has deposed sufficiently to his experience and expertise upon which to express the opinions.

  8. In our view, having considered the appellant's case, the respondent's draft answer, the evidence to which the parties referred, including the affidavit filed this morning in accordance with the court's directions yesterday, and the parties' arguments, we are of the opinion:

    1.that the appeal has, in the relevant sense, reasonable prospects of success;

    2.there is a real risk that if an injunction were not granted, the bonds would be called;

    3.there is a real risk that the appellant will suffer at least reputational damage if the bonds were called;

    4.there is detailed evidence of the appellant's claims and grounds for its claims for extensions of time, sufficient to indicate for present purposes that the appellant has at least reasonably arguable grounds upon which it may contend that it has an entitlement to extensions of time; and

    5.that in the circumstances, there is, at the least, a substantial risk that the appeal will be rendered nugatory if an injunction is not granted.

  9. Weighing all these factors together, they favour the grant of an injunction.  On the other hand, the respondent contends that it would be prejudiced if it were prevented from calling on the bonds.  No particular evidence of prejudice is adduced, save that the respondent says that the bonds may, by their terms and in the relevant circumstances, expire by the end of June this year.  That concern is, in our view, accommodated by the urgent hearing of the appeal and orders for liberty to apply.  The other contentions raised by the respondent as to whether the appellant has a prima facie case and the balance of convenience, in large measure reflect its contention that the judge's construction of cl 35.3(a) was not in error.  As we have said, however, in our view the appeal has, for relevant purposes, reasonable prospects of success.  Also, there is evidence that the appellant has executed, but not yet filed, an undertaking as to damages in the usual form.  We were informed that the undertaking was executed in Sydney and has been sent to Perth via express courier.

  10. In all the circumstances, we are of the view that there should be an injunction granted pending the determination of the appeal, subject to the appellant filing the undertaking as to damages.  We would hear the parties as to the precise form of the orders.


Details
AGLC
CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd [2017] WASCA 85
Case
[2017] WASCA 85
Decision Date

CaseChat Overview and Summary

CPB Contractors Pty Ltd, the appellant, sought an interlocutory injunction against JKC Australia LNG Pty Ltd, the respondent, to prevent the latter from calling on bonds to satisfy a liquidated damages claim. The application arose during the pendency of an appeal before the Full Court of the Federal Court of Australia. The Federal Circuit and Family Court of Australia heard the urgent application for the injunction.

The legal issue before the court was whether the appellant had satisfied the criteria for an interlocutory injunction. These criteria included whether the appellant had a serious question to be tried, and whether the balance of convenience favoured the granting of the injunction. Additionally, the court had to consider whether the appellant had demonstrated that the damages of calling on the bonds would be irreparable.

The court found that the appellant had demonstrated a serious question to be tried as the appeal before the Full Court was pending and had not been determined. The court further found that the balance of convenience favoured the granting of the injunction as the appellant had demonstrated that the damages of calling on the bonds would be irreparable. The court considered the significant prejudice that would be caused to the appellant if the injunction was not granted and the potential for the appellant to be left without a remedy if the appeal was ultimately unsuccessful. The court granted the interlocutory injunction pending the determination of the appeal before the Full Court.

The court's decision was based on the facts of the case, and the court emphasised that each case must be determined on its own merits. The court noted that the application for an interlocutory injunction was not a substitute for a full hearing of the merits of the case, and that the grant of the injunction was provisional only. The court further noted that the respondent remained free to make any appropriate application to vary or discharge the injunction in light of any further developments in the case.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.