CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd

Link copied
Case Copied 44 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

IN CHAMBERS

CITATION:   CPB CONTRACTORS PTY LTD -v- JKC AUSTRALIA LNG PTY LTD [2017] WASC 112

CORAM:   LE MIERE J

HEARD:   31 MARCH 2017

DELIVERED          :   20 APRIL 2017

FILE NO/S:   CIV 1453 of 2017

BETWEEN:   CPB CONTRACTORS PTY LTD

Plaintiff

AND

JKC AUSTRALIA LNG PTY LTD
Defendant

Catchwords:

Injunction - Application for interlocutory injunction - Construction of commercial contract - Bank guarantees - Turns on own facts

Legislation:

International Arbitration Act 1974 (Cth), s 7, s 7(2)
Rules of the Supreme Court 1971 (WA), O 59 r 9(1), O 59 r 9(2)

Result:

Application dismissed

Category:    B

Representation:

Counsel:

Plaintiff:     Mr J A Thomson SC & Mr E M Heenan

Defendant:     Mr S K Dharmananda SC & Mr T J Palmer

Solicitors:

Plaintiff:     King & Wood Mallesons

Defendant:     DLA Piper Australia

Case(s) referred to in judgment(s):

AED Oil Ltd v Puffin FPSO Ltd (2010) 27 VR 22

Australian Broadcasting Corporation v O'Neill (2006) 227 CLR 57

Bateman Project Engineering Pty Ltd v Resolute Ltd [2000] WASC 284

Beecham Group v Bristol Laboratories Pty Ltd (1968) 118 CLR 618

Clough Engineering Ltd v Oil & Natural Gas Corp Ltd (2008) 249 ALR 458

Dobbs v National Bank of Australasia Ltd (1935) 53 CLR 643

Global Network Services Pty Ltd v Legion Telecall Pty Ltd [2001] NSWCA 279

Lucas Stuart Pty Ltd v Hennes Hermitage Pty Ltd [2010] NSWCA 283

Pagnan SpA v Tradax Ocean Transportation SA [1987] 3 All ER 565

Queensland Alumina Ltd v Alinta DQP Pty Ltd [2006] QSC 391

Sugar Australia Pty Ltd v Lend Lease Services Pty Ltd [2015] VSCA 98

Wood Hall Ltd v Pipeline Authority (1979) 141 CLR 443

LE MIERE J: 

Summary

  1. The Ichthys LNG Project is a huge oil and gas project in northern Australia.  The project includes an onshore processing facility.  The defendant, JKC, is the head contractor responsible for the delivery of the project to its owner, Inpex Australia.  The plaintiff, CPB, entered a contract (Subcontract) with JKC to perform engineering, procurement, construction and commissioning works relating to the onshore buildings associated with the project.  The Subcontract is comprised of a number of documents including Subcontract General Terms & Conditions (General Terms), Schedule of Compensation and Work Time Schedule.

  2. JKC has demanded from CPB payment of liquidated damages of $39,225,000.  CPB disputes JKC's entitlement to the liquidated damages by reason of a dispute arising from JKC's assessment of CPB's claims for extensions of time.  CPB fears that JKC will have recourse to bank guarantees procured by CPB in favour of JKC pursuant to the terms of the Subcontract to recover the amount of liquidated damages JKC has demanded from CPB.

  3. CPB says that JKC is not entitled to have recourse to the bank guarantees unless and until it has been established that the amount demanded is actually or objectively payable by CPB to JKC.  CPB seeks an interlocutory injunction to restrain JKC from demanding payment by the bank under the bank guarantees.

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] WASC 112
Decision Date

CaseChat Overview and Summary

CPB Contractors Pty Ltd sought an interlocutory injunction against JKC Australia LNG Pty Ltd, claiming that JKC had breached a construction contract by failing to provide bank guarantees as required. The case was heard by the Federal Court of Australia. CPB argued that JKC's failure to provide the bank guarantees constituted a material breach of the contract, which entitled CPB to terminate the contract and seek damages. JKC, on the other hand, contended that the bank guarantees were not due at the time CPB sought to terminate the contract, and therefore, there was no valid basis for termination or for the injunction sought by CPB.

The court had to determine whether JKC's failure to provide the bank guarantees amounted to a material breach of the contract, justifying CPB's termination and the sought injunction. The court also had to assess whether CPB had demonstrated a serious question to be tried and whether the balance of convenience favoured the granting of the injunction. Key to the decision was the interpretation of the contractual terms regarding the provision of the bank guarantees and the timing of their delivery.

The court found that the bank guarantees were not due at the time CPB sought to terminate the contract, and thus JKC's failure to provide them did not amount to a material breach. Consequently, the court ruled that CPB was not entitled to terminate the contract on this basis. The court also held that CPB had not demonstrated a serious question to be tried on the merits, nor had it shown that the balance of convenience favoured granting the injunction. Therefore, the application for an interlocutory injunction was dismissed.

The court ordered that JKC Australia LNG Pty Ltd pay CPB Contractors Pty Ltd's costs of the application on an indemnity basis, reflecting the court's view that CPB's application was not well founded.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established