SUPREME COURT OF SOUTH AUSTRALIA
(Full Court)
COMMERCIAL & GENERAL CORPORATION PTY LTD v MANASSEN HOLDINGS PTY LTD & ANOR
[2021] SASCFC 40
Judgment of the Full Court
(The Honourable Justice Stanley, the Honourable Justice Nicholson and the Honourable Justice Livesey)
24 September 2021
APPEAL AND NEW TRIAL
CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION OF CONTRACTS
CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION OF CONTRACTS - INTERPRETATION OF MISCELLANEOUS CONTRACTS AND OTHER MATTERS
ESTOPPEL - ESTOPPEL BY CONDUCT - PROMISSORY ESTOPPEL - GENERAL PRINCIPLES
On 10 September 2016, the parties entered into an Underwriting Agreement. Pursuant to that agreement, the respondents (the plaintiffs) agreed to subscribe for units in a unit trust of which the appellant (the defendant) was the trustee, subject to the satisfaction of certain conditions precedent. The maximum value of the units for which the plaintiffs may have been required to subscribe was $40 million.
The commercial purpose of the Underwriting Agreement was to enable the defendant to have access to up to $40 million to assist settlement on a contract with the South Australian Minister for Transport and Infrastructure for the sale and purchase of land.
On 11 October 2016, the defendant issued the plaintiffs a funding notice pursuant to the Agreement. Despite numerous extensions to the settlement date (Closing), the Sale Contract never settled and the plaintiffs were not ultimately required to subscribe for any units in the relevant unit trust. On 14 December 2016, the Minister terminated the sale contract and, on 22 December 2016, the defendant issued a revocation notice formally advising that the plaintiffs’ funds were no longer required.
The defendant paid the plaintiffs a commission of $1.2 million, being the base commission payable under the Agreement. The plaintiffs claimed that pursuant to clause 6.1 and paragraph 1(b) of Schedule 5 to the Agreement, they were also entitled to a daily fee of $20,000 for the 30-day period from 1 November 2016 to 30 November 2016.
Clause 1 of Schedule 5 provided that the plaintiffs would be entitled to an additional payment by way of a daily fee if the Underwriter … subscribes or may be required to subscribe (whether or not it does actually subscribe) for any Preference Unit at any time on or after 1 November 2016 ...”. That daily fee would accrue from 1 November 2016 for a maximum of 30 days, and would become due and payable by the earlier of “the date of Closing … and the Relevant Date”.
The plaintiffs also claimed that the defendant was estopped by its representations from denying that it would pay the plaintiffs the $20,000 daily fee until settlement.
The trial Judge found the plaintiffs were entitled to a daily fee of $20,000 for the 30-day period from 1 November 2016 to 30 November 2016, and awarded the plaintiffs an additional $600,000, along with pre-judgment interest and costs. However, the trial Judge rejected the promissory estoppel claim on the basis that the plaintiffs had not established…
Keep reading for free
Create a free CaseChat account to read Commercial & General Corporation Pty Ltd v Manassen Holdings... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2021] SASCFC 40
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court were the proper construction of the Underwriting Agreement, specifically the meaning of "Relevant Date" and the conditions under which the plaintiffs became entitled to the daily fee. The court was also required to determine whether the plaintiffs had accrued termination rights after the initial settlement date passed without closing, and if so, whether their subsequent election to proceed constituted a waiver of those rights. Furthermore, the court considered whether the plaintiffs' claim for the daily fee was sustainable on the grounds of promissory estoppel, and if so, whether such an estoppel could operate to create positive legal rights.
The majority of the court, comprising Livesey and Stanley JJ, held that the plaintiffs were only entitled to the daily fee if the "Relevant Date" was extended to 30 November 2016 due to a failure to obtain Foreign Investment Board Approval. They reasoned that the purpose of the daily fee was to compensate the plaintiffs for keeping the Maximum Underwritten Amount available. Once the original Relevant Date of 31 October 2016 passed without Closing, the plaintiffs were no longer bound to subscribe and had accrued termination rights. If they subsequently chose to waive these rights and proceed, this was a matter of their own choice and did not mean they were "required to subscribe" in a manner that would trigger the daily fee. The court also found that it was unlikely commercial parties would intend for a daily fee to be payable when one party retained the sole discretion to proceed and also the right to terminate. Regarding promissory estoppel, the court held that the mere non-receipt of a promised benefit is not sufficient detriment; rather, it is the reliance and consequential detriment that forms the basis of such a claim, and that promissory estoppel can, in appropriate circumstances, create positive legal rights. Nicholson J dissented in part.
The Full Court allowed the appeal, setting aside the orders made at trial, and dismissed the cross-appeal and the defendant's notice of contention. The parties were to be heard on the terms of the final orders and the question of costs.
Orders
Orders of the court
Held per Livesey J (Stanley J agreeing), allowing the appeal and dismissing the cross appeal and notice of contention:
1. The plaintiffs only became entitled to payment of the daily fee if, by reason of a failure to obtain Foreign Investment Board Approval by 31 October 2016, the “Relevant Date” was extended to 30 November 2016. The purpose of the daily fee was to compensate the plaintiffs for being required to keep the Maximum Underwritten Amount available.
2. Once the Relevant Date of 31 October 2016 passed without Closing occurring, the plaintiffs were no longer bound to subscribe and they accrued termination rights pursuant to clauses 3.3 and 4.1 of the Agreement. From 1 November 2016, it was entirely the plaintiffs’ choice as to whether they subscribed.
3. If after 1 November 2016 the plaintiffs chose to waive their termination rights and elected to proceed, with the result that they might then be compelled to subscribe, that nonetheless remained the result of their choice. It cannot be said that this comes within the words “may be required to be subscribe” in clause 1 of Schedule 5.
4. It is unlikely that these commercial parties intended that the daily fee should be paid where it remained entirely within the capacity of one party as to whether it would proceed and, in that setting, retain both the right to terminate and the right to receive a substantial daily fee.
5. The mere non-receipt of a promised benefit is not a detriment sufficient to found a promissory estoppel. It is the plaintiffs’ reliance and consequential detriment which forms the basis of a promissory estoppel, not merely the defendant’s departure from the representation made. To do otherwise converts the estoppel claim into a contractual claim for loss of expectation.
6. Promissory estoppel can in appropriate circumstances operate so as to provide a positive source of legal rights.
Held per Nicholson J, dissenting in part and dismissing the appeal, the cross-appeal and the notice of contention.
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
Established by:
Whilst this agreement did not, at least on the evidence, appear to have been amended from a pro forma document, the unusual and somewhat unique nature of the agreement suggests that particular attention must be given to what might be described as a “businesslike intention”:[28] Poor drafting may justify a court in being more ready to depart from the natural and ordinary meaning of the terms of a contract,[29] and no doubt, the poorer the drafting, the less willing a court should be to be “driven by semantic niceties to attribute to the parties an improbable and unbusinesslike intention”.[30] But poor drafting provides “no reason to depart from the fundamental rule of construction of contractual documents that the intention of the parties must be ascertained from the language they have used interpreted in the light of the relevant factual situation in which the contract was made”.[31] Where there is ambiguity which permits of two alternative and semantically not improbable interpretations, construction in accordance with what it may be supposed would be the approach of honest and reasonable businesspersons may assist in choosing one such alternative over the other.[28] Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd (2017) 261 CLR 544, [98] (Nettle J).[29] Arnold v Britton [2015] AC 1619, [18] (Lord Neuberger of Abbotsbury PSC, with whom Lord Sumption and Lord Hughes JJSC agreed), [66] (Lord Hodge JSC).[30] Mitsui Construction Co Ltd v Attorney-General (Hong Kong) (1986) 33 BLR 1, 14, cited with approval in Gan Insurance Co Ltd v Tai Ping Insurance Co Ltd [2001] 2 All ER (Comm) 299, [13] (Mance LJ).[31] Mitsui Construction (1986) 33 BLR 1, 14. See also Rainy Sky SA v Kookmin Bank [2011] 1 WLR 2900, [26] (Lord Clarke of Stone-cum-Ebony JSC, with whom Lord Phillips of Worth Matravers PSC, Lord Mance, Lord Kerr of Tonaghmore and Lord Wilson JJSC agreed).Consideration of the appeal At its core, the defendant’s complaint on appeal is that the learned trial Judge, in the course of what are admirably clear and comprehensive reasons, erred in construing the Underwriting Agreement because:1. After 31 October 2016, the defendant had no enforceable right to “require” the plaintiffs to subscribe to underwrite the purchase of the Preference Units under the Underwriting Agreement;2.The Relevant Date was 31 October 2016 and could only be a date after 31 October 2016 if Closing was delayed only because the Senior Debt Lender required FIRB approval, which was not the case; and3. On 31 October 2016, the additional fee payable was not ascertainable pursuant to the formula set out in Schedule 5 of the Underwriting Agreement.Meaning of “Relevant Date” Before determining the defendant’s appeal relating to the plaintiffs’ entitlement to the daily fee, it is first necessary to address what is meant by the phrase the “Relevant Date”. Clause 1 of the Agreement defines the “Relevant Date” as 31 October 2016, unless Closing is delayed beyond 31 October 2016 only because the Senior Debt Lender requires FRIB approval to provide the Senior Debt Facility, in which case the Relevant Date is automatically extended until 30 November 2016:Relevant Date means (a)where Closing will occur after 31 October 2016 only because the Senior Debt Lender requires FRIB approval to provide the Senior Debt Facility; 30 November 2016; and(b)otherwise, 31 October 2016.