SUPREME COURT OF QUEENSLAND
CITATION:
Wagners Cement Pty Ltd & Anor v Boral Resources (Qld) Pty Limited & Anor [2020] QCA 289
PARTIES:
WAGNERS CEMENT PTY LTD
ACN 126 029 481
(first appellant)
WAGNERS QUEENSLAND PTY LTD
ACN 122 170 745
(second appellant)
v
BORAL RESOURCES (QLD) PTY LIMITED
ACN 009 671 809
(first respondent)
BORAL LIMITED
ACN 008 421 761
(second respondent)FILE NO/S:
Appeal No 7375 of 2020
SC No 4294 of 2019DIVISION:
Court of Appeal
PROCEEDING:
General Civil Appeal
ORIGINATING COURT:
Supreme Court at Brisbane – [2020] QSC 124; [2020] QSC 163 (Bond J)
DELIVERED ON:
15 December 2020
DELIVERED AT:
Brisbane
HEARING DATE:
22 October 2020
JUDGES:
Fraser and Philippides JJA and Crow J
ORDER:
In default of agreement between the appellants and the respondents upon the orders (including declarations, monetary orders, and orders about costs) that are appropriate to give effect to the Court’s reasons, the appellants and the respondents have leave to lodge and serve a submission in writing upon that topic, any such submission not to exceed 10 pages (in addition to any draft order annexed to the submission) and to be made within 10 business days of this order unless the Registrar otherwise directs.
CATCHWORDS:
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – INTERPRETATION OF MISCELLANEOUS CONTRACTS AND OTHER MATTERS – where the parties entered into a long term contract under which the first appellant (“the Supplier”) agreed to supply cement products to the first respondent (“the Purchaser”) – where the contract contained a price adjustment mechanism which allowed the Purchaser to serve a notice on the Supplier containing market pricing evidence – where such a notice would have the effect of reducing the price of products under the contract unless the Supplier elected to suspend supply for six months – where the Purchaser served a notice containing market pricing evidence that consisted of a quotation for supply commencing at a future date, rather than at the date of the notice – whether this was a valid and effective pricing notice under the clause
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – INTERPRETATION OF MISCELLANEOUS CONTRACTS AND OTHER MATTERS – where, in response to the purported pricing notice served by the Purchaser, the Supplier gave the Purchaser a notice stating that the notice was invalid and referring the matter to the dispute resolution process under the contract – where this notice also stated that if, as the Purchaser contended, the notice was valid, the Supplier elected to suspend supply under the contract – whether the Supplier waived any invalidity in the Purchaser’s notice by its notice electing to suspend supply – whether the Supplier’s notice was effective to suspend supply under the contract
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – INTERPRETATION OF MISCELLANEOUS CONTRACTS AND OTHER MATTERS – where the price adjustment clause provided that if, during a suspension period, the Purchaser ceased to be able to…
Keep reading for free
Create a free CaseChat account to read Wagners Cement Pty Ltd v Boral Resources (Qld) Pty Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] QCA 289
- Decision Date
CaseChat Overview and Summary
The primary legal issues involved the interpretation of Clause 7.2, whether the Supplier's response to an allegedly invalid notice constituted a waiver, the interpretation of Clause 7.6 regarding the resumption of supply during a suspension period, and whether the Purchaser could serve a pricing notice during a suspension period. The court had to determine if the Purchaser's notices were valid under Clause 7.2, if the Supplier's response effectively suspended supply, and whether the Purchaser could resume procurement at a different price during a suspension period.
The court concluded that the Purchaser's notice dated 1 April 2019 was a valid Pricing Notice under Clause 7.2. The court found that the Supplier's notice dated 1 May 2019 was a valid notice electing to suspend supply under Clause 7.4. The court further ruled that the Supplier's notice did not result in an Affected Period as described in Clause 3.4. Additionally, the Purchaser's notice dated 2 October 2019 was held to be a valid Pricing Notice under Clause 7.2.
The court allowed the appeal and cross-appeal, setting aside certain orders made in the Trial Division. The court ordered declarations regarding the invalidity of the 18 March 2019 notice, the validity of the 1 April 2019 and 1 May 2019 notices, and the suspension period commencing 1 May 2019. It also directed that the parties submit written submissions regarding the appropriate orders, including declarations and costs, within 10 business days unless otherwise directed by the Registrar.
Orders
Orders of the court
In default of agreement between the appellants and the respondents upon the orders (including declarations, monetary orders, and orders about costs) that are appropriate to give effect to the Court’s reasons, the appellants and the respondents have leave to lodge and serve a submission in writing upon that topic, any such submission not to exceed 10 pages (in addition to any draft order annexed to the submission) and to be made within 10 business days of this order unless the Registrar otherwise directs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi