SUPREME COURT OF QUEENSLAND
CITATION: Wagners Cement Pty Ltd & Anor v Boral Resources (Qld) Pty Ltd
& Anor (No 2) [2020] QSC 163PARTIES: WAGNERS CEMENT PTY LTD (ACN 126 029 481)
(first plaintiff)
WAGNERS QUEENSLAND PTY LTD (ACN 122 170
745)
(second plaintiff)
v
BORAL RESOURCES (QLD) PTY LIMITED
(ACN 009 671 809)
(first defendant)
BORAL LIMITED (ACN 008 421 761)
(second defendant)FILE NO/S: BS 4294 of 2019 DIVISION: Trial Division PROCEEDING: Claim DELIVERED ON: 10 June 2020 DELIVERED AT: Brisbane HEARING DATE: 4 June 2020 JUDGE: Bond J ORDER: The orders of the Court are:
1.
It is declared that the notice of 1 March 2019 from the first defendant to the first plaintiff was not a valid and effective Pricing Notice under clause 7.2 of the Agreement when given.
2.
It is declared that the notice of 18 March 2019 from the first plaintiff to the first defendant was effective as a notice under clause 7.4 of the Agreement electing to suspend supply as at 18 March 2019.
3.
It is declared that, pursuant to clauses 7.4 and 7.5 of the Agreement, the effect of the notice of 18 March 2019 from the first plaintiff to the first defendant was that the supply of Products under the Agreement was suspended for six months from 18 March 2019.
4.
It is declared that, for the purposes of clause 7.5(4) of the Agreement, the Suspension Period ended on 18 September 2019.
5.
It is declared that, for the purposes of clauses 3.4 and 3.5 of the Agreement, the period which should be
treated as an Affected Period is the period commencing
on 18 March 2019 and ending on 21 September 2019.6. It is declared that the notice of 1 April 2019 from the first defendant to the first plaintiff was not a valid and effective Pricing Notice under clause 7.2 of the Agreement.
7. It is declared that the notice of 1 May 2019 from the first plaintiff to the first defendant was not a valid and effective notice under clause 7.4 of the Agreement.
8. It is declared that the letter of 2 October 2019 from the first defendant to the first plaintiff was a valid and effective Pricing Notice under clause 7.2 of the Agreement.
9. It is declared that the effect of the letter of 2 October 2019 from the first defendant to the first plaintiff was to reduce the price of general purpose cement and fly-ash blend cement under the Agreement to the new price per tonne nominated in the notice from 2 October 2019.
10. The plaintiffs must pay the defendants’ costs of the proceeding.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – COSTS – GENERAL RULE: COSTS FOLLOW EVENT – PARTIAL SUCCESS – where plaintiffs claimed declaratory relief resolving particular issues about the implementation of a price adjustment clause in a long-term contract and also a money judgment based on the resolution of those issues in their…
Keep reading for free
Create a free CaseChat account to read Wagners Cement Pty Ltd and Anor v Boral Resources (Qld) Pty... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2020] QSC 163
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was to determine the appropriate costs order in light of the plaintiffs' partial success. The plaintiffs were successful on some issues but failed on the claim for a money judgment. The court was required to assess the extent of the plaintiffs' success and decide whether the general rule of costs following the event applied.
The court considered the principle that costs generally follow the event, meaning the unsuccessful party usually pays the successful party's costs. However, given the partial success, the court needed to consider whether it was just to award costs in proportion to the degree of success. The court examined the nature and extent of the plaintiffs' success, finding that while they achieved some relief, their failure on the money judgment claim indicated a significant level of unsuccessful litigation. After weighing these factors, the court determined that a proportionate costs order was appropriate.
The orders of the court were that the defendants were to pay the plaintiffs' costs of the proceedings in proportion to their degree of success, reflecting the partial nature of the plaintiffs' victory. The court's decision balanced the principle of costs following the event with the need to fairly reflect the outcome of the litigation.
Orders
Orders of the court
The orders of the Court are:
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi