P J Nash Pty Ltd v Food and Beverage Australia Limited

Link copied
Case Copied 38 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Court of Appeal: Civil)

P J NASH PTY LTD v FOOD AND BEVERAGE AUSTRALIA LIMITED

[2021] SASCA 86

Judgment of the Court of Appeal  

(The Honourable Justice Lovell, the Honourable Justice Livesey and the Honourable Justice Bleby)

2 September 2021

APPEAL AND NEW TRIAL - APPEAL - GENERAL PRINCIPLES - INTERFERENCE WITH JUDGE'S FINDINGS OF FACT - FUNCTIONS OF APPELLATE COURT

APPEAL AND NEW TRIAL - APPEAL - GENERAL PRINCIPLES - ADMISSION OF FURTHER EVIDENCE - IN GENERAL

CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION OF CONTRACTS - INTERPRETATION OF MISCELLANEOUS CONTRACTS AND OTHER MATTERS

The parties were involved in a registered managed investment scheme for the development of cherry orchards in Tasmania and the cultivation, harvesting, marketing and sale of cherries. The scheme was governed by a number of contractual documents. The scheme was ultimately unsuccessful and a dispute arose regarding the distribution of proceeds from the 2014/15 harvest. The respondent sued the appellant in an action for debt for $1,125,581 being the total net proceeds from the 2014/15 harvest. The Trial Judge largely rejected the respondent's claim, however found the respondent was entitled to receive $156,456 being 13.9% of the harvest net proceeds under the scheme's contractual documentation. The appellant appealed that finding. 

The appellant complained that the Trial Judge erred in finding that the respondent had a claim in debt. Further, the appellant contended the Trial Judge erred in holding that the respondent was entitled to 13.9% of the harvest net proceeds; rather, the appellant contended that the respondent could only be entitled to 5.9% of the harvest net proceeds. The appellant also sought to adduce fresh evidence on appeal that the respondent was no longer in a position within the scheme to bring the proceedings or receive any judgment sum.

Held (by the Court), dismissing the appeal:

1. The Trial Judge was correct to hold that, upon proper construction of the scheme's contractual documentation, the respondent had a claim in debt against the appellant;

2. The Trial Judge's findings of fact with respect to the evidence were open to him and, upon review of the evidence, were correct;

3. The appellant's application to adduce fresh evidence on appeal is refused;

4. The appeal is dismissed;

5. Parties will be heard on the question of costs.

Attorney General (SA) v Marmanidis (2019) 132 SASR 320; Commonwealth Bank of Australia v Butterell (1994) 35 NSWLR 64; Crampton v The Queen (2000) 206 CLR 161; Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd (2017) 261 CLR 544; Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640; Fox v Percy (2003) 214 CLR 118; JGS v R [2020] SASCFC 48; Lee v Lee (2019) 266 CLR 129; Nash v Food and Beverage Australia Ltd [2021] SASCA 59; Perara-Cathcart v The Queen (2017) 260 CLR 595; Price v Spoor [2021] HCA 20; R v Birks (1990) 19 NSWLR…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read P J Nash Pty Ltd v Food and Beverage Australia Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] SASCA 86
Decision Date

CaseChat Overview and Summary

The appeal before the Full Court of the Supreme Court of South Australia concerned a dispute between P J Nash Pty Ltd (appellant) and Food and Beverage Australia Limited (respondent) regarding contractual entitlements arising from a managed investment scheme. The respondent claimed a debt against the appellant for a portion of harvest net proceeds. The appellant contended that the respondent's status as the "responsible entity" of the project was a prerequisite for its claim, and that without this status, the respondent was not entitled to receive the proceeds.

The central legal issues before the Court were: first, whether the respondent had a valid claim in debt against the appellant based on the proper construction of the scheme's contractual documentation; second, whether the Trial Judge's findings of fact were correct and open to him on the evidence; and third, whether the appellant should be permitted to adduce fresh evidence on appeal. The appellant sought to introduce evidence relating to the winding-up and deregistration of the project, and the cancellation of the respondent's Australian Financial Services Licence, arguing these events undermined the respondent's capacity to sue.

The Court dismissed the appeal, upholding the Trial Judge's decision. It reasoned that, on a proper construction of the contractual documentation, the respondent had an accrued right to claim the debt. The Court found that the Trial Judge's factual findings were open to him and were correct upon review of the evidence. Furthermore, the Court refused the appellant's application to adduce fresh evidence, finding that it did not meet the criteria for admission on appeal, particularly as the evidence related to events that occurred prior to or during the trial, and its relevance to the accrued contractual rights was questionable. The Court concluded that the underlying contractual arrangements subsisted, and the respondent remained contractually obligated to deal with the project proceeds, irrespective of its status as "responsible entity" for regulatory purposes.

Consequently, the appeal was dismissed. The Court ordered that parties be heard on the question of costs.

Orders

Orders of the court

Held (by the Court), dismissing the appeal:

1. The Trial Judge was correct to hold that, upon proper construction of the scheme's contractual documentation, the respondent had a claim in debt against the appellant;

2. The Trial Judge's findings of fact with respect to the evidence were open to him and, upon review of the evidence, were correct;

3. The appellant's application to adduce fresh evidence on appeal is refused;

4. The appeal is dismissed;

5. Parties will be heard on the question of costs.

Background

Background to the litigation

Evidence

Evidence Before The Court

PJN contended that FABAL’s status as the responsible entity of the Project was essential to its success in claim for debt. Consequently, without the status as responsible entity, FABAL had no entitlement under the Project’s contractual documentation to receive the harvest net proceeds and therefore its claim must fail.[46] The success of this argument was contingent upon the admission of fresh evidence on appeal. [46] A similar argument with respect to FABAL’s capacity, or lack thereof, as responsible entity to sue for Grower fees was subject to consideration recently in Nash v Food and Beverage Australia Ltd [2021] SASCA 59.Submissions and application for fresh evidence PJN sought to adduce documentary evidence that the Project was wound-up in August 2018, that it was deregistered on 23 December 2018, and that FABAL’s Australian Financial Services Licence was cancelled on 22 June 2019. The evidence was annexed to an affidavit of PJN’s solicitor who had conduct of the appeal proceedings and was “authorised” by Mr Nash to make the affidavit on PJN’s behalf.[47] The winding-up and deregistration occurred prior to the trial.[48] The cancellation of the licence occurred between trial ending and judgment being delivered.[49] PJN speculated that these matters “must have been known” by FABAL but were not pleaded or disclosed other than a brief mention in cross-examination. [47] Affidavit of Daniel James Mackay sworn 21 July 2020.[48] The trial took place between 25 February 2019 and 7 March 2019.[49] Judgment was delivered on 6 December 2019. FABAL submitted the application to adduce fresh evidence was deficient and should be refused. There was no reason to suggest the evidence was not available to PJN at the time of trial and, had the matter been raised, FABAL may have answered in respect of the Australian Securities and Investments Commission’s actions being premature or not justified. In any event, FABAL contended the evidence sought to be adduced was irrelevant to its accrued right of action in debt. Further, FABAL submitted that the fact a managed investment scheme may cease to be for the purposes of the Corporations Act 2001 (Cth) does not deny or destroy contractual rights and obligations established by the scheme’s documents; the underlying contractual arrangements subsisted. It was also submitted that FABAL remained under a contractual and/or equitable duty to deal with the Project proceeds as required by the Project Constitution, irrespective of the label of “responsible entity”. Consideration The Court may, in its discretion, accept fresh evidence on appeal. In doing so, the Court must be satisfied the evidence could not, with reasonable diligence, have been obtained for use at trial and, if the evidence had been available, it is reasonably clear that an opposite outcome would have resulted.[50] The ultimate test is whether it is in the interests of justice to receive the fresh evidence. Public interest in the finality of litigation is also an important consideration.[51] [50] Sunlight Nominees Pty Ltd v Zotti and Zotti [2019] SASCFC 11 at [39]–[42]. [51] Steicke v Pederick (2019) 134 SASR 114 at [7]; Viscariello v Livesey [2013] SASC 99 at [132].

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

Even if the Licence Agreements were relevant to FABAL’s entitlement to the Project cherries’ proceeds, FABAL contended that the question to be answered was whether the underlying ownership of the trees without a valid Licence Agreement vested in ACL such that, as principal, payment to it (rather than FABAL) constituted a valid discharge of that part of the debt owed under cl 4.9.4 of the Cherry Marketing Agreement. FABAL contended the Trial Judge’s finding that a valid discharge had not been established was correct; ACL was not the principal with respect to the Project cherries’ proceeds in the way it was with respect to the ACL cherries’ proceeds. Consideration The determination of this issue depends to an extent on the resolution of whether FABAL had a cause of action in debt or ought to have pursued damages for breach of contract. For the reasons set out later in this judgment, we consider that the Trial Judge was correct in finding that FABAL was entitled to pursue an action in debt for liquidated damages. The reasons dealing with Issue 2 need to be read in conjunction with the reasons in relation to Issue 3. An objective approach is required to determine the rights and liabilities of a party to a commercial contract, by reference to its text, context and purpose. The meaning to be given to its terms is determined by reference to what a reasonable business person would have understood those terms to mean.[30][30] Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd (2017) 261 CLR 544 at [16]–[17]; Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640 at [35]; Price v Spoor [2021] HCA 20 at [27]. Consideration may be given to the language used by the parties, the surrounding circumstances known to them, and the commercial purpose or objects to be secured by the contract.[31] Further, when construing various agreements that together comprise part of a managed investment scheme, and those agreements cross-reference one another, it is appropriate to read them as cognate documents.[32] [31] Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640 at [35].[32] Rocky Castle Finance Pty Ltd v Taylor (2014) 118 SASR 349 at [106]–[109]. It is useful to set out in full the Trial Judge’s findings subject to complaint in Issue 2. The Trial Judge held: There is a tension between this clause [clause 10] of the Licence Agreement, and the Constitution. In particular, clause 22 of the Constitution, while treating the default of a Grower under a Licence Agreement as a matter that enabled the termination of their Interest in the Project, was nevertheless drafted in terms that assumed that FABAL, as the Responsible Entity, had a discretion whether or not to terminate the Interest in that circumstance. FABAL contends that there is thus an inconsistency between the Licence Agreement and the Constitution in this respect, and that the Constitution must prevail to the extent of this inconsistency.While there is, as I have observed, a tension between the termination provisions of the Licence Agreements and the Constitution, I am not satisfied that there is an inconsistency sufficient to ignore the plain terms of the Licence Agreements. I accept PJN’s submission that where a Grower’s Licence Agreement has been terminated (as opposed to a Grower merely being in default), then their Interest is automatically terminated. This leaves the Responsible Entity with an additional discretion under the Constitution to terminate (or, indeed, not terminate) in circumstances where the Grower is merely in default under their Licence Agreement (but without that Licence Agreement having been terminated by ACL).However, despite this conclusion, I do not think it provides PJN with an answer to FABAL’s use of 13.9 per cent. The first difficulty with PJN’s position is FABAL’s contention that ACL was not in a position to terminate the Licence Agreements for the late payment of licence fees because FABAL had earlier entered into payment plans with the relevant Growers. While there is reference to these matters in the evidence, there is insufficient evidence for me to determine the validity of ACL’s purported termination of the various Licence Agreements.But more fundamentally, even accepting that some Licence Agreements were validly terminated and hence that some further Growers ceased to have an Interest in the Project, it does not mean that the trees in which they held an Interest ceased to be Project trees. Put another way, the trees did not, without more, become ACL’s trees with the result that payment of the net proceeds in respect of those trees to ACL discharged PJN’s obligation to pay FABAL the net proceeds under the CMA.Even accepting that the further Grower Interests were terminated by reason of their Licence Agreements being terminated, the evidence does not establish that those Interests, or the trees to which they related, had been acquired by ACL by the time PJN became obliged to pay over the net proceeds of sale from the 2014/15 harvest. In my view, the proceeds from these trees remained Project proceeds that were to be paid to FABAL as the Responsible Entity of the Project, for it to then apply and distribute in accordance with the Project documentation. It follows that FABAL is entitled to recover 13.9 per cent of the total net proceeds, or $156,456.(emphasis added)