SUPREME COURT OF QUEENSLAND
CITATION:
IW & CA Price Constructions Pty Ltd v Australian Building Insurance Services Pty Ltd & Ors [2017] QSC 39
PARTIES:
IW & CA PRICE CONSTRUCTIONS PTY LTD ABN 50301203933 A TRUSTEE FOR THE COASTAL BUILDING INSURANCE CLAIMS & REPAIRS TRUST
(plaintiff)
v
AUSTRALIAN BUILDING INSURANCE SERVICES PTY LTD ACN 162 498 599(first defendant)
BRUCE WILLIAM CARRIGAN
(second defendant)IAN WINSTON PRICE
(third party)
FILE NO/S:
No 9993 of 2013
DIVISION:
Trial Division
PROCEEDING:
Trial
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
21 March 2017
DELIVERED AT:
Brisbane
HEARING DATE:
4 – 7 October 2016 written submissions 17, 24 October, 1, 9 November 2016.
JUDGE:
A Lyons J
ORDER:
1. I will hear the parties as to Costs and as to the form of the Orders.
CATCHWORDS:
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – IMPLIED TERMS – GENERALLY – where the defendant business was sold by the plaintiff to the second defendant – where the defendants claim that the duties to cooperate, to act in good faith and to account were implied into the contract of sale – whether the duties are implied into the contract
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – DISCHARGE, BREACH AND DEFENCES TO ACTION FOR BREACH – OTHER MATTERS – where the defendant business was sold by the plaintiff to the second defendant – where the defendants submit that the plaintiff and third party breached the implied duties to cooperate, to act in good faith and to account by inter alia disparaging the second defendant to a major client of the business – whether any breaches occurred
DAMAGES – MEASURE AND REMOTENESS OF DAMAGES IN ACTIONS FOR BREACH OF CONTRACT – REMOTENESS AND CAUSATION – LOSS OF PROFITS – where the defendant business was sold by the plaintiff to the second defendant – where the defendants claim the plaintiff breached the implied duties to cooperate, to act in good faith and to account by inter alia disparaging the second defendant to a major client of the business – where the defendants claim that the breaches of the implied duties caused the major client to temporarily cease allocating work to the business – where the defendants claim damages for loss of profits – whether the actions of the plaintiff caused the damages claimed
DAMAGES – MEASURE AND REMOTENESS OF DAMAGES IN ACTIONS FOR BREACH OF CONTRACT – REMOTENESS AND CAUSATION – OTHER CASES - where the defendant business was sold by the plaintiff to the second defendant – where the defendants claim the plaintiff breached the implied duties to cooperate, to act in good faith and to account by inter alia disparaging the second defendant to a major client of the business – where the defendants claim that the breaches of the implied duties caused the major client to temporarily cease allocating work to the business – where the defendants claim damages for diminution of the goodwill of the business…
Keep reading for free
Create a free CaseChat account to read IW & CA Price Constructions Pty Ltd v Australian Building In... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] QSC 39
- Decision Date
CaseChat Overview and Summary
The legal issues were whether the duties of cooperation, good faith, and accounting were implied into the contract of sale, whether the plaintiff breached those duties, and if so, whether those breaches caused the damages claimed. The court examined the terms of the contract, the conduct of the plaintiff, and the causation of the claimed damages.
The court found that the duties of cooperation, good faith, and accounting were not implied into the contract of sale. It concluded that the plaintiff did not breach any such duties, and therefore, there were no damages for loss of profits or diminution of goodwill. The court ordered that the plaintiff owed the defendants certain sums for unpaid purchase price, work in progress, and damages for loss of profits from the November 2013 storm events, but not for the diminution of goodwill.
The court will hear the parties on costs and the form of the orders. The amount owing to the plaintiff under the contract is $550,000 plus interest from 1 February 2014. The amount owing to ABIS for work in progress is $382,180.27 plus interest from 1 January 2014. The amount of the diminution of goodwill is not payable. The court will also consider the form of the orders and the costs.
Orders
Orders of the court
1. I will hear the parties as to Costs and as to the form of the Orders.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi