DISTRICT COURT OF QUEENSLAND
CITATION:
Australian Building Insurance Services Pty Ltd v CGU Insurance Limited [2019] QDC 18
PARTIES:
AUSTRALIAN BUILDING INSURANCE SERVICES PTY LTD (ACN 162 498 599)
(plaintiff)
v
CGU INSURANCE LIMITED (ABN 27 004 478 371)
(defendant)FILE NO/S:
4368/17
DIVISION:
Civil
PROCEEDING:
Trial
ORIGINATING COURT:
District Court at Brisbane
DELIVERED ON:
22 February 2019
DELIVERED AT:
Brisbane
HEARING DATE:
10 August 2018, 1 February 2019
Written submissions: 6, 8 February 2019JUDGE:
Koppenol DCJ
ORDER:
1. Plaintiff’s claim dismissed.
2. Judgment for the Defendant.
3. I will hear the parties as to costs.
CATCHWORDS:
CONTRACTS - NOVATION - where defendant consented to assignment of vendor’s rights and obligations under supplier agreement following sale of business - whether novation to plaintiff/purchaser effected
BUILDING CONTRACTS - whether supplier agreement constituted “contract or other arrangement for carrying out building work” under QBSA Act - whether “payment time” had passed when payments made - whether invoices “disputed invoices” under supplier agreement
BUILDING CONTRACTS - whether plaintiff “contracted party” under QBSA Act for pre-novation work completed by another party - whether entitled to interest at penalty rate on late payments for pre-novation work
EVIDENCE - QUANTUM – ONUS OF PROOF - whether rational evidentiary foundation on which Court could make proper estimate
Queensland Building Services Authority Act 1991, ss 67A, 67AAA(1), 67P, Sched 2
ALH Group Property Holdings Pty Ltd v Chief Commissioner of State Revenue (NSW) (2012) 245 CLR 338, applied
Ball Construction Pty Ltd v Conart Pty Ltd [2014] QSC 124, followed
In the matter of FAL Healthy Beverages and FAL Retail Pty Ltd [2017] NSWSC 476, followed
TCL Air Conditioner (Zhongshan) Co Ltd v Castel Electronics Pty Ltd [2014] FCAFC 83, followed
IW & CA Price Constructions Pty Ltd v Australian Building Insurance Services Pty Ltd & Ors [2017] QSC 39, referred toCOUNSEL:
S Couper QC and P Travis for the plaintiff
A Morris QC and A Harding for the defendantSOLICITORS:
Axia Litigation Lawyers Pty Ltd for the plaintiff
MCK Lawyers for the defendant
The Claim
The sole issue in this matter is whether the plaintiff has proven that the defendant is required to pay it “interest at the penalty rate” under section 67P (Late progress payments) of the Queensland Building Services Authority Act 1991 (QBSA Act). The plaintiff’s claim is for $242,032.14.
Section 67P provides as follows:
“67P Late progress payments
(1) This section applies if—
(a) the contracting party for a building contract is required to pay an amount (the progress amount) to the contracted party for the building contract; and
(b) the progress amount is payable as the whole or a part of a progress payment; and
(c) the time (the payment time) by which the progress amount is required to be paid has passed, and the progress amount, or a part of the progress amount, has not been paid.
(2) For the period for which the progress amount, or the part…
Keep reading for free
Create a free CaseChat account to read Australian Building Insurance Services Pty Ltd v CGU Insuran... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] QDC 18
- Decision Date
CaseChat Overview and Summary
The primary legal issue was whether there was a rational evidentiary foundation on which the court could make a proper estimate of the damages claimed by the plaintiff. The plaintiff argued that the evidence presented was adequate to support their claim, while the defendant contended that the plaintiff had failed to meet the onus of proof required to establish the amount of damages claimed. The court was required to determine whether the evidence was sufficient to enable it to make an informed assessment of the damages claimed by the plaintiff.
In delivering the judgment, the court held that the plaintiff had failed to provide a rational evidentiary foundation for the quantum of damages claimed. The court found that the plaintiff's evidence was insufficient to enable it to make a proper estimate of the damages claimed. The court noted that the plaintiff had not provided detailed evidence of the losses incurred, and that the evidence provided was speculative and not based on concrete facts. The court concluded that the plaintiff had not discharged the onus of proof and dismissed the claim. Judgment was entered in favour of the defendant.
The court will hear the parties as to costs at a later date. The plaintiff's claim for damages was dismissed, and judgment was entered in favour of the defendant.
Orders
Orders of the court
1. Plaintiff’s claim dismissed.
2. Judgment for the Defendant.
3. I will hear the parties as to costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi