SUPREME COURT OF QUEENSLAND
CITATION:
Australian Building Insurance Services Pty Ltd v CGU Insurance Limited [2020] QCA 121
PARTIES:
AUSTRALIAN BUILDING INSURANCE SERVICES PTY LTD
ACN 162 498 599
(applicant)
v
CGU INSURANCE LIMITED
ABN 27 004 478 371
(respondent)FILE NO/S:
Appeal No 3110 of 2019
DC No 4368 of 2017DIVISION:
Court of Appeal
PROCEEDING:
Application for Leave s 118 DCA (Civil)
ORIGINATING COURT:
District Court at Brisbane – [2019] QDC 18 (Koppenol DCJ)DELIVERED ON:
5 June 2020
DELIVERED AT:
Brisbane
HEARING DATE:
16 September 2019
JUDGES:
Fraser and Philippides JJA and Crow J
ORDERS:
1. Leave to appeal be granted.
2. The appeal be allowed.
3. The orders of the District Court dismissing the appellant’s claim and awarding judgment for the respondent be set aside and, in lieu thereof, judgment for the appellant in the amount of $242,032.14 be entered.
4. Unless the parties file submissions as to costs within 14 days of the publication of these reasons, not to exceed four A4 pages in length, the respondents are to pay the appellant’s costs of and incidental to the appeal and the proceeding below on the standard basis.
CATCHWORDS:
APPEAL AND NEW TRIAL – PROCEDURE – QUEENSLAND – WHEN APPEAL LIES – FROM DISTRICT COURT – BY LEAVE OF COURT – where the District Court dismissed the applicant’s claim as plaintiff against the respondent for interest at the statutory penalty rate pursuant to s 67P of the Queensland Building Services Authority Act 1991 (Qld) (“QBSA Act”) – where the respondent did not advance any basis upon which to oppose leave to appeal and the hearing proceeded on the merits of the proposed appeal – whether the application concerns issues of statutory interpretation of general significance to those involved in contracting for building services and raises an arguable case – whether leave to appeal should be granted
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – NOVATION AND ASSIGNMENT – where the appellant purchased a building insurance claims repair work business from the seller, which was supplier of repair work services to the respondent pursuant to a supplier agreement – where there were various incomplete insurance repair jobs under the supplier agreement when the business was sold – where the seller consented in writing to the assignment of its interest in the supplier agreement to the appellant and the respondent also consented to the assignment – where the respondent accepted that the assignment of the seller’s rights and obligations effected a novation of the supplier agreement – where the appellant, following novation, completed all incomplete repair jobs and subsequently issued invoices totalling $601,896 which were paid by the respondent, some of which were delayed – where the appellant, before the District Court, claimed statutory penalty interest consequent on the late payment of the invoices pursuant to s 67P of the QBSA Act, on the basis that the appellant was the “contracted party for a building contract” within…
Keep reading for free
Create a free CaseChat account to read Australian Building Insurance Services Pty Ltd v CGU Insuran... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] QCA 121
- Decision Date
CaseChat Overview and Summary
The court held that the appellant, having purchased a building insurance claims repair work business from the seller and subsequently completing the unfinished jobs, was indeed the contracted party for the building contract. The court clarified that the statutory provision was not concerned with the physical undertaking of the work but rather the contractual obligation to pay the progress amount under the building contract. Therefore, the appellant, as the entity that undertook the contractual obligations to carry out the building work, was the contracted party. The court further found that the requirement for the progress amount to qualify as a "progress payment" under the Building Industry Payments Act 1991 did not prevent the appellant's claim for penalty interest.
The court granted leave to appeal, allowed the appeal, and set aside the District Court's orders. Judgment was entered in favour of the appellant for the amount of $242,032.14. Unless the parties submitted written costs submissions within 14 days of the publication of the reasons, the respondents were to pay the appellant's costs of the appeal and the proceeding below on the standard basis.
Orders
Orders of the court
1. Leave to appeal be granted.
2. The appeal be allowed.
3. The orders of the District Court dismissing the appellant’s claim and awarding judgment for the respondent be set aside and, in lieu thereof, judgment for the appellant in the amount of $242,032.14 be entered.
4. Unless the parties file submissions as to costs within 14 days of the publication of these reasons, not to exceed four A4 pages in length, the respondents are to pay the appellant’s costs of and incidental to the appeal and the proceeding below on the standard basis.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
In its written submissions, the respondent also drew support from s 67P(1)(b) of the Act and the requirement therein that “the progress amount is payable as the whole or part of a progress payment” and directed attention to the BCIPA, which defined the right to a progress payment in terms of construction work “carried out or undertaken to be carried out ‘under the contract’”.[23] It was submitted that the right to a progress payment did not exist for construction work not carried out “under the contract”, including work that was carried out under a different contract and consequently outside the scope of operation of the BCIPA. That approach was said to be consistent with the authorities set out by Douglas J in Ball Construction.[24] The work that was carried out by Price Constructions under the original supplier agreement was not construction work that was carried out under the novated supplier agreement because it preceded the making of that contract. Accordingly, the primary judge correctly found that it was outside the scope of s 67P.[23]Respondent’s outline at [11].[24]Walton Construction (Qld) Pty Ltd v Salce & Ors [2008] QSC 235 at [22]; Walton Construction (Qld)Pty Ltd v Corrosion Control Technology Pty Ltd [2012] 2 Qd R 90 at [42]-[45]; McNab NQ Pty Ltd v Walkrete Pty Ltd [2013] QSC 128 at [28] referred to in Ball Construction Pty Ltd v Conart Pty Ltd [2014] QSC 124 at [11]-[12].Consideration Section 67P(1)(a) of the Act focuses, as a precondition to a statutory entitlement to penalty interest under s 67P(2), on the contractual obligation under the “building contract” to pay an amount (the “progress amount” being an amount that qualifies for payment as a BCIPA “progress payment”). Section 67P(1)(a) is not directed to a person who physically undertakes contractual work but to the contractual obligation to pay the progress amount in question imposed under the building contract – that is the contractual obligation imposed on the party for whom the building work, the subject of the contract, is to be carried out (the contracting party) for the benefit of the party who is to carry out the work thereunder (the contracted party). By the novated supplier agreement, it was the appellant who undertook contractual obligations to carry out building work, including that which Price Constructions had performed but which was incomplete and rectification, if required, of that work, and thus became the contracted party for a building contract to which the respondent was the contracting party for whom the construction work was to be carried out thereunder. Nor did the requirement under s 67P(1)(b) for that the progress amount to qualify as a “progress payment” under the BCIPA provide any impediment to the appellant’s claim for penalty interest. “Progress payment” is defined under BCIPA[25] to mean a payment to which a person is entitled under s 12 (and includes a final, single or one off payment for carrying out construction work under the construction contract). A “construction contract”[26] relevantly means one under which one party “undertakes to carry out” construction work for another party. By s 12 of the BCIPA, the right to progress payments relevantly arises from “each reference date under a construction contract” where a “person has undertaken to carry out construction work” “under the contract”. “Reference date” under a construction contract is relevantly defined[27] to mean the date stated in or worked out under the contract as the date a progress payment may be made.[25]See sch 2 of BCIPA.[26]See sch 2 of BCIPA.[27]See sch 2 of BCIPA.