SUPREME COURT OF QUEENSLAND
CITATION:
Lake Laurel Pty Ltd & Ors v Nichols Constructions Pty Ltd & Ors (No 2) [2019] QSC 145
PARTIES:
LAKE LAUREL PTY LTD ACN 010 7023 511 TRADING AS BERGER CONTRACTING
(First Plaintiff)
LUTZ BERGER
(Second Plaintiff)
PETER JAMES RYAN
(Third Plaintiff)
v
NICHOLS CONSTRUCTIONS PTY LTD ACN 010 763 505(First Defendant)
LESLIE EDWIN NICHOLS and LESLIE EDWIN NICHOLS AS PERSONAL REPRESENTATIVE OF JUDELLE CHRISTINE NICHOLS
(Second Defendants)
FILE NO/S:
BS No 3368 of 2014
DIVISION:
Trial Division
PROCEEDING:
Trial
DELIVERED ON:
6 June 2019
DELIVERED AT:
Brisbane
HEARING DATE:
20, 21, 23 and 24 May 2019
JUDGE:
Bowskill J
ORDER:
Judgment for the third plaintiff on his claim against the first and second defendants for payment of the principal sum under the loan agreement and the mortgage in the amount of $3,775,000.00 with interest and costs to be agreed between the parties or, failing agreement, to be determined by the court.
The parties are directed to provide a draft form of judgment reflecting the court’s decision, and addressing interest and costs. If interest and costs are not agreed, the parties are to file and serve written submissions in relation to those issues within 7 days.
CATCHWORDS:
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – IMPLIED TERMS – GENERALLY – where the parties were involved in a project to subdivide land – where the first plaintiff and the first defendant entered into a loan agreement, with the second defendants as guarantors, which was secured by a registered mortgage, under which the first defendant agreed to pay the principal sum of $3,775,000.00 to the first plaintiff, by incremental instalments on the sale of each lot in the proposed subdivision, with the balance to be repaid 12 months from registration of the plan(s) of subdivision – where the debt under the loan agreement and mortgage were later assigned to the third plaintiff – where the third plaintiff claims the debt has become due and payable, as a consequence of the first defendant’s breach of express and implied terms of the loan agreement and mortgage, by allowing the development approval for the land to lapse, and failing to obtain registration of the plan(s) of subdivision within a reasonable time – where the defendants do not challenge the contention that the first defendant breached the loan agreement and/or the mortgage in the ways contended by the third plaintiff, but argue the principal sum has not become payable because of an earlier breach by the first plaintiff of the implied obligation under the loan agreement and the mortgage to cooperate – whether the implied obligation to cooperate required the first plaintiff to take steps to ensure that plan(s) for subdivision of the land were registered, or not to hinder or obstruct the first defendant’s efforts in that regard – whether such a breach, even if established, could be relied upon to defend the claim by the third plaintiff, as assignee, to recover the principal sum…
Keep reading for free
Create a free CaseChat account to read Lake Laurel Pty Ltd v Nichols Constructions Pty Ltd (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] QSC 145
- Decision Date
CaseChat Overview and Summary
The court found that the implied obligation to cooperate did not require the first plaintiff to take steps to ensure that plans for the subdivision of the land were registered, or to refrain from hindering or obstructing the first defendant’s efforts in that regard. The court was not persuaded, on the evidence before it, that anything the first plaintiff did or did not do obstructed or hindered the first defendant in doing that. The court concluded that the principal sum under the loan agreement had become due and payable, and there was judgment for the third plaintiff on his claim against the first and second defendants for payment of the principal sum under the loan agreement and the mortgage in the amount of $3,775,000.00. The parties were directed to provide a draft form of judgment reflecting the court’s decision and addressing interest and costs. If interest and costs were not agreed, the parties were to file and serve written submissions in relation to those issues within 7 days.
Orders
Orders of the court
Judgment for the third plaintiff on his claim against the first and second defendants for payment of the principal sum under the loan agreement and the mortgage in the amount of $3,775,000.00 with interest and costs to be agreed between the parties or, failing agreement, to be determined by the court.
The parties are directed to provide a draft form of judgment reflecting the court’s decision, and addressing interest and costs. If interest and costs are not agreed, the parties are to file and serve written submissions in relation to those issues within 7 days.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
In addition, there is no contention that, by operation of clause 10 of the mortgage, subject to the defendants’ argument of a prior disentitling breach by Lake Laurel, all moneys secured by the mortgage became due and payable.(ii) breach of the implied term that registration of the plan(s) of subdivision for the Ziebarth Subdivision would occur within a reasonable period of time The defendants do not challenge a finding that it was an implied term of the loan agreement and the mortgage that the plan(s) for the “Ziebarth Subdivision”, as that term is defined in clause 1 of the loan agreement, was required to be registered within a reasonable time.[18] [18] This is supported by York Air Conditioning and Refrigeration (A/sia) Pty Ltd v The Commonwealth (1949) 80 CLR 11 at 62; and Perri v Coolangatta Investments Pty Ltd (1982) 149 CLR 537 at 543. Nor do the defendants challenge the argument(s) of the third plaintiff as to what constituted a reasonable time. There were effectively three time periods identified by the third plaintiff:1.By 13 August 2012, on the basis of Mr Berger’s evidence, that it would take about 13 months after obtaining the development approval, to obtain operational works approval, to construct the civil works, and then to register the plan of subdivision.[19]2.By 13 April 2014, on the basis of the evidence of Mr McAnany, civil engineer, that he would estimate about 2 years and 9 months from the obtaining of development approval, to registration of the plans.[20]3.By 8 April 2013, which is 12 months before the proceedings were commenced (because payment was required 12 months from registration of the plan(s) of subdivision).[19] T3-34 and 3-38.[20] Exhibit 20 and T 3-74 to 3-76. What is a reasonable time is a question of fact, to be determined having regard to all the circumstances, including those which are known or foreseeable at the time of the contract as well as subsequent circumstances and events.[21][21] Hart v MacDonald (1910) 10 CLR 417 at 421-422; Telina Developments Pty Ltd v Stay Enterprises Pty Ltd [1984] 2 Qd R 585 at 587 and 591-592; Rudi’s Enterprises Pty Ltd v Jay (1987) 10 NSWLR 568 at 575-576. On the evidence I find that a reasonable time, for registration of the plan(s) of subdivision of Lot 261, was about three years from the January 2013 floods. I adopt the time periods estimated by Mr McAnany (a total of 2 years and 9 months, including 13 months for design and operational works approval, 12 months for civil works construction, 2 months for plan sealing and 6 months for slippage), round this up to three years, and calculate it from the time of the January 2013 floods, having regard to the evidence of Mr Boheim, a town planner with the Council. Mr Boheim gave evidence that both the 284 Patrick Street and Lot 261 sites were affected by floodwaters as a result of the January 2013 floods. He said that following the floods, Council developed “an awareness of issues with the design” of drainage and flooding requirements in relation to these sites, “that we weren’t previously aware of”. He said the Council requires the owner/developer of those sites to address those issues before the Council will seal any further plans. He confirmed that even if everything was constructed in accordance with the original development approval, the Council still would not seal the plan for stage 2, until these other drainage design issues are addressed.[22][22] T 4-8.