FEDERAL COURT OF AUSTRALIA
Construction, Forestry, Maritime, Mining and Energy Union v Milin Builders Pty Ltd [2019] FCA 1070
Keep reading for free
Create a free CaseChat account to read Construction, Forestry, Maritime, Mining and Energy Union v... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] FCA 1070
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court included the interpretation of the phrase "refuse entry" within the context of the FW Act, the proportionality of the penalty to the contravening conduct, and the principles to be applied in making a declaration of contravention. The court had to determine whether the First Respondent had indeed refused entry as alleged, and if so, what penalty should be imposed to achieve deterrence. Additionally, the court needed to consider whether declaratory relief should be granted, and if so, in what terms.
The court found that the First Respondent had refused entry to the union officers as alleged. It examined the principles of proportionality and deterrence in determining the appropriate penalty, taking into account the First Respondent's contrition, cultural considerations, and the absence of prior contraventions. The court acknowledged the First Respondent's appropriate contrition and its overall good compliance culture, which warranted a discount on the otherwise appropriate penalty. The court imposed a pecuniary penalty of $15,000.00, considering the deterrence factors and the circumstances of the case. The court also granted the declaratory relief as sought by the parties, specifying the contravention as per the agreement. Finally, the court ordered the penalty payment within 28 days, dismissed the proceeding otherwise, and made no order as to costs.
This decision underscores the court's role in interpreting industrial laws, applying principles of deterrence and proportionality in penal matters, and exercising discretion in granting declaratory relief.
Orders
Orders of the court
1. A pecuniary penalty of $15,000.00 be imposed upon the first respondent.
2. The penalty so imposed be paid to the applicant not later than 28 days from the date of these orders.
3. The proceeding be otherwise dismissed.
4. There be no order as to costs.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
It is appropriate for the court to acknowledge that the first respondent has exhibited appropriate contrition for its conduct. I accept the submission of the intervener that the Agreed Contravention could fairly be described as an “aberration”. It is not open to the court to reject the first respondent’s evidence as to its contrition; nor to find that it has made the admissions that it has for any particular reason. Clearly, it would have been preferable for the admissions to have been made sooner than they were and the penalty that I will impose in respect of the Agreed Contravention might well have been smaller had that occurred; but the first respondent is entitled, all the same, to recognition (in the form of a discount on the penalty that would otherwise be appropriate) for the steps that it has taken.Cultural considerations The first respondent led evidence to show that the Agreed Contravention was properly described as an “aberration”. I need not repeat that evidence here. I accept that it was an isolated event, and that the first respondent otherwise has in place an adequate system to ensure its compliance with pt 3-4 of the FW Act and a good, overall culture of compliance. I also accept that the relationship between the applicant and the first respondent is both improved and cooperative. There was a wealth of evidence led as to what might be described as the first respondent’s level of community engagement. That evidence was led in aid of the submission that the first respondent does not want for incentive to conduct itself lawfully, and that it “…does, and will continue to, direct its resources responsibly for the benefit of the community.” I accept that submission. It is appropriate to have regard to the many and varied positive contributions that the first respondent makes (and, it appears, will continue to make) to the construction industry and the ACT community more broadly.Loss and damage caused Given the nature of the rights that were sought to be exercised, it is not surprising that there is no evidence of any loss or damage arising from the Agreed Contravention. This factor has no bearing on the penalty to be imposed.Size and financial position The first respondent accepts that it is “well-resourced”. There is no suggestion that it lacks the means to sustain the imposition of a penalty; nor that its contravention should be excused (or partially excused) on account of its size.Prior contraventions The first respondent has not previously (nor since) been found to have contravened any of the requirements for which pt 3-4 of the FW Act provides.Conclusions On the strength of the observations above, I consider that the requirements of deterrence—both specific and general—and the circumstances of this case more generally, warrant the imposition upon the first respondent of a pecuniary penalty in the sum of $15,000.00.DECLARATORY RELIEF The parties are agreed that the court should grant declaratory relief in respect of the Agreed Contravention in the following terms, namely that:Milin Builders Pty Ltd contravened s.501 of the Fair Work Act 2009 by, through its employees, refusing Messrs Hardy and Miller entry to part of the Trilogy Apartment Building Site in Phillip ACT, namely a meal room, on 5 February 2016.