JKC Australia LNG Pty Ltd v Inpex Operations Australia Pty Ltd

Link copied
Case Copied 37 min read

CITATION:JKC Australia LNG Pty Ltd v Inpex Operations Australia Pty Ltd & Ors [2018] NTCA 6

PARTIES:JKC AUSTRALIA LNG PTY LTD (ABN 14 154 383 409)

v

INPEX OPERATIONS AUSTRALIA PTY LTD

(ABN 48 150 217 262)

and

ICHTHYS LNG PTY LTD

(ACN 150 217 299)

and

HUGH DAVIS

TITLE OF COURT:  COURT OF APPEAL OF THE NORTHERN TERRITORY

JURISDICTION:  CIVIL APPEAL from the SUPREME COURT exercising Territory jurisdiction

FILE NO:AP 9 of 2017 (21706782)

DELIVERED:  26 June 2018

HEARING DATE:  28 February 2018

JUDGMENT OF:  Grant CJ, Southwood J and Mildren AJ

CATCHWORDS:

ADMINISTRATIVE LAW – JUDICIAL REVIEW – CONSTRUCTION CONTRACTS (SECURITY OF PAYMENTS)

Whether adjudicator appointed under the Construction Contracts (Security of Payments) Act (NT) failed to provide procedural fairness – relevant issue identified by the adjudicator and the parties were given opportunity to address it – no failure to provide procedural fairness – appeal allowed – whether adjudicator a bona fide attempt to comply with the essential requirements of the Act – no notice of dispute given within the prescribed time – respondent liable to pay amount of the claim – no obligation in those circumstances to determine whether works identified in the payment claim undertaken and their value – notice of contention dismissed.

Construction Contracts (Security of Payments) Act (NT) ss 3, 4, 8, 10, 15, 20, 26, 27, 28, 29, 30, 33, 34, 38, 43, 45, 47, 48

AJ Lucas Operations Pty Ltd v Mac-Attack Equipment Hire Pty Ltd (2009) 25 NTLR 14, Amasya Enterprises Pty Ltd v Asta Developments (Aust) Pty Ltd (No 2) [2015] VSC 500, Brodyn Pty Ltdt/asTime Cost and Quality v Davenport (2004) 61 NSWLR 42, Independent Fire Sprinklers (NT) Pty Ltd v Sunbuild Pty Ltd (2008) 24 NTLR 15, John Holland Pty Ltd v TAC Pacific Pty Ltd [2009] QSC 205, Laing O’Rourke Australia Construction Pty Ltd v Samsung C&T Corporation [2016] WASCA 130, Maxcon Constructions Pty Ltd v Vadasz [2018] HCA 5, M & P Builders Pty Ltd v Norblast Industrial Solutions Pty Ltd (2014) 34 NTLR 162, Musico v Davenport [2003] NSWSC 977, Pacific General Securities Ltd & Anor v Soliman and Sons & Ors (2006) 196 FLR 388, Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4, Probuild Constructions (Aust) Pty Ltd vDDI Group Pty Ltd [2017] NSWCA 151, SZBEL v Minister for Immigration and Multicultural and Indigenous Affairs (2006) 228 CLR 152, Zurich Bay Holdings Pty Ltd v Brookfield Multiplex Engineering and Infrastructure Pty Ltd [2014] WASC 40, referred to.

REPRESENTATION:

Counsel:

Appellant:N Hutley SC with BA Millar

First Respondent:  A Wyvill SC with JW Roper

Second Respondent  A Wyvill SC with JW Roper

Third Respondent  No appearance

Solicitors:

Appellant:De Silva Hebron as town agent for DLA Piper Australia

First Respondent  Paul Maher Solicitors as town agent for Allens

Second Respondent:                   Paul Maher Solicitors as town agent for Allens

Third Respondent:  Not applicable

Judgment…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read JKC Australia LNG Pty Ltd v Inpex Operations Australia Pty L... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] NTCA 6
Decision Date

CaseChat Overview and Summary

In this case, JKC Australia LNG Pty Ltd (the appellant) appealed against a decision of the Supreme Court of the Northern Territory, which quashed a determination made by an adjudicator under the Construction Contracts (Security of Payments) Act (NT) (the Act). The primary dispute between the appellant and Inpex Operations Australia Pty Ltd (the respondent) involved the validity of an adjudication determination made by the adjudicator regarding a payment claim made by the appellant. The respondent disputed the amount claimed by the appellant, leading to the adjudication process being initiated. The main legal issues before the court were whether the adjudicator failed to provide procedural fairness and whether the adjudicator made a bona fide attempt to comply with the essential requirements of the Act. The court below had quashed the adjudicator's determination, finding that the adjudicator did not provide the respondent with procedural fairness by notifying it of the proposed conclusions that could not be easily anticipated, thus depriving the respondent of the possibility of a successful outcome.

The court's reasoning focused on the principles of procedural fairness and the adjudicator's compliance with the Act. The court held that while an error of law construing provisions of the Act which vest an adjudicator with jurisdiction to make a determination will render a determination a nullity, non-jurisdictional errors of law or fact made by an adjudicator in the process of making a bona fide attempt to carry out the functions conferred by the Act are not amenable to review. However, if an adjudicator has not made a bona fide attempt to comply with the essential requirements of the Act or if there has been a substantial denial of procedural fairness, an adjudication will be reviewable. The court below found that the adjudicator did not warn the parties that he was considering making a determination based on the implied terms in the EPC Contract and the Act, and did not provide the respondent with a fair opportunity to address that proposed basis. Therefore, the court below concluded there was jurisdictional error and quashed the determination.

The court allowed the appeal and set aside the order of the Supreme Court quashing the adjudicator's determination. The court held that the adjudicator's determination was valid and that the respondent was liable to pay the amount of the claim. The court found that there was no obligation for the adjudicator to determine whether the underlying work had been performed and correctly valued under the construction contract or whether the payment claim was a valid claim within the meaning of the Act, as the respondent had failed to give notice of dispute within the prescribed time. As a result, the respondent's contention that the order quashing the adjudicator's determination should stand was dismissed.

Orders

Orders of the court

Background

Background to the litigation

The second question in this appeal is the correctness of INPEX’s contention by notice that even if the Court below was in error about the failure to provide procedural fairness to INPEX, the order quashing the adjudicator’s determination should stand because the obligation to determine the payment dispute under s 33(1)(b) of the Act could not be validly discharged: (a) unless the adjudicator considered whether the underlying work had been performed and correctly valued under the construction contract; and (b) without determining whether the payment claim was a valid claim within the meaning of the Act.Factual background As the court below stated, INPEX are joint venturers in the Ichthys Gas Field Development Project (the Project). The Project consists of a central processing facility off the Western Australian coast connected by a pipeline to the onshore processing facilities at Bladin Point, which will include two LNG trains, LPG and condensate plants, product storage tanks, administration facilities and a materials offloading facility and jetty. By a construction contract dated 9 February 2012 (the EPC Contract), the appellant (JKC) was engaged by INPEX to provide engineering procurement, supply, construction and commissioning of onshore facilities for the Project for a contract price in the order of USD 13 billion. The works to be performed by JKC under the EPC Contract included what are called “Re-measurable Works”. This category of works included work involving module fabrication packages which were subcontracted to four subcontractors. On 3 November 2016, JKC issued two invoices to INPEX in respect of part of the Re-measurable Works, one for USD 205,825,452.00 and a separate invoice for GST on that amount. On 24 November 2016, INPEX issued a letter disputing USD 133,501,780.00 of the first invoice and USD 17,510,093.00 of the second invoice. On 3 January 2017, JKC served on INPEX an application under s 28 of the Act for adjudication of the resulting dispute (the Application). The Application did not seek a determination of the entire disputed amount. It sought a determination that an amount of USD 83,933,837.00 was owing by INPEX to JKC on the ground that, although it claimed an entitlement to the whole amount, the balance of the amounts claimed were not readily amenable to adjudication under the Act. In response, INPEX accepted that the EPC Contract was the relevant construction contract, disputed the jurisdiction of the third respondent (the Adjudicator) on a number of grounds not relevant to this appeal, and disputed in detail the merits of JKC’s entitlement to the USD 83,933,837.00 (the disputed sum). In due course the Adjudicator was appointed under the Act. As the Application consisted of 34 volumes of material, on 12 January 2017 the Adjudicator applied for, and the Construction Contracts Registrar granted, an extension of time within which to make a determination. By email to the parties on 25 January 2017, the Adjudicator sought further submissions from the parties as follows:GentlemenI have had the opportunity to review the parties’ submission and the EPC Contract. A possible issue arises with respect to uncertainty in the payment terms of the EPC Contract. The question is: whether the provisions implied into deficient construction contracts by section 20 of the NT Act should or should not be imported into the EPC Contract?I invite both parties to address this question, in no more than two pages, by close of business Friday, 27 January 2017. Submissions from both parties must be strictly confined to the question raised. Please provide electronic copies of relevant authorities.

Evidence

Evidence Before The Court

Decision

Reasons for decision

On 28 April 2017 the Determination was quashed by the court below.The decision at first instance In the Court below, INPEX sought relief in the nature of certiorari to quash the Determination or, alternatively, a declaration that the Determination was void and of no force and effect. Although all the parties were agreed that the Adjudicator’s finding that the implied terms in Division 5 of the Schedule to the Act were imported into the EPC Contract was plainly wrong, the court below observed that by itself did not mean that the decision was amenable to judicial review. Her Honour noted that an error of law construing provisions of the Act which vest an adjudicator with jurisdiction to make a determination will render a determination a nullity reviewable by a court[1], but non-jurisdictional errors of law or fact made by an adjudicator in the process of making a bona fide attempt to carry out the functions conferred by the Act are not amenable to review. Her Honour held, citing Brodyn Pty Ltdt/asTime Cost and Quality[2] and a number of decisions of the Supreme Court to the same effect,[3] that if an adjudicator has not made a bona fide attempt to comply with the essential requirements of the Act, or if there has been a substantial denial of procedural fairness, an adjudication will be reviewable. There was no challenge to this part of the judgment below by any of the parties. The principal argument which was mounted by INPEX in the court below was that there was a substantial failure by the Adjudicator to accord INPEX natural justice. INPEX contended that the Adjudicator did not warn the parties that he was considering making a determination on the basis that both parties had misconstrued the EPC Contract and the Act and that he intended to proceed on the basis that cl 6 was implied into the contract, that INPEX had not complied with cl 6, and as a consequence INPEX was obliged to pay the full amount regardless of the merits of its claim. It was put that this deprived INPEX of the opportunity to put material before the Adjudicator as to why that result should not follow even if the implied terms were imported into the EPC Contract. For example, it was suggested that INPEX could have submitted that the payment claim did not comply with the requirements of the EPC Contract by failing to supply proper particulars, and so did not attract the operation of cl 6; or that JCK was precluded by estoppel or waiver from relying on any failure of INPEX to comply with the 14 day requirement for disputing liability in cl 6; or that the Adjudicator had an obligation under the Act to determine if any money was owing, which, at a minimum, required him to be satisfied that the work had been done and valued in accordance with the terms of the EPC Contract. The court below accepted INPEX’s submissions. Her Honour held that: (1) procedural fairness required the Adjudicator to notify the parties of “proposed conclusions that were not put forward by the parties and could not be easily anticipated”;[4] and (2) a failure to provide such procedural fairness which deprived a party of the possibility of a successful outcome[5] will enable the Court to set aside the adjudication. As the Adjudicator had not given INPEX reasonable notice of the basis upon which he intended to make his determination and a fair opportunity to address that proposed basis, and make submissions as to why he should not decide that way, her Honour found there was jurisdictional error and made an order in the nature of certiorari quashing the Determination.The ground of appeal

Ratio Decidendi

Legal Principle Established