Costojic Pty Ltd v Whatareya Pty Ltd

Link copied
Case Copied 46 min read

CITATION:Costojic Pty Ltd v Whatareya Pty Ltd & Anor [2023] NTSC 32      

PARTIES:COSTOJIC PTY LTD


(ACN 601 969 064)

v

WHATAREYA PTY LTD


(ACN 128 309 857)

AND

DEO, Jaswant

TITLE OF COURT:  SUPREME COURT OF THE NORTHERN TERRITORY

JURISDICTION:  SUPREME COURT exercising Territory jurisdiction

FILE NO:2022-02553-SC

DELIVERED:  12 April 2023

HEARING DATE:  6 March 2023

JUDGMENT OF:  Brownhill J

CATCHWORDS:

BUILDING AND CONSTRUCTION – Adjudication – Judicial review – Payment claims – Time in which claim is brought – Statutory precondition to the exercise of the power to adjudicate – Where construction contract allows a repeat claim to be made – Ground of review not made out.

BUILDING AND CONSTRUCTION – Adjudication – Judicial review – Payment claims – Procedural fairness – Whether actual or reasonable notice of determination based on issue or principle – Ground of review not made out.

BUILDING AND CONSTRUCTION – Adjudication – Judicial review – Payment claims – Procedural fairness – Whether opportunity to be heard in relation to an award of interest – Ground of review not made out.

K & J Burns Electrical Pty Ltd v GRD Group (NT) Pty Ltd (2011) 29 NTLR 1, applied.

Hall Contracting Pty Ltd v MacMahon Contractors Pty Ltd (2014) 34 NTLR 17; JKC Australia LNG Pty Ltd v INPEX Operations Australia Pty Ltd (2018) 41 NTLR 149; Minister for Immigration and Multicultural Affairs v Eshetu (1999) 197 CLR 611; R v Federal Court of Australia; Ex parte WA National Football League (1979) 143 CLR 190, referred to.

AJ Lucas Operations Pty Ltd v Mac-Attack Equipment Hire Pty Ltd (2009) 25 NTLR 14, distinguished.

Construction Contracts (Security of Payments) Act 2004 (NT) ss 3, 4, 7A, 8, 27, 28, 29, 33, 34, 35, 39

Construction Contracts (Security of Payments) Legislation Amendment Act 2019 (NT)

Department of the Attorney-General and Justice, Review of the Construction Contracts (Security of Payments) Act (NT) (Issues Paper, October 2017)

Economic Policy Scrutiny Committee, Parliament of the Northern Territory, Inquiry into the Construction Contracts (Security of Payments) Legislation Amendment Bill 2019 (Report, August 2019)

Explanatory statement, Construction Contracts (Security of Payments) Legislation Amendment Bill 2019

Northern Territory, Parliamentary Debates, Legislative Assembly, 14 August 2019, 6774 (Natasha Fyles, Minister for Justice and Attorney-General)

REPRESENTATION:

Counsel:

Plaintiff:JW Roper SC             

First Defendant:  T Ambrose    

Second Defendant:  No appearance              

Solicitors:

Plaintiff:Maher Raumteen Solicitors           

First Defendant:  Baker Merz Lawyers

Second Defendant:  No appearance  

Judgment category classification:    B

Judgment ID Number:  Bro2305                  

Number of pages:  42       

IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWIN

Costojic Pty Ltd v Whatareya Pty Ltd & Anor [2023] NTSC 32

No. 2022-02553-SC

BETWEEN:

COSTOJIC PTY LTD
(ACN 601 969 064)

Plaintiff

AND:

WHATAREYA PTY LTD
(ACN 128 309 857)

First Defendant

AND:

JASWANT DEO

Second Defendant

CORAM:    BROWNHILL J

REASONS FOR JUDGMENT

(Delivered 12 April 2023)

  1. This is an application for judicial review of a determination by an adjudicator under the Construction Contracts (Security of Payments) Act 2004 (NT)…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Costojic Pty Ltd v Whatareya Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2023] NTSC 32
Decision Date

CaseChat Overview and Summary

The court was asked to consider an application for judicial review of a determination made by an adjudicator under the Construction Contracts (Security of Payments) Act 2004 (NT). The application, brought by Costojic Pty Ltd, contested the adjudicator's decision to adjudicate on a payment claim made by Whatareya Pty Ltd, arguing that the claim was out of time, the adjudicator had denied natural justice by making part of the determination on a basis not put to him by either party, and the adjudicator had determined interest payable at a rate not put to him by either party. The central issue was whether the adjudicator's determination was legally sound and if the process adhered to the principles of natural justice.

The court examined whether the adjudicator had the authority to adjudicate on the payment claim that was submitted beyond the stipulated time under the contract. It also considered if the adjudicator's decision to include matters not presented by the parties, such as the basis of the determination and the interest rate, constituted a denial of natural justice. The court was required to determine if the adjudicator's actions were within the scope of his powers and if they were procedurally fair.

In assessing the arguments, the court found that the adjudicator did not err in law by deciding on the payment claim despite it being out of time. The court held that the adjudicator had the discretion to determine the claim under the provisions of the Act. Regarding the natural justice argument, the court determined that the adjudicator did not deny natural justice by considering issues not explicitly put to him by the parties, as long as these issues were within the scope of the claim and the contract. The court also concluded that the adjudicator's decision to calculate interest at a specific rate was reasonable and did not amount to a failure to adhere to natural justice principles. The application for judicial review was dismissed.

The court ordered that the application for judicial review be dismissed and that Whatareya Pty Ltd recover its costs of the application from Costojic Pty Ltd.

Background

Background to the litigation

This is an application for judicial review of a determination by an adjudicator under the Construction Contracts (Security of Payments) Act 2004 (NT) (‘the Act’). The issues are whether the adjudicator should have dismissed the application for adjudication because it related to a payment claim made out of time, whether the adjudicator denied the parties natural justice by making part of the determination on a basis not put to him by either party, or by determining interest payable at a rate not put to him by either party.Background The following facts are not in dispute. The plaintiff (‘Costojic’) was responsible for a subdivision of land in Zuccoli into 10 separate lots. On 12 October 2020, Costojic and the first defendant (‘Whatareya’) entered into a contract under which Whatareya was to undertake earth and drainage works for the subdivision. The contract was a fixed price contract for a lump sum of $438,819.15. The contract comprised a short instrument of agreement (‘IOA’) executed by the parties, with three attachments comprising: (i) the ‘AS4000-1997 General Terms and Conditions’ (‘T&Cs’[1]); (ii) drawings and technical specifications; and (iii) a costs agreement framework. An engineering company (‘ADG’) were appointed as the superintendent under the contract. Up to September 2021, Whatareya issued four progress claims to ADG under the contract for works in the period up to April 2021. A total of $324,517.59 was allowed and paid by Costojic to Whatareya. After allowed variations, retentions and deductions, the remaining value of the contract was some $135,381.38. On 11 January 2021, Whatareya encountered a water main in excavating for sewerage works. It contacted ADG by phone and then sent an email to ADG informing ADG of the presence of the water main. The water main was not shown on any of the drawings forming part of the contract. Its presence caused delay to the works on the subdivision. The parties were in dispute about whether it was Costojic’s obligation to identify the existence of the water main (by inclusion in the drawings) or whether it was Whatareya’s obligation to identify its existence by undertaking a ‘Dial Before You Dig’ search before performing the works. The parties were also in dispute about the extent and nature of the delay caused. In October 2021, Whatareya issued a progress claim (‘payment claim 5’) to ADG, which allowed a discount of $40,000 to its claim for payment as liquidated damages on account of the water main. On 22 October 2021, ADG certified the amount payable for payment claim 5 as $128,067.28. That amount was not paid by Costojic within the time provided for by the contract or prior to Whatareya’s application for the adjudicator’s determination. On 23 November 2021, ADG issued a certificate of practical completion. On 17 June 2022, Whatareya issued a progress claim (‘payment claim 6’) which included a claim for $172,260.61 in respect of the claim under payment claim 5, and a claim for $101,515.77 for ‘disruption claims’ referable to the water main, of which only the claim in relation to ‘Disruption 1’ (‘Disruption Claim 1’) is in issue in these proceedings.

Decision

Reasons for decision

Ratio Decidendi

Legal principle established