Independent Fire Sprinklers (NT) Pty Ltd v Sunbuild Pty Ltd

Link copied
Case Copied 21 min read

Independent Fire Sprinklers (NT) Pty Ltd v Sunbuild Pty Ltd

[2008] NTSC 46

PARTIES:  INDEPENDENT FIRE SPRINKLERS
(NT) PTY LTD
(ACN 094 910 844)
v
SUNBUILD PTY LTD
(ACN 061 313 979)
TITLE OF COURT:  SUPREME COURT OF THE
NORTHERN TERRITORY
JURISDICTION:  SUPREME COURT OF THE TERRITORY EXERCISING TERRITORY JURISDICTION
FILE NO:  NO 140 OF 2008 (20828941)
DELIVERED:  14 November 2008
HEARING DATES:  29 October 2008
JUDGMENT OF:  MILDREN J
CATCHWORDS: 

BUILDING AND CONTRUCTION – construction contract – adjudicator’s determination – subsequent judgment – whether judgment should be stayed or set aside – whether adjudicator has jurisdiction to determine whether the application was served within time – whether determination void – whether other relief available to the plaintiff – Construction Contract (Security of

Payment Act (NT) – summons dismissed with costs

Statutes:

Building and Construction Industry Security Payment Act 1999 (NSW), s 17

Construction Contract (Security of Payments) Act (NT), cl 6(2) of Div 5 of

the Schedule, cl 6(2)(b) of Div 5 of the Schedule, s 3, s 4, s 5, s 8,
s 8(a), s 19, s 20, s 23(1), s 26, s 28, s 28(1), s 28(2), s 29, s 33,
s 33(1), s 33(1)(a), s 33(1)(a)(ii), s 33(1)(a)(iii), s 36(2), s 39(1), s 40,
s 45, s 45(1), s 46(b), s 47, s 47(4), s 48(1)

Interpretation Act, s 25

Citations:

Applied:

Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR

355

Followed:

Brodyn Pty Ltd trading as Time Cost and Quality v Davenport & Anor

(2004) 61 NSWLR 421

Parisienne Basket Shoes Pty Ltd & Ors v Whyte (1937–1938) 59 CLR 369

Referred to:

Bunbury Foods Pty Ltd v National Bank of Australasia Ltd (1984) 153 CLR

491

Cripps & Son v Wickenden [1973] 1 WLR 944

Trans Australian Construction Pty Ltd v Nilsen (SA) Pty Ltd [2008] NTSC

42

REPRESENTATION:

Counsel:

Plaintiff:  J Sexton SC with A Young
 Defendant:  A Wyvill

Solicitors:

 Plaintiff:  Ward Keller
 Defendant:  Minter Ellison

Judgment category classification: B

Number of pages:  19
IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWIN

Independent Fire Sprinklers (NT) Pty Ltd v Sunbuild Pty Ltd

[2008] NTSC 46

No. 140 of 2008 (20828941)

BETWEEN:

INDEPENDENT FIRE SPRINKLERS
(NT) PTY LTD

(ACN 094 910 844)

Plaintiff

AND:

SUNBUILD PTY LTD

(ACN 061 313 979)

Defendant

CORAM:  MILDREN J

REASONS FOR JUDGMENT

(Delivered 14 November 2008)

  1. This is an application by summons on originating motion to set aside a

    judgment registered in this Court on 17 October 2008 in favour of the

    defendant against the plaintiff in the sum of $362,160.20.

    Factual background

  2. The plaintiff and defendant contracted on the terms set out in a written

contract dated 6 November 2006 for the installation by the plaintiff of the
fire protection system at the Evolution on Gardiner project in Darwin of

which the defendant, Sunbuild, is the builder.

  1. In or about June 2007 disputes arose between the parties. The plaintiff, IFS,

contends that Sunbuild requested IFS to agree to variations to…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Independent Fire Sprinklers (NT) Pty Ltd v Sunbuild Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2008] NTSC 46
Decision Date

CaseChat Overview and Summary

Independent Fire Sprinklers (NT) Pty Ltd (IFS) filed an application seeking to set aside a judgment in favour of Sunbuild Pty Ltd (Sunbuild), which was registered in the court on 17 October 2008 for the sum of $362,160.20. The dispute between IFS and Sunbuild arose from a written contract in June 2007, with IFS contending that the contract was either repudiated or discharged by agreement. Sunbuild initiated proceedings claiming sums due under three invoices for increased costs, and subsequently served a further notice under clause 23 of the contract. IFS argues that the adjudicator lacked jurisdiction to make the determination, as the payment dispute arose on 11 June 2008, outside the 90-day time limit under section 23(1) of the relevant Act.

The court was required to decide whether the adjudicator had jurisdiction to make the determination that led to the judgment in favour of Sunbuild. The court considered the structure of the Act, the objects of the Act, and the provisions governing adjudication of disputes. The court also examined the contract between the parties and the notices served by Sunbuild. IFS argued that clause 23.3 of the contract was a draconian provision and that the payment dispute arose immediately or shortly after the service of the payment claim. The court had to determine whether the adjudicator's decision was correct and whether the payment dispute arose within the time limit stipulated by the Act.

The court found that the adjudicator correctly concluded that the payment dispute arose 28 days after the service of the payment claim and that Sunbuild had complied with section 28(1) of the Act. The court held that the provisions in the Schedule, Division 5 were implied into the contract and that the adjudicator was right in his conclusion. Therefore, the court dismissed IFS's application to set aside the judgment. The court found that the adjudicator had jurisdiction to make the determination, and the judgment in favour of Sunbuild was upheld.

The final orders of the court were that IFS's application to set aside the judgment was dismissed, and the judgment in favour of Sunbuild was upheld. The court found that the adjudicator had jurisdiction to make the determination, and the payment dispute arose within the time limit stipulated by the Act. The court dismissed IFS's argument that the adjudicator lacked jurisdiction and that the payment dispute arose outside the time limit. The court's decision upheld the judgment in favour of Sunbuild, and IFS's application to set it aside was dismissed.

Orders

Orders of the court

Background

Background to the litigation

This is an application by summons on originating motion to set aside a judgment registered in this Court on 17 October 2008 in favour of the defendant against the plaintiff in the sum of $362,160.20. Factual background The plaintiff and defendant contracted on the terms set out in a written In or about June 2007 disputes arose between the parties. The plaintiff, IFS, IFS complains that in these circumstances the contract was either repudiated by Sunbuild or discharged by agreement. Sunbuild commenced proceedings in action No 35 of 2008 on 14 March 2008 claiming sums due under three invoices for the increased costs of On or about 11 June 2008, Sunbuild served a further notice under cl 23 of In these proceedings, IFS contends that the adjudicator had no jurisdiction to make the determination which has led to the judgment because the payment dispute arose on 11 June 2008 and hence was outside of the 90 day time limit provided for by s 23(1) of the Act. The structure of the Act The preamble of the Act provides it is “an Act to secure payments under Section 3 sets out the objects of the Act, namely, to promote security of payments under constructions contracts which is to be achieved by facilitating timely payments between the parties to construction contracts, to provide for the rapid resolution of payment disputes arising under The Act provides that the Act applies to construction contracts as defined by Section 28(2) states the basic requirements of an application and the details It is apparent that an adjudication under the Act does not finally determine the rights of the parties. Section 47 provides that the provisions of Part 3 dealing with the adjudication of disputes: “... does not prevent a party to a construction contract from starting proceedings before an arbitrator or other person or a court or other body in relation to a dispute or other matter arising under the contract.” Section 26 provides that the object of an adjudication of a payment dispute is to determine the dispute fairly and as rapidly, informally and inexpensively as possible. It is not in dispute that Sunbuild relying on cl 23.3 of the contract notified IFS of the difference between the cost, losses, expenses and damages it Counsel for the plaintiff submitted that cl 23.3 is a draconian provision. That may well be so and it is difficult to comprehend why a subcontractor would agree to be bound by such a provision. However, a subcontractor in the position of IFS is not necessarily without remedies if the Builder does Counsel for the plaintiff submitted that the invoice in question was a payment claim within the meaning of that term as defined by s 4. Further, it was submitted by the plaintiff, that the amount claimed in the payment claim was due to be paid under the contract because cl 23.3 provides that the “difference is a debt due and payable upon such notice by the Subcontractor to the Builder”. It is not in dispute that the amount has not been paid. Therefore, counsel for the plaintiff submitted that the payment dispute arose immediately or within a very short time after service of that

Evidence

Evidence Before The Court

Decision

Reasons for decision

The learned adjudicator held that the provisions in the Schedule, Division 5 were implied into the contract. In my opinion he was right and therefore he correctly concluded that the payment dispute arose 28 days after service of the payment claim and that the defendant had complied with s 28(1) of the Act. Conclusion

Ratio Decidendi

Legal Principle Established