M & P Builders Pty Limited v Norblast Industrial Solutions Pty Ltd

Link copied
Case Copied 18 min read

M & P Builders Pty Limited v Norblast Industrial Solutions Pty Ltd & Anor

[2014] NTSC 25

PARTIES:M & P BUILDERS PTY LIMITED

v

NORBLAST INDUSTRIAL SOLUTIONS PTY LTD

AND

BREARS, John

TITLE OF COURT:  SUPREME COURT OF THE NORTHERN TERRITORY

JURISDICTION:  SUPREME COURT OF THE NORTHERN TERRITORY EXERCISING TERRITORY JURISDICTION

FILE NO:36 of 2014 (21422889)

DELIVERED:  27 June 2014

HEARING DATE:  3 June 2014

JUDGMENT OF:  SOUTHWOOD J

CATCHWORDS:

JUDICIAL REVIEW – decision of an adjudicator – construction of contract – extension of prescribed time for determination – availability of merits review –procedural fairness

Construction of Contracts (Security of Payments) Act 2004 (NT) s 20, s 27, s 33, s 33(1)(b), s 33(2), s 33(3), s 34(2), s 34(2)(a), s 34(3)(a), s 34(3)(b), s 34(4), Schedule Division 5 6(2)(a), Division 5 6(2)(b)
Interpretation Act1978 (NT) s 24(2)

A J Lucas Operations Pty Ltd v Mac-Attack Equipment Hire Pty Ltd and Another (2009) 25 NTLR 1; Hall Contracting Pty Ltd v Macmahon Contractors Pty Ltd & Anor [2014] NTSC 20; Musico v Davenport [2003] NSWSC 977; Trans Australian Constructions Pty Limited v Nilsen (SA) Pty Ltd and Another (2008) 23 NTLR 123; Independent Fire Sprinklers (NT) Pty Ltd v Sunbuild Pty Ltd (2008) 24 NTLR 15; Zurich Bay Holdings Pty Ltd v Brookfield Multiplex Engineering and Infrastructure Pty Ltd [2014] WASC 40, referred to

REPRESENTATION:

Counsel:

Plaintiff:W Roper

First Defendant:  C Cureton

Solicitors:

Plaintiff:De Silva Hebron

First Defendant:  Squire Patton Boggs

Judgment category classification:   B

Judgment ID Number:  Sou1405

Number of pages:  17

IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWIN

M & P Builders Pty Limited v Norblast Industrial Solutions Pty Ltd & Anor

[2014] NTSC 25

No. 36 of 2014 (21422889)

BETWEEN:

M & P BUILDERS PTY LIMITED

(ACN 009 627 383)

Plaintiff

AND:

NORBLAST INDUSTRIAL SOLUTIONS PTY LTD

(ACN 110 217 671)

First Defendant

AND:

JOHN BREARS
  Second Defendant

CORAM:    SOUTHWOOD J

REASONS FOR JUDGMENT

(Delivered 27 June 2014)

Introduction

  1. This is an application for judicial review of a determination of the second defendant as an adjudicator appointed under the Construction of Contracts (Security of Payments) Act (the Act).

  2. On 21 April 2104 the second defendant determined that the plaintiff should pay the first defendant the sum of $195,360.00 in respect of invoice 9258, $193,966.00 in respect of invoice 9305 and $127,215.00 in respect of invoice 9454, being a total of $516,571.00, on or before 21 May 2014. He did so on the basis that the plaintiff was liable to make those payments in accordance with implied condition 6(2)(b) of Division 5 of the Schedule to the Act because the plaintiff did not give the first defendant notices of dispute for each of the three invoices in accordance with implied condition 6(2)(a) and (3) of Division 5 of the Schedule to the Act.

  3. Condition 6(2) of the Schedule to the Act states:

    The party must –

    (a)Within 14 days after receiving the payment claim –

    (i)Give…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read M & P Builders Pty Limited v Norblast Industrial Solutions P... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2014] NTSC 25
Decision Date

CaseChat Overview and Summary

In the case of M & P Builders Pty Limited v Norblast Industrial Solutions Pty Ltd, the plaintiff sought to challenge the adjudicator's determinations regarding payment disputes related to subcontracted works for the RAAF Air Traffic Control Tower in Darwin. The plaintiff, a subcontractor to Spotless Facilities Services Pty Ltd, was engaged by the Australian Department of Defence for corrosion prevention works. Norblast Industrial Solutions Pty Ltd, the first defendant, was subcontracted by the plaintiff to provide access scaffolding and associated encapsulation and carry out blasting and repainting. The case involved three invoices: 9454, 9258, and 9305, with the first defendant seeking payment for stand-down periods and work interruptions due to health concerns and a cyclone.

The legal issues before the court were whether there was a jurisdictional error in the adjudicator's determination concerning invoice 9454, whether the adjudicator had the authority to extend the prescribed time for making a determination, and if the plaintiff was entitled to a merits review or procedural fairness in the adjudication process. The court had to assess whether the adjudicator's determinations were legally sound and whether there was a breach of procedural fairness.

The court found that there was a jurisdictional error in the adjudicator's determination regarding invoice 9454 as the adjudicator exceeded the prescribed time limit for making the determination. However, this did not vitiate the other payment disputes. Consequently, the court quashed the adjudicator's determination that the plaintiff was liable to pay $127,215.00 to the first defendant for invoice 9454, as well as the determination that the plaintiff should pay interest of $918.39 on that amount. The court dismissed the plaintiff's application to quash the determinations concerning invoices 9258 and 9305, finding no grounds for doing so. The plaintiff's request for a merits review or declarations that the determinations were void and of no effect was also dismissed.

The court made the following orders: the adjudicator's determination that the plaintiff should pay $127,215.00 in respect of invoice 9454 is quashed; the adjudicator's determination that the plaintiff should pay interest of $918.39 on the amount of $127,215.00 is quashed; and the plaintiff's application to quash the determinations of the adjudicator in respect of the payment disputes involving invoices 9258 and 9305, or alternatively for declarations that those determinations are void and of no effect, is dismissed. The court will hear the parties further as to costs and any ancillary orders.

Orders

Orders of the court

(i) The second defendant’s determination that the plaintiff should pay the first defendant $127,215.00 in respect of invoice 9454 is quashed.

(ii) The second defendant’s determination that the plaintiff should pay the first defendant interest of $918.39 on the amount of $127,215.00 is quashed.

(iii) The plaintiff’s application to quash the determinations of the second defendant in respect of the payment disputes involving invoices 9258 and 9308, or alternatively declarations that those determinations are void and of no affect, is dismissed.

Background

Background to the litigation

The first defendant concedes that there was no payment dispute about invoice 9454.The background facts Spotless Facilities Services Pty Ltd is engaged by the Australian Department of Defence to manage certain repairs and maintenance contracts on their behalf. The plaintiff is subcontracted to Spotless Facilities Services Pty Ltd for corrosion prevention works upon the RAAF Air Traffic Control Tower in Darwin. The first defendant is subcontracted to the plaintiff to provide access scaffolding and associated encapsulation and carry out blasting and repainting of steel works being part of the RAAF Air Traffic Control Tower in Darwin. The first defendant started providing the services it subcontracted to undertake on 11 July 2013. However, the works were seriously interrupted from time to time and the site is now in indefinite shutdown. On 11 September 2013, which was during the final stages of the erection and encapsulation of scaffold to the East side of the tower, workers reported experiencing a stinging eye sensation. On 12 September 2013 work on the East side of the tower was put on standby by Spotless Facilities Services Pty Ltd to enable any health issues to be investigated by an Occupational Hygienist. Work continued on the West side of the tower and the works in that location were completed by 20 November 2013. On 22 November 2013 due to an imminent issue of a cyclone warning and watch the Cyclone Action Plan for the site necessitated the removal of the encapsulation and the boards from the remaining scaffold, leaving only scaffolding tubing in place. On 26 November 2013 the first defendant started rebuilding the scaffold on the East side of the tower. On 28 November 2014 the first defendant rendered invoice 9258 which charged for stand down at RAAF Darwin ATC corrosion prevention works. In the top right hand corner of the invoice there appears the following statement: TERMS: Net 30, which means that the total amount outstanding in the invoice was to be paid and received by the first defendant within 30 days. For the stand down of the UHP Hydro Blaster the first defendant charged a daily rate of $1,500.00. For stand down of the East side scaffold and encapsulation the first defendant charged a daily rate of $1,000.00. For labour stand down the first defendant charged an hourly rate of $100.00. For labour to remove the scaffold and planks the first defendant charged an hourly rate of $140.00. On 2 December 2013 the Occupational Hygienist received a report from an employee of the first defendant who had developed a skin rash. The site was closed and the first defendant was put on standby while an investigation was carried out. On 20 December 2013 Spotless Facilities Services Pty Ltd instructed the plaintiff to stand-down for the Christmas break and to make the site safe and secure in accordance with the site Cyclone Action Plan. On 20 December 2013 the first defendant advised the plaintiff that it would be on stand down from 20 December 2013 to 2 January 2014. On 23 and 24 December the first defendant again stripped the scaffold and removed the planks from the site.

Decision

Reasons for decision

In the circumstances, there was no bar to the simultaneous adjudication of these three payment disputes and the jurisdictional error which arises in the payment dispute about invoice 9454 does not vitiate the other payment disputes. However, as there was a jurisdictional error in the payment dispute about invoice 9454 the second defendant’s determination that the plaintiff was liable to pay $127,215.00 to the first defendant for that claim and his determination that the plaintiff was liable to pay $918.39 interest on that amount should be quashed.Conclusion In the circumstances, I make the following orders:(i)The second defendant’s determination that the plaintiff should pay the first defendant $127,215.00 in respect of invoice 9454 is quashed.(ii)The second defendant’s determination that the plaintiff should pay the first defendant interest of $918.39 on the amount of $127,215.00 is quashed.(iii)The plaintiff’s application to quash the determinations of the second defendant in respect of the payment disputes involving invoices 9258 and 9305, or alternatively declarations that those determinations are void and of no affect, is dismissed. I will hear the parties further as to costs and any ancillary orders

Ratio Decidendi

Legal principle established