HIGH COURT OF AUSTRALIA
GAGELER CJ,
GORDON, EDELMAN, STEWARD AND GLEESON JJDAVID HARVEY & ORS APPELLANTS
AND
MINISTER FOR PRIMARY INDUSTRY AND
RESOURCES & ORS RESPONDENTSHarvey v Minister for Primary Industry and Resources
[2024] HCA 1
Date of Hearing: 5 September 2023
Date of Judgment: 7 February 2024D9/2022
ORDER
1.Appeal allowed.
2.Set aside order 1 of the orders made by the Full Court of the Federal Court of Australia on 29 April 2022 and in its place:
(a)order that the appeal be allowed;
(b)declare that the grant of ML 29881 under s 40(1)(b)(ii) of the Mineral Titles Act 2010 (NT) is a future act that is the creation of a right to mine for the sole purpose of the construction of an infrastructure facility associated with mining within s 24MD(6B)(b) of the Native Title Act 1993 (Cth); and
(c)order that the first respondent be restrained from deciding the application for ML 29881 until completion of the procedures in s 24MD(6B) of the Native Title Act 1993 (Cth).
3.Each party bear its own costs of the appeal.
On appeal from the Federal Court of Australia
Representation
S A Glacken KC with R W Kruse for the appellants (instructed by Northern Land Council)
S B Lloyd SC with L S Peattie for the first and second respondents (instructed by Solicitor for the Northern Territory)
R N Traves KC with M A Eade for the third respondent (instructed by Ward Keller)
Notice: This copy of the Court's Reasons for Judgment is subject to formal revision prior to publication in the Commonwealth Law Reports.
GAGELER CJ, GORDON, STEWARD AND GLEESON JJ. The McArthur River Project is an enterprise carried on by the third respondent, Mount Isa Mines Limited ("Mt Isa Mines"), in the Northern Territory. The McArthur River Project comprises the mining of zinc-lead-silver ore, the processing, treatment and concentration of this ore, its storage, and its transportation for sale. The ore concentrate must travel 120 kilometres by road to the "Bing Bong" loading facility located on the Gulf of Carpentaria. There it is loaded onto a bulk-carrier vessel for transhipment to larger ocean-going ships. This part of the Gulf is shallow, and the bulk‑carrier must use a navigation channel which needs to be maintained by regular dredging. The resulting dredged sediment is pumped onshore to a Dredge Spoil Emplacement Area ("DSEA"), which is of limited capacity and has been filling up. In 2013, Mt Isa Mines applied for a new mineral lease (to be called "ML 29881") under the Mineral Titles Act 2010 (NT) to enable it to construct a new DSEA on a pastoral lease it owns nearby the Bing Bong loading facility.
The first and second appellants, Mr Harvey and Mr Simon, are native title holders in respect of the land comprising the pastoral lease.[1] The third appellant is the relevant prescribed body corporate for the purposes of the Native Title Act 1993 (Cth). The proposed grant of ML 29881 will be…
Keep reading for free
Create a free CaseChat account to read Harvey v Minister for Primary Industry and Resources and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2024] HCA 1
- Decision Date
CaseChat Overview and Summary
The central legal issues before the High Court of Australia were whether the proposed grant of ML 29881 constituted the creation of a right to mine for the sole purpose of constructing an infrastructure facility associated with mining, as contemplated by section 24MD(6B)(b) of the *Native Title Act*. This required the Court to determine whether the definition of "infrastructure facility" in section 253 of the Act was exhaustive and, if so, whether the DSEA qualified as such a facility. The Court also had to consider the interpretation of the phrase "associated with mining" in the context of the proposed DSEA.
The High Court, in allowing the appeal, reasoned that the definition of "infrastructure facility" in section 253 of the *Native Title Act*, when considered in light of the Explanatory Memorandum accompanying the legislation, should be interpreted as exhaustive. The Court found that the DSEA, being a facility specifically for the disposal of spoil generated by dredging operations directly linked to mining, fell within the ordinary meaning of an "infrastructure facility" and was indeed "associated with mining". Consequently, the Court declared that the grant of ML 29881 was a future act that triggered the procedural rights under section 24MD(6B)(b) of the Act. The Court ordered that the Minister be restrained from deciding the application for ML 29881 until the prescribed procedures under section 24MD(6B) were completed.
Orders
Orders of the court
1. Appeal allowed.
2. Set aside order 1 of the orders made by the Full Court of the Federal Court of Australia on 29 April 2022 and in its place:
(a) order that the appeal be allowed;
(b) declare that the grant of ML 29881 under s 40(1)(b)(ii) of the Mineral Titles Act 2010 (NT) is a future act that is the creation of a right to mine for the sole purpose of the construction of an infrastructure facility associated with mining within s 24MD(6B)(b) of the Native Title Act 1993 (Cth); and
(c) order that the first respondent be restrained from deciding the application for ML 29881 until completion of the procedures in s 24MD(6B) of the Native Title Act 1993 (Cth).
3. Each party bear its own costs of the appeal.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
Established by: GAGELER CJ, GORDON, STEWARD AND GLEESON JJ,