Harvey v Minister for Primary Industry and Resources

Link copied
Case Copied 80 min read

FEDERAL COURT OF AUSTRALIA

Harvey v Minister for Primary Industry and Resources [2022] FCAFC 66 

Appeal from: Friday v Minister for Primary Industry and Resources [2021] FCA 794
File number: NTD 16 of 2021
Judgment of: JAGOT, CHARLESWORTH AND O'BRYAN JJ
Date of judgment: 29 April 2022
Catchwords:

NATIVE TITLE – where the first respondent intends to grant a mineral lease (ML 29881) to the third respondent under the Mineral Titles Act 2010 (NT) – where land subject to the proposed lease would be used for the construction of a “dredge spoil emplacement area” to deposit dredged material from a loading facility located on adjacent land subject to a mineral lease already held by the third respondent – where loading facility is used to load ore concentrate from the McArthur River Mine for transhipment to ocean going vessels for export – whether the proposed grant of ML 29881 is a future act within s 24MD(6B)(b) of the Native Title Act 1993 (Cth), being the “creation of a right to mine for the sole purpose of the construction of an infrastructure facility associated with mining”

STATUTORY INTERPRETATION – interpretation of s 24MD(6B)(b) of the Native Title Act – meaning of “a right to mine” in the context of the Native Title Act – meaning of “infrastructure facility” as defined by s 253 of the Native Title Act

Legislation:

Acts Interpretation Act 1901 (Cth) ss 13(1), 15AB(1)

Aboriginal Land Rights (Northern Territory) Act 1976 (Cth) s 3(1)

Native Title Act 1993 (Cth) ss 3, 24AA, 24MB, 24MD(1), 24MD(6A), 24MD(6B), 24OA, 25, 26(1)(c)(i), 28, 29, 227, 233, 253

Native Title Amendment Act 1998 (Cth)

Native Title Amendment Bill 1993 (Cth)

Native Title Amendment Bill 1997 (Cth)

Native Title Amendment Bill (No 2) 1997 (Cth)

Native Title Amendment Bill 1998 (Cth)

Explanatory Memorandum, Native Title Amendment Bill 1993 (Cth)

Explanatory Memorandum, Native Title Amendment Bill (No 2) 1997 (Cth)

Supplementary Explanatory Memorandum, Native Title Amendment Bill (No 2) 1997 (Cth)

McArthur River Project Agreement Ratification Act 1992 (NT)

McArthur River Project Agreement Ratification Amendment Act 1993 (NT)

Mineral Titles Act 2010 (NT) ss 4(1), 8, 12(1), 14, 40(1)(b)(ii), 44(1), 71, 72, 74(2)

Mining Act 1980 (NT)

Cases cited:

Banjima People v State of Western Australia (No 2) [2013] FCA 868; 305 ALR 1

CIC Insurance Ltd v Bankstown Football Club Ltd [1997] HCA 2; 187 CLR 384

Commissioner of Taxes (Vic) v Lennon (1921) 29 CLR 579

Commonwealth v Baume (1905) 2 CLR 405

CPCF v Minister for Immigration and Border Protection [2015] HCA 1; 255 CLR 514

Dilworth v Stamps Commissioner [1899] AC 99

Douglas v Tickner (1994) 49 FCR 507

Federal Commissioner of Taxation v Broken Hill Pty Co Ltd (1969) 120 CLR 240

Federal Commissioner of Taxation v Consolidated Media Holdings Ltd [2012] HCA 55; 250 CLR 503

Fejo v Northern Territory [1998] HCA 58; 195 CLR 96

FMG Pilbara Pty Ltd v Cox [2009] FCAFC 49; 175 FCR 141

Harrison v Melham [2008] NSWCA…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Harvey v Minister for Primary Industry and Resources and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] FCAFC 66
Decision Date

CaseChat Overview and Summary

In the matter of Harvey v Minister for Primary Industry and Resources, the appeal was brought before the court to challenge the grant of a mineral lease (ML 29881) by the Minister to Mount Isa Mines under the Mineral Titles Act 2010 (NT). The proposed land subject to the lease was intended for the construction of a "dredge spoil emplacement area" to deposit dredged material from a facility on adjacent land, which was used to load ore concentrate from the McArthur River Mine for export. The primary legal issue before the court was whether the proposed grant of ML 29881 constituted a future act under s 24MD(6B)(b) of the Native Title Act 1993 (Cth), specifically the "creation of a right to mine for the sole purpose of the construction of an infrastructure facility associated with mining".

The court found that the grant of ML 29881 did not constitute the creation or variation of a right to mine, and therefore s 24MD(6B)(b) did not apply. The court's reasoning hinged on the interpretation of the terms "a right to mine" and "infrastructure facility" within the context of the Native Title Act. The court concluded that the dredge spoil emplacement area (DSEA) would not be considered an infrastructure facility under the ordinary meaning of the term, and even if it were, the grant of the mineral lease did not create or vary a right to mine. The court also noted that the construction of the DSEA involved engineered walls and drains, which indicated a level of sophistication that qualified it as a facility. However, this conclusion did not affect the outcome, as the primary issue was the applicability of the section of the Native Title Act to the grant of the mineral lease.

In conclusion, the court dismissed the appeal, finding that the proposed grant of ML 29881 was not a future act under s 24MD(6B)(b) of the Native Title Act. The court ordered that the appeal be dismissed and that the parties confer on the issue of costs, with the opportunity to file agreed orders or limited submissions if necessary.

Orders

Orders of the court

1. The appeal be dismissed.

2. Within 14 days of the date of these orders, the parties are to file agreed proposed orders as to the costs of the appeal or, failing agreement, submissions on the issue of costs limited to 5 pages.

3. Any dispute on the question of the costs of the appeal will be determined on the papers.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

For the reasons that follow, we dismiss the appeal. Mount Isa Mines’ contention that the grant of ML 29881 would not be the creation or variation of a right to mine is correct, with the consequence that s 24MD(6B)(b) is inapplicable to the grant of ML 29881.BACKGROUND FACTS The primary judge made detailed findings with respect to the process of advertising the proposed grant of ML 29881, being matters relevant to the issues before his Honour. The process of advertising was protracted and involved missteps. Those missteps, and related correspondence, are detailed by the primary judge at [11]-[51] of his judgment. Nothing in the appeal turns on those matters, and it is therefore unnecessary to refer to those findings. Similarly, it is not necessary to refer to the communications between the relevant parties, between 2016 and 2019, regarding the appropriate procedures under the NTA which apply to the proposed grant. It suffices for present purposes to provide an overview regarding the background to the application for ML 29881 and the purpose of the proposed mineral lease. The following is a summary of the key background facts, drawn from the trial judgment, which are relevant to the disposition of the appeal. They are in relatively short compass.Mineral Leases held by Mount Isa Mines The McArthur River Mine Project was established under the McArthur River Project Agreement Ratification Act 1992 (NT) (the Project Act) for, amongst other things, the mining of zinc-lead-silver and the treatment, storage and transport of ore and concentrate. Pursuant to s 4 of the Project Act, the McArthur River Project Agreement (being an agreement between the Northern Territory and Mount Isa Mines entered into on 25 November 1992) was ratified and its implementation was authorised. The Project Act was amended by the McArthur River Project Agreement Ratification Amendment Act 1993 (NT). Pursuant to s 4A of the amended Project Act, six mining leases and one exploration licence, which had been granted to Mount Isa Mines under the original Project Act and the Mining Act 1980 (NT), were “re-granted” to it, being mining leases MLN 1121 to 1126 (inclusive) and EL 8078 (see Sch 2 of the amended Project Act). As shown on the map annexed to the trial judgment, mining leases MLN 1121 to 1125 (inclusive) are located at, or in the vicinity of, the McArthur River Mine site whereas MLN 1126 is located some distance north-east of the mine site on the southern coastline of the Gulf of Carpentaria. The permitted uses of the area covered by MLN 1121 to 1125 (inclusive) were set out in cl 4 of those mineral leases. It is contextually relevant to have regard to those purposes which are stated as follows:PURPOSEThe Company may use or permit to be used the Lease Area for the purposes of:(a) Mining, processing, treatment and concentration of the Ore including the treatment of tailings or other mining material and removal of Ore, Concentrate, tailings or other mining material from the Lease Area;(b) the erection of machinery, conveyor apparatus, plant, buildings or other structures, or use thereof;(c) impounding and retaining of waste resulting from the Mining, treatment or processing operations;(d) the erection and use of residential premises or recreational facilities for persons engaged in or connected with the McArthur River Project;(e) the cutting and construction of water races, drains, dams and roads for use in connection with the McArthur River Project;(f) the boring or sinking for, pumping or raising of, water for the use of that water for or in connection with the McArthur River Project;(g) exploring for minerals on the Lease Area;(h) the Mining and use of extractive minerals for or in connection with all or any of the purposes specified in paragraphs (a), (b), (c), (d), (e) and (f) of this clause; and(i) such other purposes necessarily incidental to or in connection with paragraphs (a), (b), (c), (d), (e), (f), (g) and (h) of this clause, including the management, protection and rehabilitation of the Environment.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Given our conclusion as to the proper construction of the definition of “infrastructure facility”, it is unnecessary to determine whether the DSEA would be an infrastructure facility within the ordinary meaning of that term. Nevertheless, as the matter was fully argued, we will briefly express our conclusion that the DSEA would be an infrastructure facility within the ordinary meaning of the term. The mere fact that the DSEA is to be constructed from natural material does not prevent it from being a facility. The Summary of Proposed Works states that the DSEA will include engineered internal and external walls and internal and external drains. The function or purpose of the DSEA is to manage the relocation and deposition of dredge spoil. The evidence of Mr Rooney described the operation of Mount Isa Mine’s current dredge spoil emplacement area on MLN 1126, and the primary judge found that that description broadly corresponded to the description of the proposed works set out in the Summary of Proposed Works. Mr Rooney’s evidence was that the DSEA consists of ponds (commonly referred to as “cells”) and a retention basin and that, as dredge spoil is deposited into the cells the silt within the dredge spoil begins to separate from the water and gravity is used to pass the dredge spoil between cells to drop out further silt and fine sediment from the water. This decantation of the water from the dredge spoil leaves a dry silt within the cells and supernatant water being released through the dredge spoil drain. The cells contain the residue dry silt and some of that dry silt is then pushed up and redeposited to be able to recreate the walls of each cell for subsequent lifts of the DSEA. The cell walls are created so that there is control of the deposition of the dredge spoil and the cells are monitored and maintained to ensure the operational integrity of the DSEA. In our view, the sophistication of the construction of the DSEA is sufficient to satisfy the requirements of being a facility. The function or purpose of the DSEA is to support the operation and functioning of the barge channel and thereby the Bing Bong Loading Facility. The DSEA is therefore an infrastructure facility (within the ordinary meaning of that term) within Mount Isa Mine’s port operations.CONCLUSION In conclusion, the primary judge was correct to conclude that the proposed grant of ML 29881 under the Mineral Titles Act is not a future act within s 24MD(6B)(b) of the NTA, both for the reason given by his Honour, that the DSEA would not be an infrastructure facility within the meaning of the NTA, and for the further reason that the grant of ML 29881 would not constitute the creation or variation of a right to mine. We therefore dismiss the appeal. In relation to costs, the parties requested an opportunity to confer following the delivery of reasons for judgment. It is therefore appropriate to make orders that would enable such conferral and the subsequent filing of agreed proposed orders or, failing agreement, short submissions on that issue.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.