| IN THE COURT OF APPEAL OF NEW ZEALAND |
| CA28/2017 [2017] NZCA36 |
| BETWEEN | CUSTOM STREET HOTEL LIMITED |
| AND | PLUS CONSTRUCTION NZ LIMITED PLUS CONSTRUCTION CO LIMITED |
| Hearing: | 19 October 2017 |
Court: | Kós P, Harrison and Clifford JJ |
Counsel: | R B Stewart QC, I Rosic and S S McMullan for Appellant |
Judgment: | 7 March 2018 at 2 pm |
JUDGMENT OF THE COURT
AThe appeal is dismissed.
BThe appellant must pay the respondents one set of costs for a standard appeal on a band A basis and usual disbursements. We certify for second counsel.
____________________________________________________________________
REASONS OF THE COURT
(Given by Kós P)
This appeal concerns the meaning of default provisions in a standard construction contract called NZS 3910:2003 (the contract). Each side has purported to cancel the contract, asserting breach by the other. What is to happen in such a case?
Background
The appellant, Custom Street Hotel Ltd (Custom), owns the former Reserve Bank building at 67 Customs Street East, Auckland (the site). It wished to convert it into a hotel. On 1 November 2013 it entered a construction contract with the respondents, Plus Construction NZ Ltd and Plus Construction Co Ltd (collectively, Plus) for $14.45 million plus GST. But problems overwhelmed the project. Plus says that was because of Custom’s failure to obtain consents. Custom says Plus could still have made progress, that it failed to resource the project adequately and that it simply abandoned the job.
In July 2014 Plus stopped work on the site. It advanced three claims, initially before an adjudicator, under the Construction Contracts Act 2002 (CCA). The adjudicator, Derek Firth, found fault on both sides. In a decision dated 15 October 2014 he said “the fault for the shambles does not all lie at the door of Plus”. But he also found there was much work Plus could have completed despite the relevant consents being incomplete. Time was now at large. Plus was entitled to a reasonable time to complete the work.
The last consent required was then obtained in November 2014. The parties then discussed making a fresh start. A new programme of works was canvassed. Before these discussions ended, Plus complained about non-payment of some of its invoices. On 27 January 2015 it issued a default notice for two outstanding payment claims totalling $258,508. Part of that sum had been due since November 2014. The notice was issued pursuant to cl 14.3.1(b) of the contract. If the principal’s defaults were not rectified within 10 working days, rights of suspension or termination arose.[1] The 10-working-day period would expire at midnight on 11 February 2015.
[1]See below at [16] of this judgment.
Before that, on 5 February 2015, the project engineer (the engineer) suspended work on the site on the basis of alleged breaches by Plus concerning site safety. Plus was not operating on the site in any…
Keep reading for free
Create a free CaseChat account to read Custom Street Hotel Limited v Plus Construction NZ Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2018] NZCA 36
- Decision Date
CaseChat Overview and Summary
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi