IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2016-404-000219 [2016] NZHC 2934
UNDER the Arbitration Act 1996 IN THE MATTER OF
an application for leave to appeal under
cl 5(5) of Schedule 2 to the Arbitration Act
1996BETWEEN
CUSTOM STREET HOTEL LIMITED Plaintiff
AND
PLUS CONSTRUCTION NZ LIMITED First Defendant
PLUS CONSTRUCTION CO LIMITED Second Defendant
Hearing: 6 December 2016 Appearances:
R B Stewart QC and I Rosic for Plaintiff
A R B Barker for DefendantsJudgment:
8 December 2016
JUDGMENT OF GILBERT J
This judgment is delivered by me on 8 December 2016 at 11.30 am pursuant to r 11.5 of the High Court Rules.
..................................................... Registrar / Deputy Registrar
Counsel/Solicitor:
R B Stewart QC, Auckland
Gilbert Walker, Auckland
ARB Barker, Barrister, Auckland
CUSTOM STREET HOTEL LTD v PLUS CONSTRUCTION NZ LTD & ANOR [2016] NZHC 2934 [8 December 2016]
[1] Custom Street Hotel Ltd (Custom Street) claims the sum of $3.6125 million pursuant to a performance bond arranged by Plus Construction (Plus) to assure performance of its obligations as the contractor under a construction contract for the redevelopment of the Reserve Bank building on Customs Street, Auckland into a
15 storey hotel. Payment under the bond is contingent on the engineer to the contract stating that, in his opinion, the contractor has failed to perform its obligations under the contract and the amount claimed under the bond is properly due under the contract. The engineer issued the certificate and the parties agreed to refer to arbitration the question of whether the engineer was correct to do so.
[2] The Hon. Rodney Hansen QC was appointed as sole arbitrator. In an award dated 17 November 2015, he determined that the engineer was not entitled to issue the certificate because Plus had not failed to perform its obligations under the contract and no amount was due by Plus under the contract. Accordingly, Custom Street had no right to claim under the bond.
[3] On 2 June 2016, Palmer J gave leave to appeal to this Court on five questions of law:1
(a) Did the arbitrator err in holding that the defendants’ breach must be repudiatory in nature before the defendants would be disentitled from terminating?
(b)Did the arbitrator correctly construe cl 14.3.3 of the contract and err in holding that the defendants terminated in accordance with cl 14.3.3?
(c) Did the arbitrator correctly construe cl 14.2.4 of the contract and err in holding that the difference, between a certified cost to complete the contract works and the cost to Custom Street had the contract works been completed by Plus, could not be “properly due under the
contract” until the contract works have been completed?
1 Custom Street Hotel Ltd v Plus Construction NZ Ltd [2016] NZHC 1180.
(d)Did the arbitrator err in holding that the damages claimed by Custom Street for breach of contract cannot be “properly due under the contract” until Custom Street’s claim is admitted or determined as to liability and quantum?
(e) Did the…
Keep reading for free
Create a free CaseChat account to read Custom Street Hotel Limited v Plus Construction NZ Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] NZHC 2934
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the proposed questions of law were worthy of consideration by the Court of Appeal. This involved assessing whether the questions were capable of bona fide and serious argument, involved an interest of sufficient importance, and whether the cost and delay of a further appeal were justified. The test for leave under cl 5(5) of the Arbitration Act 1996 was confirmed by the Court of Appeal in Downer Construction v Silverfield Developments, emphasizing that the primary focus was on whether the question of law was worthy of consideration. The court also considered the wider consequences of the proposed appeal, given the substantial amount in issue and the potential impact on the standard conditions of contract used in the construction industry in New Zealand.
The court concluded that the proposed questions of law were worthy of consideration by the Court of Appeal. The questions involved significant interpretation issues of the standard form contract, which had not been previously considered by the Courts. Additionally, the private interest in the appeal was significant, given the substantial amount in dispute and the potential impact on the construction industry. The court accepted that the cost and delay of a further appeal were justified in this context. Consequently, the application for leave to appeal to the Court of Appeal was granted, with the approved questions of law as agreed by counsel.