Customs Street Hotel Limited v Plus Construction NZ Limited

Link copied
Case Copied 3 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV-2016-404-000219 [2016] NZHC 1180

BETWEEN

CUSTOMS STREET HOTEL LIMITED

Applicant

AND

PLUS CONSTRUCTION NZ LIMITED First Respondent

PLUS CONSTRUCTION CO LIMITED Second Respondent

Hearing: 23 May 2016

Appearances:

R B Stewart QC and I Rosic for Applicant
A Barker for Respondents

Judgment:

2 June 2016

JUDGMENT OF PALMER J

This judgment is delivered by me on 2 June 2016 at 4.30 pm pursuant to r 11.5 of the High Court Rules.

..................................................... Registrar / Deputy Registrar

Counsel / Solicitors:

R B Stewart QC, Auckland

A Barker, Barrister, Auckland

Gilbert Walker, Auckland (I Rosic)

Alexander Dorrington, Auckland (D Marsden)

CUSTOMS STREET HOTEL LTD v PLUS CONSTRUCTION NZ LTD & ANOR [2016] NZHC 1180 [2 June 2016]

Summary

[1]      Custom Street Hotel Ltd applies for leave to appeal an arbitral award on five questions of law.  I am satisfied there are serious arguments regarding the questions which could substantially affect the rights of the parties and that leave to appeal should be granted.

Questions for Appeal

[2]      The  applicants,  Custom  Street  Hotel  Ltd  (CSH),  contracted  with  the respondents (to whom I refer collectively as Plus) to develop a hotel on Customs Street in Auckland.  There were problems with the development.  In early 2015 CSH required the engineer to suspend the contract works and both parties purportedly terminated the contract.  The parties agreed to arbitration over whether CSH could make demand on a performance bond for some $3.6 million.  In November 2015 the arbitrator, the Hon Rodney Hansen QC, held Plus had validly cancelled the contract and no sums were properly due by it under the contract.  So the engineer was wrong to issue his certificate and CSH could not make demand under the bond.

[3]      CSH seeks leave to appeal on the following questions:

(a)       In relation to Plus’ purported termination of the construction contract:

(i)Did the arbitrator err in holding that the defendants’ breach must be repudiatory in nature before the defendants would be disentitled from terminating?

(ii)Did  the  arbitrator  correctly  construe  clause  14.3.3  of  the contract and err in holding that the defendants terminated in accordance with clause 14.3.3?

(b)In relation to the proper construction of clause 2(c) of the performance bond issued by Plus in favour of CSH:

(i)Did  the  arbitrator  correctly  construe  clause  14.2.4  of  the contract and err in holding that the difference, between a certified cost to complete the contract works and the cost to CSH had the contract works been completed by Plus, could not be “properly due under the contract” until the contract works have been completed?

(ii)Did the arbitrator err in holding that the damages claimed by CSH for breach of contract cannot be “properly due under the contract” until CSH’s claim is admitted or determined as to liability and quantum?

(iii)Did the arbitrator err in holding that CSH cannot rely upon the amounts claimed under the indemnity clause in the contract as amounts “properly due under the contract”.

Leave to Appeal

[4]…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Customs Street Hotel Limited v Plus Construction NZ Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2016] NZHC 1180
Decision Date

CaseChat Overview and Summary

Customs Street Hotel Limited (CSH) applied for leave to appeal an arbitral award against Plus Construction NZ Limited and Plus Construction Co Limited. The award was issued in relation to a construction contract dispute over a hotel development in Auckland. The High Court of New Zealand was tasked with deciding whether leave to appeal should be granted on the basis of five questions of law. The key legal issues involved the validity of the termination of the construction contract by Plus, the interpretation of certain clauses in the contract and performance bond, and the determination of what constitutes "properly due under the contract."

The Court found that the questions presented had the potential to substantially affect the rights of the parties. In particular, the Court was satisfied that there were serious arguments regarding the interpretation of the contract clauses and the conditions under which sums could be claimed as "properly due under the contract." The Court noted that if the arbitrator's interpretation was incorrect, it could significantly alter the financial obligations and entitlements of the parties. Therefore, the Court granted leave to appeal and directed that the substantive appeal be heard separately, with a case management conference to be scheduled within 15 working days of the judgment.