IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2016-404-000219 [2016] NZHC 1180
BETWEEN CUSTOMS STREET HOTEL LIMITED
Applicant
AND
PLUS CONSTRUCTION NZ LIMITED First Respondent
PLUS CONSTRUCTION CO LIMITED Second Respondent
Hearing: 23 May 2016 Appearances:
R B Stewart QC and I Rosic for Applicant
A Barker for RespondentsJudgment:
2 June 2016
JUDGMENT OF PALMER J
This judgment is delivered by me on 2 June 2016 at 4.30 pm pursuant to r 11.5 of the High Court Rules.
..................................................... Registrar / Deputy Registrar
Counsel / Solicitors:
R B Stewart QC, Auckland
A Barker, Barrister, Auckland
Gilbert Walker, Auckland (I Rosic)
Alexander Dorrington, Auckland (D Marsden)
CUSTOMS STREET HOTEL LTD v PLUS CONSTRUCTION NZ LTD & ANOR [2016] NZHC 1180 [2 June 2016]
Summary
[1] Custom Street Hotel Ltd applies for leave to appeal an arbitral award on five questions of law. I am satisfied there are serious arguments regarding the questions which could substantially affect the rights of the parties and that leave to appeal should be granted.
Questions for Appeal
[2] The applicants, Custom Street Hotel Ltd (CSH), contracted with the respondents (to whom I refer collectively as Plus) to develop a hotel on Customs Street in Auckland. There were problems with the development. In early 2015 CSH required the engineer to suspend the contract works and both parties purportedly terminated the contract. The parties agreed to arbitration over whether CSH could make demand on a performance bond for some $3.6 million. In November 2015 the arbitrator, the Hon Rodney Hansen QC, held Plus had validly cancelled the contract and no sums were properly due by it under the contract. So the engineer was wrong to issue his certificate and CSH could not make demand under the bond.
[3] CSH seeks leave to appeal on the following questions:
(a) In relation to Plus’ purported termination of the construction contract:
(i)Did the arbitrator err in holding that the defendants’ breach must be repudiatory in nature before the defendants would be disentitled from terminating?
(ii)Did the arbitrator correctly construe clause 14.3.3 of the contract and err in holding that the defendants terminated in accordance with clause 14.3.3?
(b)In relation to the proper construction of clause 2(c) of the performance bond issued by Plus in favour of CSH:
(i)Did the arbitrator correctly construe clause 14.2.4 of the contract and err in holding that the difference, between a certified cost to complete the contract works and the cost to CSH had the contract works been completed by Plus, could not be “properly due under the contract” until the contract works have been completed?
(ii)Did the arbitrator err in holding that the damages claimed by CSH for breach of contract cannot be “properly due under the contract” until CSH’s claim is admitted or determined as to liability and quantum?
(iii)Did the arbitrator err in holding that CSH cannot rely upon the amounts claimed under the indemnity clause in the contract as amounts “properly due under the contract”.
Leave to Appeal
[4]…
Keep reading for free
Create a free CaseChat account to read Customs Street Hotel Limited v Plus Construction NZ Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] NZHC 1180
- Decision Date
CaseChat Overview and Summary
The Court found that the questions presented had the potential to substantially affect the rights of the parties. In particular, the Court was satisfied that there were serious arguments regarding the interpretation of the contract clauses and the conditions under which sums could be claimed as "properly due under the contract." The Court noted that if the arbitrator's interpretation was incorrect, it could significantly alter the financial obligations and entitlements of the parties. Therefore, the Court granted leave to appeal and directed that the substantive appeal be heard separately, with a case management conference to be scheduled within 15 working days of the judgment.