Custom Street Hotel Ltd v Plus Construction NZ Ltd

Link copied
Case Copied 34 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV-2016-404-000219 [2016] NZHC 2011

UNDER the Arbitration Act 1996

BETWEEN

CUSTOM STREET HOTEL LIMITED Plaintiff

AND

PLUS CONSTRUCTION NZ LIMITED First Defendant

PLUS CONSTRUCTION CO LIMITED Second Defendant

Hearing: 3 August 2016

Appearances:

R B Stewart QC, I Rosic and S McMullan for Plaintiff
A Barker for Defendants

Judgment:

29 August 2016

JUDGMENT OF GILBERT J

This judgment is delivered by me on 29 August 2016 at 11.30 am pursuant to r 11.5 of the High Court Rules.

..................................................... Registrar / Deputy Registrar

Counsel/Solicitors:

R B Stewart QC, Auckland

Gilbert Walker, Auckland

Andrew Barker, Barrister, Auckland

CUSTOM STREET HOTEL LTD v PLUS CONSTRUCTION NZ LTD [2016] NZHC 2011 [29 August 2016]

Contents

Introduction ..........................................................................................................[1] Background ...........................................................................................................[2] Questions of law..................................................................................................[19]

Question 1 – Did the arbitrator err in holding that Plus’s
breach must be repudiatory in nature before Plus would be
disentitled from terminating? .......................................................................[20]

Question 2 – Did the arbitrator correctly construe clause 14.3.3 of the contract and err in holding that the defendants terminated

in accordance with clause 14.3.3? ................................................................[28]

Question 3 – Did the arbitrator correctly construe clause 14.2.4 of the contract and err in holding that the difference, between a certified cost to complete the contract works and the cost to Custom Street had the contract works been completed by Plus, could not be “properly due under the contract” until the contract

works have been completed?........................................................................[40]

Question 4 – Did the arbitrator err in holding that the damages claimed by Custom Street for breach of contract cannot be “properly due under the contract” until Custom Street’s claim

is admitted or determined as to liability and quantum? ...............................[49]

Question 5 – Did the arbitrator err in holding that Custom Street cannot rely upon the amounts claimed under the indemnity clause

in the contract as amounts “properly due under the contract”?....................[54]

Result ...................................................................................................................[61]

Introduction

[1]      This is an appeal on questions of law arising out of an arbitral award of

Hon. Rodney Hansen QC dated 17 November 2015.

Background

[2]     The plaintiff, Custom Street Hotel Ltd (Custom Street), entered into a construction  contract  dated  1  November  2013  with  the  defendants,  a  Korean company, Plus Construction Co. Ltd (Plus Korea) and Plus Construction NZ Ltd (Plus NZ) (together, Plus) for the re-development of the Reserve Bank Building on Customs Street, Auckland into a 15 storey hotel.  This contract replaced an earlier construction contract entered into in December 2012 between Custom Street and Plus NZ.

[3]      The contract price was $14.45 million plus GST subject to any variations or adjustments under the contract.   The contract works were to be completed within

52 weeks.

[4]      Plus as contractor and ANZ as surety provided a performance bond for 25 per cent of the contract price, $3.6125 million, in favour of Custom Street as beneficiary. The expiry date of the bond was 31 March 2015. The bond was payable:

Upon written demand by the beneficiary stating that the contractor has failed to perform…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Custom Street Hotel Ltd v Plus Construction NZ Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2016] NZHC 2011
Decision Date

CaseChat Overview and Summary

Custom Street Hotel Ltd, the plaintiff, appealed an arbitral award against Plus Construction NZ Ltd and Plus Construction Co. Ltd, the defendants, regarding a construction contract for the redevelopment of the Reserve Bank Building in Auckland. The appeal raised five questions of law concerning the interpretation of the contract and the validity of the engineer's certification under the performance bond. The court found that the arbitrator did not err in his interpretation of the contract and certification process. The court upheld the arbitrator's findings that Plus Construction NZ Ltd validly terminated the contract, the damages for breach of contract could not be claimed until the contract works were completed, and Custom Street Hotel Ltd could not rely on the indemnity clause to circumvent the contract's dispute resolution process. The appeal was dismissed, and the defendants were awarded costs on a 2B basis.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.