Between late 2005 and early 2006, the appellants entered into agreements with the respondent, Station Properties Ltd (in liquidation and in receivership) (Station), for the purchase of units in an apartment development in Queenstown (the agreements). They claimed to have done so on the understanding that they would not be required to purchase the units, their role being simply that of underwriters facilitating the raising of funding to enable the construction of the development so that it could be on-sold to an organisation which would operate it under a brand name as serviced apartments. They were, in effect, investors who expected to receive a return on what was intended to be a relatively short-term investment.
Between the time the agreements were made and the time the development was substantially completed in mid-2008, the value of the units dropped significantly as a result of a general downturn in the property market. Station was unable to find a purchaser for the development and looked to the appellants and other purchasers to settle their transactions. The appellants refused to settle. One, Mr Selwyn, purported to cancel his agreement. Ultimately, in April 2010, Station took the view that the appellants had repudiated the agreements and cancelled them. Station then sued the appellants for damages for breach of contract, based on the resale prices achieved for the units or, in the case of the Donaldsons, on its then market value.
Station was unsuccessful in the High Court,[1] but succeeded in the Court of Appeal.[2] The…
Grounds of appeal
[14] The appellant contends that the primary judge erred in finding that the respondent had discharged the onus of establishing the matters required under the relevant provision.
[15] It was submitted that his Honour failed to give adequate weight to the evidence of the second witness, and that the findings of fact were not reasonably open on the material before the Court.
[16] The respondent, for its part, submits that no error is disclosed, and that the conclusions reached were well within the range of outcomes available to the primary judge.
Consideration
[17] It is convenient to deal first with the question of construction, as the resolution of that issue informs the remaining grounds advanced by the appellant.
[18] For the reasons that follow, we are of the view that the appeal should be allowed in part and the matter remitted for further determination.
Continue reading Kumar v Station Properties Ltd
Sign in free to access the full text
Details
AGLC
Kumar v Station Properties Ltd [2015] NZSC 34
Case
[2015] NZSC 34
Decision Date
CaseChat Overview and Summary
The appellants entered into agreements with the respondent, Station Properties Limited (in liquidation and in receivership), for the purchase of units in an apartment development in Queenstown. The property market deteriorated between the time the agreements were made and the development was completed, and Station was unable to sell the development. The appellants refused to complete the purchase of their units and Station cancelled the agreements, seeking damages for breach of contract. The appellants argued that Station was in breach of essential contractual obligations, entitling them to cancel the agreements. The Supreme Court allowed the appeal, reinstating the orders of Toogood J in the High Court, and held that the appellants were entitled to cancel the agreements on the basis that Station breached essential contractual obligations, namely the provision of a furniture package and a management agreement for the development as serviced accommodation.