IN THE HIGH COURT OF NEW ZEALAND NAPIER REGISTRY
I TE KŌTI MATUA O AOTEAROA AHURIRI ROHE
CIV-2018-441-29
[2019] NZHC 304
BETWEEN MURRAY PAUL AND MARIE PAUL
Appellants
AND
JADE RESIDENTIAL LIMITED
Respondent
Hearing: 13 August 2018 Appearances:
K A Lomas for Appellants M B Lawson for Respondent
Judgment:
1 March 2019
JUDGMENT OF GRICE J
(Appeal from District Court)
Contents
Para No
Background [1]
The decision [5]
Grounds of appeal [10]
Scope of appeal [12]Questions on appeal [15]
Substantive findings [17]
Were the milestone payments due and payable? [17]
“Closed-in” milestone [17]
“Lined” milestone [25]
What was the effect of the dispute resolution clause on the cancellation
of the contract by the Pauls? [40]
Was the contract otherwise validly cancelled? [58]
Were the Paul’s in breach of cl 14 of the contract? [69]
Was the Judge entitled to allow further evidence to be adduced on
quantum? [73]
Conclusion [86]
Good faith [89]
Costs [91]
PAUL v JADE RESIDENTIAL LIMITED [2018] NZHC 304 [1 March 2019]
Background
[1] In the District Court, Jade Residential Limited (the original plaintiff and the respondent here) obtained judgment against Mr and Mrs Paul (the original defendants and the appellants in this court) for a sum to be fixed at a subsequent hearing.1
[2] The judgment concerned work Jade had done in the construction of the Pauls’ house in Havelock North. The house was finally completed after the Pauls purported to cancel the construction contract with Jade. The cancellation was precipitated by Jade ceasing to work on the job before the house was completed. Jade did so because the Pauls had not paid two milestone payments which Jade said were due.
[3] Jade made a claim for payment of the two milestone payments. The Pauls lodged a counterclaim for damages for the cost they had incurred to complete the house.
[4]Both parties now appeal against the District Court decision.
The decision
[5]The District Court Judge found that:
(a)The Pauls could not lawfully cancel the contract because they had refused to go to dispute resolution and the contract contained a clause requiring the parties to go to mediation in the event of a dispute.2
(b)Jade had not completed the contractual milestones. These were called the “closed-in” milestone and “lined” milestone. The milestones required completion before specified payments were due for each milestone.3
1 Jade Residential Limited v Paul [2018] NZDC 5673.
2 At [56].
3 At [27], [38] and [57].
(c)Failure to complete the milestones meant that there was no obligation on the Pauls to meet any progress payment at the time the accounts were rendered by align="left">(d)The Judge found that while the Pauls unlawfully cancelled the contract,
Jade was not “without fault”.5
[6]Jade could not rely on the contractual milestone payments of $134,513 and
$57,576—the amounts contained in the statement of claim—as the milestones had not been completed.6 The Judge concluded the most appropriate outcome would be for the Pauls to pay Jade for the actual work done, rather than the milestones. The Judge…
Keep reading for free
Create a free CaseChat account to read Paul v Jade Residential Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] NZHC 304
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.