IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2023-404-002246
[2023] NZHC 2974
UNDER the Arbitration Act 1996 and Part 19 of the High Court Rules 2016 BETWEEN
RAU PAENGA LIMITED
Applicant
AND
CPB CONTRACTORS PTY LIMITED
Respondent
Hearing: 18 October 2023 Appearances:
A R Galbraith KC, J K Stewart, G J de Lisle and J K Wilson for Plaintiff
S W P Foote KC, J K Goodall KC and J A Clark for Defendant
Judgment:
24 October 2023
Reissued:
25 October 2023
JUDGMENT OF VENNING J
Re: Application for interim relief
This judgment was delivered by me on 24 October 2023 at 4.00 pm, pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar Date……………
Solicitors: MinterEllisonRuddWatts, Auckland
Lindsay & Francis, Auckland
Counsel: A R Galbraith KC/J K Wilson, Auckland
S W P Foote KC/J K Goodall KC, Auckland
RAU PAENGA LIMITED v CPB CONTRACTORS PTY LIMITED [2023] NZHC 2974 [24 October 2023]
[1] Rau Paenga Limited (RPL) seeks orders restraining the respondent, CPB Contractors Pty Limited (CPB), from, in reliance on default notices issued to the Engineer (Engineer) to the Contract on 4 September 2023:
(a)requiring the Engineer to suspend the contract work under cl 14.3.3 of the Contract; and
(b) terminating the Contract under cl 14.3.3 until further order of the Court or arbitral tribunal.1
[2]CPB opposes the application.
Background
[3] On 28 March 2019 RPL, a Crown owned enterprise, engaged CPB to construct the Parakiore Recreation and Sports Centre for a price of $220 million.2 The due date for completion was 28 October 2021. The Contract is based on NZS 3910:2013 standard form with modifications as agreed.
[4] The project has suffered significant delays and increased costs. The contractual due date for completion was revised to 6 January 2022 factoring in 40 days extension of time awarded to CPB under the Contract. CPB has sought further extensions of time which have been declined by the Engineer. Although CPB has claimed $297 million to date, the certified costs to date are presently limited to approximately $203 million. CPB’s revised programme, dated 1 September 2023, forecasts a completion date in June 2025. CPB considers the actual total cost of the project will be $696 million.
[5] The parties ultimately blame each other for various breaches of obligations resulting in the delay and increased costs. Resolution of a number of CPB’s claims through the contractual dispute resolution process is ongoing.
1 In its originating application RPL sought further orders but at the outset of the hearing Mr Galbraith KC confirmed the relief sought was restricted to the above.
2 The figures are approximate.
[6] CPB proposes to suspend or terminate the Contract. On 4 September 2023 CPB issued three default notices:
(a)Parakiore Recreation and Sport Centre: Default notice – IFC (Issued for Construction) and Engineer’s Conduct (the IFC and Engineer’s Conduct Default Notice);
(b)Parakiore Recreation and Sport Centre: Default notice – Ground Conditions (Ground Conditions Default Notice); and
Keep reading for free
Create a free CaseChat account to read Rau Paenga Limited v CPD Contractors Pty Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NZHC 2974
- Decision Date
CaseChat Overview and Summary
The Court found it had jurisdiction to grant interim measures under the Arbitration Act 1996. To obtain such measures, RPL must satisfy the Court that harm not adequately reparable by damages is likely if the measure is not granted, the harm substantially outweighs that likely to result to the respondent if the measure is granted, and there is a reasonable possibility RPL will succeed on the merits of the claim.
The Court found there is a reasonable possibility RPL will succeed on the merits because the default notices are arguably deficient and contestable. The harm to RPL if the interim measures are not granted is not adequately reparable by damages and substantially outweighs any harm to CPB. The harm includes increased costs, loss of key personnel, disruption to the building process, and loss of reputation. The Court can consider harm to third parties closely aligned with RPL.
The Court granted the interim measures sought by RPL, restraining CPB from suspending or terminating the contract until further order of the Court or arbitral tribunal. RPL is to have costs on a 3B basis.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi