Trade Guaranty + Surety Limited v Carterton District Council

Link copied
Case Copied 43 min read

IN THE HIGH COURT OF NEW ZEALAND MASTERTON REGISTRY

I TE KŌTI MATUA O AOTEAROA WHAKAORIORI ROHE

CIV-2023-435-008

[2024] NZHC 47

UNDER the Companies Act 1993

BETWEEN

TRADE GUARANTY + SURETY LIMITED

Applicant

AND

CARTERTON DISTRICT COUNCIL

Respondent

Hearing: 3 November 2023

Appearances:

T Nelson for Applicant

M Holland for Respondent

Judgment:

1 February 2023


JUDGMENT OF ASSOCIATE JUDGE SKELTON


[1]    The applicant, Trade Guaranty + Surety Ltd (TGS), applies by originating application to set aside a statutory demand served on it by the respondent, Carterton District Council (Council). The statutory demand requires payment of the sum of

$343,172 (including GST), being payment sought by the Council under a contractor’s performance bond provided by TGS. The Council opposes the application.

Background

[2]    TGS is in the business of providing bond and surety instruments, often under construction contracts.

[3]    On 22 November 2018, the Council entered into a construction contract with CHB Earthmovers Ltd (CHB) for the construction of a reservoir at the Carterton

TRADE GUARANTY + SURETY LIMITED v CARTERTON DISTRICT COUNCIL [2024] NZHC 47

[1 February 2023]

wastewater treatment plant (Contract). The form of contract is the New Zealand Standard “Conditions of contract for building and civil engineering construction” (NZS 3910:2013). Under the special conditions of the Contract, CHB agreed to provide a contractor’s performance bond for 10 per cent of the tendered  sum.  On  24 January 2019, TGS provided the contractor’s bond for CHB in the form provided for by sch 3 of NZS 3910:2013 (Bond).

[4]    On 29 July 2021, the engineer to the Contract issued a certificate that in his opinion CHB was in default under the Contract. On the same day, the Council served a notice of default on CHB based on the engineer’s certificate, although the notice of default was dated 19 July 2021. On 30 August 2021, the Council gave notice to CHB that it had not remedied its default and the Council would be resuming possession of the construction site under cl 14.2.1 of the Contract on 31 August 2021. CHB disputes the validity of the engineer’s certificate and the notice of default and says that the Council breached the Contract in resuming possession.

[5]    On 16 June 2023, the Council wrote to TGS making a demand on the Bond for its full value, $343,172 (including GST). On 1 August 2023, TGS responded stating that it had been advised by CHB that there were still matters in dispute under the Contract, and for payment to be made the Council would need to provide evidence that the outstanding disputes have been determined.

[6]    On 4 August 2023, the  Council served the statutory demand on TGS.  On   10 August 2023, TGS’s solicitors invited the Council to withdraw the demand on the basis that CHB is not liable under the Contract. The Council declined to withdraw the demand.

[7]    On 15 August 2023, CHB issued a notice to the engineer triggering the dispute process under the Contract. On 17 August 2023, TGS applied to set…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Trade Guaranty + Surety Limited v Carterton District Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] NZHC 47
Decision Date

CaseChat Overview and Summary

The case of Trade Guaranty + Surety Limited v Carterton District Council involves an application by TGS to set aside a statutory demand served by the Carterton District Council for the full value of a contractor's performance bond provided by TGS for CHB Earthmovers Ltd. The statutory demand was issued for $343,172, including GST, and TGS argues there is a substantial dispute regarding the existence of the debt claimed. The legal issues in the case revolve around the interpretation of the contractor's performance bond, the conditions for calling up the bond, and whether there is a substantial dispute about the debt claimed. The Court found that the bond is conditional in nature and not payable on demand. To make a call on the bond, the Council must prove that CHB breached its contractual obligations and suffered damages as a result. The Court found that there is a substantial dispute regarding the Council's entitlement to call up the bond, both in terms of the Council's right to resume possession of the site and the extent of CHB's liability for damages and liquidated damages. As a result, the statutory demand was set aside. The Court also noted that if a dispute resolution process under the Contract had been triggered, the statutory demand could have been set aside on other grounds, but this was not necessary given the substantial dispute over the debt claimed.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established