| IN THE COURT OF APPEAL OF NEW ZEALAND I TE KŌTI PĪRA O AOTEAROA |
| CA449/2017 [2018] NZCA 132 |
| BETWEEN | RICHINA PACIFIC LIMITED |
| AND | SAMSON CORPORATION LIMITED |
| Hearing: | 21 March 2018 |
Court: | Kós P, Miller and Gilbert JJ |
Counsel: | D J Chisholm QC and DAC Bullock for First Appellant |
Judgment: | 1 May 2018 at 3.00 pm |
JUDGMENT OF THE COURT
AThe appeal is dismissed.
BThe respondent is entitled to one set of costs, payable by both appellants, for a standard appeal on a band B basis and usual disbursements. We certify for second counsel.
____________________________________________________________________
REASONS OF THE COURT
(Given by Miller J)
The principal question in this appeal is whether a performance bond given by AAI Ltd (the second appellant) to secure the performance of a building contractor, Mainzeal Property & Construction Ltd, was discharged when Mainzeal and the building owner, Samson Corporation Ltd (the respondent), agreed to allow the contract engineer to certify practical completion on terms that expressly excluded part of the contract works, an automated car stacker.
The bond provided that it would be “null and void” if Mainzeal “duly carries out and fulfils all the obligations imposed on [it] by the Contract Documents prior to commencement of the period of Defects Liability”.
Mainzeal went into receivership on 6 February 2013 without completing its obligations under the construction contract. In particular, the car stacker never met the contractual performance standard. The appellants do not dispute this, but they argue that AAI is not liable to pay out under the bond. The case for AAI is as follows: the period of defects liability commenced when the engineer to the contract certified practical completion; the certificate, which was given on 25 September 2012, could not and did not have partial effect, so the bond was discharged at that point; or alternatively that the parties instead varied the contract by agreeing to treat the car stacker as a deferred work to which no practical completion requirement attached.
Richina Pacific Ltd (the first appellant) was the parent company of Mainzeal, and it agreed to indemnify AAI for any payments the latter made pursuant to the bond. It contends, in the alternative to AAI’s argument, that the bond was discharged because AAI was disadvantaged; the arrangement between Samson and Mainzeal allowed Samson into possession prematurely and resulted in Samson paying retentions prematurely. It is said that the construction contract did not provide for these things. The bond contained an indulgence clause stating that it was not discharged by, among other events, any alteration in the terms of the construction contract, but Richina says this clause does not apply. In its written submissions AAI itself did not advance this argument, which presumes that the practical completion certificate did not discharge the bond, but when asked Mr Stokes (who appeared for AAI) adopted it before us.[1]
[1]We were told that…
Keep reading for free
Create a free CaseChat account to read Richina Pacific Ltd v Samson Corporation Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] NZCA 132
- Decision Date
CaseChat Overview and Summary
The appeal was dismissed, and Samson was awarded costs on a band B basis. The Court certified for second counsel.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.