UGL (NZ) Limited v Trade Indemnity + Surety Limited

Link copied
Case Copied 7 min read

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV 2013-404-003480 [2013] NZHC 2623

BETWEEN UGL (NZ) LIMITED Plaintiff

AND

TRADE INDEMNITY+ SURETY LIMITED

Defendant

Hearing: 9 October 2013

Appearances:

D M Hughes and E E Cowle for the Plaintiff
W G C Templeton for the Defendant

Judgment:

9 October 2013

JUDGMENT OF GILBERT J

This judgment was delivered by me on 9 October 2013 at 3.30 pm

Pursuant to Rule 11.5 of the High Court Rules.

Registrar/Deputy Registrar

Date:

UGL (NZ) LIMITED v TRADE INDEMNITY+ SURETY LIMITED [2013] NZHC 2623 [9 October 2013]

[1]      UGL  (NZ)  Limited  seeks  summary  judgment  against  Trade Indemnity

+ Surety Limited for $1,210,028.54 being the monies said to be payable under a bond. The critical issue is whether UGL must prove loss before it is entitled to payment under the bond.   UGL concedes that if it is required to prove loss, its application for summary judgment must be dismissed because the quantum of loss cannot be determined in this application.  The sole issue for determination therefore concerns the proper construction of the bond.

Background

[2]      UGL   contracted   with   Transpower   New   Zealand   Limited   to   design, manufacture and install underground cables between the Hobson, Penrose and Pakuranga substations.   UGL subcontracted some of the work to JB Contractors Limited (now in receivership and in liquidation) pursuant to a subcontract agreement dated 1 September 2011.   The “Subcontract Sum” was $12,100,285.42 excluding GST.

[3]      JB Contractors agreed to provide security for 10 per cent of the Subcontract Sum to ensure its performance under the subcontract.  Clause 4 of the subcontract agreement relevantly provides:

4        Security

4.1Security  is  for  the  purpose  of  ensuring  the  due  and  proper performance of this Subcontract.  The Subcontractor will provide security in an amount equal to ten percent of the Subcontract.  The security will be in the form of an unconditional undertaking given by a New Zealand or Australian bank.

4.2Security will be lodged with UGL when this Subcontract, executed by the Subcontractor, is returned to UGL.   No payment otherwise due under the Subcontract shall become payable until the Subcontractor and its surety have executed and delivered the security to UGL.

4.3UGL will be free to convert the Security into money upon breach by the Subcontractor of any of its obligations under this Subcontract. UGL will not be liable for any loss caused by the conversion.  UGL will release the security on the expiration of the Defects Liability Period.

[4]      Rather than obtaining an unconditional undertaking from an Australian or New Zealand bank, JB Contractors procured a bond from Trade Indemnity in the form of a deed which Trade Indemnity signed as Surety.  UGL accepted this bond as performance of JB Contractors’ obligation under cl 4 of the subcontract agreement, even though it did not strictly conform to the requirements of that clause.

[5]      The recitals to the bond record that JB Contractors is required to provide UGL, as the Principal, with security in the form of a bond to ensure performance…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read UGL (NZ) Limited v Trade Indemnity + Surety Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] NZHC 2623
Decision Date

CaseChat Overview and Summary

UGL (NZ) Limited sought summary judgment against Trade Indemnity + Surety Limited for the sum of $1,210,028.54, which UGL claimed was payable under a bond. UGL argued that it was entitled to payment under the bond, but Trade Indemnity contended that UGL must first prove a loss before it can recover under the bond. The primary issue for the court was to determine whether UGL was required to prove loss before it could claim payment under the bond. If UGL needed to prove loss, it would be unable to recover in this summary judgment application, as the quantum of loss could not be determined in such proceedings.

The court examined the subcontract agreement between UGL and JB Contractors Limited, which required JB Contractors to provide security for 10% of the subcontract sum to ensure its performance. JB Contractors provided a bond from Trade Indemnity as surety instead of an unconditional undertaking from a bank. The bond stated that Trade Indemnity was jointly and severally liable with JB Contractors for payment of the sum of $1,210,028.54. The court considered the proper construction of the bond and the subcontract agreement, particularly clause 4.3, which stated that UGL could convert the security into money upon breach by JB Contractors of any of its obligations under the subcontract. The court also examined relevant case law, including Trafalgar House Construction (Regions) Ltd v General Surety & Guarantee Co. Ltd, which held that UGL must prove breach and loss before it can recover under the bond.

The court held that the bond issued by Trade Indemnity did not require payment on demand following a breach by JB Contractors under the subcontract agreement. Instead, it was in the nature of a contract of guarantee, and Trade Indemnity's obligation was to pay the damages sustained by UGL in respect of all defaults by JB Contractors up to the date of termination of the contract. As UGL had not proved loss, its application for summary judgment was dismissed. Costs were reserved.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established