JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CHAMBERS
CITATION: RE GRAHAM ANSTEE-BROOK; EX PARTE KARARA MINING LTD [No 2] [2013] WASC 59
CORAM: LE MIERE J
HEARD: 25 JULY 2012
DELIVERED : 1 MARCH 2013
FILE NO/S: CIV 1364 of 2012
MATTER :An Application for a Writ of Certiorari directed to Mr Graham Anstee-Brook exercising jurisdiction pursuant to the Construction Contracts Act 2004 (WA)
EX PARTE
KARARA MINING LTD
Applicant
Catchwords:
Prerogative writ - Certiorari - Order nisi - Construction Contracts Act 2004 (WA) - Application for adjudication - Judicial review - Jurisdictional error - Error of law - Procedural fairness
Legislation:
Construction Contracts Act 2004 (WA), s 6, s 26, s 27, s 27(1), s 30, s 31, s 31(2)(b), s 32, s 37(2)(b), s 38, s 39, s 40, s 41, s 42, s 43, s 45(1), s 46
Construction Contracts Regulations 2004 (WA)
State Administrative Tribunal Act 2004 (WA)
Result:
Application dismissed
Category: B
Representation:
Counsel:
Applicant: Ms P E Cahill SC & Mr A D Bereyne
Solicitors:
Applicant: Jackson McDonald
Case(s) referred to in judgment(s):
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190
Craig v State of South Australia (1995) 184 CLR 163
Perrinepod Pty Ltd v Georgiou Building Pty Ltd [2011] WASCA 217
Re Carey; Ex parte Exclude Holdings Pty Ltd [2006] WASCA 219
Re Graham Anstee‑Brook; Ex parte Mount Gibson Mining Ltd [2011] WASC 172
Re State Administrative Tribunal; Ex parte McCourt [2007] WASCA 125
LE MIERE J: On 16 March 2012 the court made an order nisi for a writ of certiorari to quash a determination by Mr Graham Anstee‑Brook (the Adjudicator) under the Construction Contracts Act 2004 (WA) (the Act) in respect of an application for adjudication by DM Drainage and Construction Pty Ltd (DMC) made on 28 February 2012 determining that the applicant, Karara, must pay DMC $4,981,285.50 (the Determination). Karara now applies for the order nisi to be made absolute.
The Determination
Karara is developing port, rail and mine facilities required for the mining, transport and export of iron ore deposits at the Karara mine site, approximately 328 km north north-east of Perth. The project is a greenfields project with the bulk of the works being performed at a remote location. Water is required for the mine site operation and potable use. The water will be supplied from Twin Hills Water Supply System which consists of Twin Hills borefield, two transfer pumping stations and a pipeline which is approximately 152 km long and connects Twin Hills borefield to Karara mine site. By a contract dated 6 July 2010 DMC agreed to construct the pipeline and associated works. The Determination relates to a claim for $4,975,650.70 by DMC. Karara refused to pay the claim.
DMC applied for an adjudicator to be appointed to determine the dispute under the Act. Mr Graham Anstee‑Brook was appointed the adjudicator. DMC served its application for adjudication (Application) on Karara…
Continue reading Re Graham Anstee-Brook; [No 2]
Sign in free to access the full text
- AGLC
- Re Graham Anstee-Brook; [No 2] [2013] WASC 59
- Case
- [2013] WASC 59
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining whether the adjudicator's decision contained jurisdictional errors, errors of law, and whether the process adhered to principles of natural justice. Specifically, the court needed to assess whether the adjudicator correctly interpreted the law, exercised their powers within the scope of the statutory framework, and whether the process was fair and unbiased.
In delivering the judgment, the court examined the adjudicator's decision thoroughly, finding no evidence of jurisdictional error or error of law. The court held that the adjudicator had correctly applied the relevant provisions of the Construction Contracts Act and had exercised their powers in accordance with the law. Furthermore, the court found that the process followed by the adjudicator was fair and did not contravene the principles of natural justice. Consequently, the application for judicial review was dismissed, and the adjudicator's decision was upheld.
The court ordered that the applicant pay the respondent's costs of the application for judicial review, to be taxed on the higher scale if not agreed upon within 14 days.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.