District Court
New South Wales
Medium Neutral Citation: Manfate Pty Ltd v Krahe & Krahe (No 1) [2016] NSWDC 70 Hearing dates: 7-10 March 2016; 15-17 March 2016 Date of orders: 17 March 2016 Decision date: 17 March 2016 Jurisdiction: Civil Before: Neilson DCJ Decision: Verdict and judgment for the plaintiff against the defendants in the amount of $122,335.10
Catchwords: CIVIL – Building and construction – Breach of contract – Oral contract between parties for construction of restaurant – Whether mention of a price was an estimate or a quote - Meaning of terms “estimate” and “quote” – Evidence indicating “fixed price” quote implausible – Approximately 9 years elapsed between oral agreement and swearing of affidavits – Past dealings between parties suggestive of informal, trusting and flexible contractual relationships – Contract formed prior to permission being granted by local council to perform works – Lack of specifications for the type of construction materials used – Variation to original plans resulting in significantly higher costs not discussed by parties – Implausible that parties would not discuss significant cost increase if contract were a fixed price contract
DAMAGES – Quantum meruit – Plaintiff claimed on quantum meruit basis if Court were to find that no contracted had been formed – Damages for unjust enrichment would exceed damages for breach of contract – Damages for unjust enrichment would unjustly enrich the plaintiff
WORDS AND PHRASES – Estimate – Quote – Fixed price quoteLegislation Cited: Environmental Planning and Assessment Act 1979 (NSW) Cases Cited: Brambles Holdings Ltd v Bathurst City Council [2001] NSWCA 61; (2001) 53 NSWLR 153
Hayward v Timilty [2009] NSWDC 54
Kyren Pty Ltd v Built Projects Pty Ltd [2006] SASC 204
Monarch Building Systems Pty Ltd v Quinn Villages Pty Ltd [2006] QCA 210
Watson v Foxman (1995) 49 NSWLR 315Texts Cited: Shorter Oxford Dictionary (Oxford University Press, 5th Ed, 2002) Category: Principal judgment Parties: Manfate Pty Ltd (Plaintiff)
Peter Krahe (First Defendant)
Paula Krahe (Second Defendant)Representation: Counsel:
Solicitors:
Ms J Steel (Plaintiff)
Mr P Reynolds (Defendants)
Colins Biggers & Paisley (Plaintiff)
Clifton Legal (Defendants)
File Number(s): 2015/69524 Publication restriction: No
Judgment
-
HIS HONOUR: The plaintiff company Manfate Pty Ltd was incorporated on 24 February 1995. Its directors and shareholders are Mr Thomas Christopher Murphy and his wife Mrs Judith Avril Murphy. The company was incorporated to carry on the business of Mr Thomas Christopher Murphy, a builder, and more recently a master builder. Manfate Pty Ltd now trades as Tom Murphy Builder. The defendants, Mr Peter John Krahe and his wife Mrs Paula Joanne Krahe, live in Tenterfield and have for many, many years lived in that town. They own a substantial block of land in the Tenterfield township.
-
The plaintiffs claim is for $92,142.40 plus interest. The cause of action relied upon by the plaintiff is a breach of contract. In the alternative, the plaintiff claims $112,477.84 plus interest on a quantum meruit for goods supplied and services rendered.
-
There is no dispute about…
Keep reading for free
Create a free CaseChat account to read Manfate Pty Ltd v Krahe and Krahe (No 1) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] NSWDC 70
- Decision Date
CaseChat Overview and Summary
The court was required to determine the nature of the agreement between the parties. Specifically, whether the mention of a price by the plaintiff to the defendants constituted a fixed price quote or an estimate. The court considered the meaning of the terms "estimate" and "quote," and whether the evidence indicated that the price mentioned was a fixed price quote. The court also considered the fact that approximately nine years had elapsed between the oral agreement and the swearing of affidavits, and the past dealings between the parties which suggested informal, trusting and flexible contractual relationships. Additionally, the court considered whether a contract had been formed prior to permission being granted by the local council to perform the works, the lack of specifications for the type of construction materials used, and the variation to the original plans resulting in significantly higher costs that were not discussed by the parties.
The court found that it was implausible that the parties would not discuss a significant cost increase if the contract was a fixed price contract. The court held that the price mentioned by the plaintiff to the defendants was an estimate rather than a fixed price quote, and that the parties had not entered into a binding contract for the construction of the restaurant. The court further held that the plaintiff's claim for damages on a quantum meruit basis was unjustified as it would result in unjust enrichment of the plaintiff. The court awarded damages to the plaintiff in the amount of $122,335.10.
The court's verdict and judgment were in favour of the plaintiff against the defendants. The court ordered the defendants to pay the plaintiff the sum of $122,335.10 in damages.
Orders
Orders of the court
Verdict and judgment for the plaintiff against the defendants in the amount of $122,335.10
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.