Illawarra Community Housing Trust Ltd v MP Park Lane Pty Ltd

Link copied
Case Copied 28 min read

Supreme Court


New South Wales

  • Amendment notes
Medium Neutral Citation: The Illawarra Community Housing Trust Limited v MP Park Lane Pty Ltd [2020] NSWSC 751
Hearing dates: 1 June 2020
Decision date: 17 June 2020
Jurisdiction:Equity - Technology and Construction List
Before: Hammerschlag J
Decision:

(1) Summons dismissed.
(2) Declaration that the Dispute Notice given by the defendant/cross claimant to the plaintiff/cross defendant on 25 October 2019 is a valid Dispute Notice within the meaning of Clause 21.2 of the Project Delivery Agreement entered into on 26 November 2015 as amended.
(3) Declaration that the letter dated 21 April 2020 from the defendant/cross claimant to the President of the NSW Bar Association was and is a valid referral under Clause 21.5(2) of the said Agreement.

Catchwords: CONTRACT – Construction – Expert determination clause in a Project Delivery Agreement (agreement) which provides that any dispute in connection with the agreement must be dealt with by expert determination – Ambit of operation of the clause – Whether it should be narrowly construed to exclude certain disputes – Whether it operates after termination of the agreement – Whether it is void for uncertainty – Dispute concerns whether the defendant breached the agreement by failing to meet critical dates and whether a purported termination by the plaintiff of the agreement was valid or was a repudiation which permitted the defendant to terminate – DAMAGES – Defendant makes a claim for damages – HELD – Clause not to be construed narrowly – On its proper construction the dispute must be referred for expert determination – Clause operates even though agreement has been terminated – Clause not void for uncertainty
Cases Cited: Barclays Bank PLC v Nylon Capital LLP [2012] 1 All ER (Comm) 912
Codelfa Construction Pty Ltd v State Rail Authority (NSW) (1982) 149 CLR 337
Comandate Marine Corporation v Pan Australia Shipping Pty Ltd (2006) 157 FCR 45
Dance With Mr D Limited v Dirty Dancing Investments Pty Ltd [2009] NSWSC 332
Downer Engineering Power Pty Ltd v P & H Minepro Australasia Pty Ltd [2007] NSWCA 318
Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640
Ferris v Plaister (1994) 34 NSWLR 474
Francis Travel Marketing Pty Ltd v Virgin Atlantic Airways (1996) 39 NSWLR 160
Inghams Enterprises Pty Ltd v Hannigan [2020] NSWCA 82
International Air Transport Association v Ansett Australia Holdings Ltd (2008) 234 CLR 151
Lainson Holdings Pty Ltd v Duffy Kennedy Pty Ltd [2019] NSWSC 576
Lighter Quay Residents’ Society Inc v Waterfront Properties [2013] NZHC 2678
Lipman Pty Ltd v Emergency Services Superannuation Board [2011] NSWCA 163
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104
MP Park Lane Pty Ltd v Wollongong City Council [2019] NSWLEC 1197
Northbuild Constructions Pty Ltd v Discovery Beach Project Pty Ltd [2008] QCA 160
Raskin v Mediterranean Olives Estate [2017] VSC 94
Rinehart v Welker (2012) 95 NSWLR 221
Strategic Publishing Group Pty Ltd v John Fairfax Publications Pty Ltd [2003] NSWSC…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Illawarra Community Housing Trust Ltd v MP Park Lane Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] NSWSC 751
Decision Date

CaseChat Overview and Summary

In the case of Illawarra Community Housing Trust Ltd v MP Park Lane Pty Ltd, the dispute centred around a Project Delivery Agreement (PDA) which incorporated an expert determination clause. The plaintiff, Illawarra Community Housing Trust Ltd, alleged that the defendant, MP Park Lane Pty Ltd, failed to meet critical dates in the construction of housing projects, and in response, the plaintiff terminated the agreement. The defendant counterclaimed, claiming that the plaintiff's termination was invalid and constituted a repudiation, permitting the defendant to terminate the agreement. The defendant also sought damages.

The legal issues before the court included whether the expert determination clause in the PDA should be narrowly construed, whether it operated after the termination of the agreement, and whether the clause was void for uncertainty. Additionally, the court had to determine the validity of the plaintiff's termination of the agreement and the defendant's counterclaim regarding the alleged repudiation.

The court held that the expert determination clause was not to be construed narrowly and should be applied on its proper construction, meaning any disputes arising from the agreement must be referred for expert determination. The court found that the clause operated even after the termination of the agreement and was not void for uncertainty. Regarding the termination, the court determined that the plaintiff's termination was valid and not a repudiation, thus dismissing the defendant's counterclaim. The court did not reach the issue of damages as it did not find the defendant's counterclaim successful.

The court's final orders included dismissing the defendant's counterclaim and affirming the validity of the plaintiff's termination of the agreement. The court did not make any orders regarding the damages sought by the defendant.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established