Earthtec Pty Ltd v Livingstone Shire Council

Link copied
Case Copied 74 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Earthtec Pty Ltd v Livingstone Shire Council [2023] QSC 22

PARTIES:

EARTHTEC PTY LTD (ACN 093 558 582)

Plaintiff/Respondent

v
LIVINGSTONE SHIRE COUNCIL (ABN 95 399 253 048)

Defendant/Applicant

FILE NO/S:

BS10709/21

DIVISION:

Trial Division

PROCEEDING:

Application

ORIGINATING COURT:

Supreme Court of Queensland

DELIVERED ON:

17 February 2023

DELIVERED AT:

Brisbane

HEARING DATE:

24 & 25 October 2022

JUDGE:

Freeburn J

ORDERS:

1. Pursuant to rule 171 of the Uniform Civil Procedure Rules 1999 (UCPR), the statement of claim is struck out.

2.   The plaintiff have leave to re-plead.

3. Pursuant to rule 670(1) of the UCPR, or alternatively s 1335(1) of the Corporations Act 2010 (C’th) the plaintiff give security for the defendant’s costs of the proceeding to a proposed mediation in the sum of $550,000.

4.   The parties be heard on the form of these orders and costs.

CATCHWORDS:

PROCEDURE – SUPREME COURT PROCEDURE – QUEENSLAND – PROCEDURE UNDER THE UNIFORM CIVIL PROCEDURE RULES – PLEADINGS CONTAINING IMMATERIAL FACTS – STRIKING OUT – STATEMENT OF CLAIM – where an application is brought to strike out the claim and statement of claim, in part or in whole –  where the applicant applies to strike out paragraphs in pleadings on the basis that they concern matters that were made in a “without prejudice” conference – whether the statement of claim pleads material facts or a narrative  – whether the matters pleaded, if not stated would take the defendant by surprise – whether paragraphs in the pleadings containing matters made in a “without prejudice” conference should be struck out

PROCEDURE – SUPREME COURT PROCEDURE – QUEENSLAND – PROCEDURE UNDER THE UNIFORM CIVIL PROCEDURE RULES – CORPORATIONS – SECURITY FOR COSTS – AMOUNT OF SECURITY - where it is not disputed that security for the applicants’ costs is to be proved, but there is a dispute as to the amount of security – where the quantum of likely costs contained in both parties’ expert reports is starkly different – whether the quantum specified in either party’s expert report will be suitable as security for costs – use of a broad-brush approach to the quantum of security

COUNSEL:

D de Jersey KC and B Readings for the applicant

BE Codd and CH Matthews for the respondent

SOLICITORS:

McCullough Robertson for the applicant

Shand Taylor Lawyers for the respondent

REASONS

  1. Earthtec Pty Ltd (Earthtec) is a contractor in the business of providing civil construction services such as earthmoving, road and revetment wall construction. Earthtec entered into numerous contracts with the defendant, the Livingstone Shire Council (Livingstone) for the construction of a part of the Scenic Highway adjacent to Statue Bay, near Yeppoon (the project). The project was undertaken by Livingstone as the principal.

  2. This application is two-fold. First, Livingstone applies, pursuant to rule 171 of the Uniform Civil Procedure Rules 1999 (Qld) (UCPR), to strike out Earthtec’s statement of claim, whether in part or in whole. Second, Livingstone seeks an…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Earthtec Pty Ltd v Livingstone Shire Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] QSC 22
Decision Date

CaseChat Overview and Summary

Earthtec Pty Ltd brought an action against Livingstone Shire Council, asserting claims related to alleged breaches of contract and misrepresentations. The council responded by filing an application to strike out certain parts of the statement of claim, arguing they contained information disclosed during a "without prejudice" conference, which should not be part of the formal pleadings. The council also disputed the amount of security for costs Earthtec should provide.

The court considered whether the "without prejudice" material should be excluded from the statement of claim and whether the quantum of security for costs was appropriately set. The court ruled that the "without prejudice" material did not constitute relevant facts necessary for the case and should be removed from the pleadings. The court also decided that the amount of security for costs should be set at $550,000, based on a broad-brush approach that considered the nature and complexity of the case.

The court ordered that specific parts of the statement of claim be struck out and that Earthtec be allowed to re-plead. Additionally, the court mandated that Earthtec provide security for the council’s costs up to the proposed mediation phase in the sum of $550,000. The court also directed the parties to discuss the form of these orders and the allocation of costs.

Orders

Orders of the court

1. Pursuant to rule 171 of the Uniform Civil Procedure Rules 1999 (UCPR), the statement of claim is struck out.

2. The plaintiff have leave to re-plead.

3. Pursuant to rule 670(1) of the UCPR, or alternatively s 1335(1) of the Corporations Act 2010 (C’th) the plaintiff give security for the defendant’s costs of the proceeding to a proposed mediation in the sum of $550,000.

4. The parties be heard on the form of these orders and costs.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established