NEW SOUTH WALES COURT OF APPEAL
CITATION: Commonwealth of Australia v Cockatoo Dockyard Pty Ltd [2006] NSWCA 322
FILE NUMBER(S):
40789/04
40124/05
HEARING DATE(S): 30 May 2006, 31 May 2006,1 June 2006
DECISION DATE: 23/11/2006
PARTIES:
Commonwealth of Australia
Cockatoo Dockyard Pty Limited
JUDGMENT OF: Giles JA Santow JA Tobias JA
LOWER COURT JURISDICTION: Supreme Court
LOWER COURT FILE NUMBER(S): SC50165/01
LOWER COURT JUDICIAL OFFICER: McDougall J
COUNSEL:
A: P T Taylor SC / D Caspersonn
R: T G Parker SC / B F Katekar
SOLICITORS:
A: Australian Government Solicitor, Sydney
R: Allens Arthur Robinson, Sydney
CATCHWORDS:
ESTOPPEL – dispute arising after arbitration – res judicata – Anshun estoppel – issue estoppel – cause of action estoppel – principles – effect of a deed of settlement – whether estoppel “available” under a deed of settlement – whether special circumstances within meaning of Arnold v National Westminster Bank PLC [1991] 2 AC 93 – CONTRACT – contract with Commonwealth – whether contractual obligations subsisted after the expiry of a contract – PROCEDURAL FAIRNESS – whether denial of procedural fairness – whether primary judge searched for and found an estoppel substantially different than that alleged – TORTS – NEGLIGENCE – liability – whether conduct gave rise to liability – WORKERS’ COMPENSATION – ENTITLEMENT TO AND LIABILITY FOR COMPENSATION – persons liable to pay compensation – whether Commonwealth liable to reimburse a company for workers’ compensation costs pursuant to a contract – whether conduct of contractor gave rise to a liability to pay for costs itself – whether reimbursement for such costs capable of including a fee for profit margin
LEGISLATION CITED:
Administrative Law Act 1978 (Vic)
Arbitration Act 1979 (UK)
Commercial Arbitration Act 1984 (NSW)
Commercial Arbitration Act 1984 (Vic)
Dried Fruits Act 1928–1935 (Cth)
Local Government Act 1989 (Vic)
Supreme Court Rules 1970 (NSW)
DECISION:
Appeal dismissed with costs
JUDGMENT:
IN THE SUPREME COURT
OF NEW SOUTH WALES
COURT OF APPEAL
CA 40789/04
CA 40124/05
SC 50165/01GILES JA
SANTOW JA
TOBIAS JAThursday 23 November 2006
COMMONWEALTH OF AUSTRALIA v COCKATOO DOCKYARD PTY LTD
Facts
Cockatoo Dockyard Pty Ltd (Codock) occupied and used a Naval Dockyard on Cockatoo Island pursuant to a series of agreements made with the Commonwealth of Australia from 1 March 1933 to 31 December 1992. Asbestos products were used at the Dockyard throughout that time in pipes and equipment as well as in operations involving the fitting of ships. As a result, many of Codock’s employees contracted asbestos related diseases and commenced actions against Codock for damages.
Codock alleged that the Commonwealth was liable for such damages pursuant, inter alia, to the terms of a trading agreement and lease that were entered into in 1972, and varied in 1976 and 1987. Together with some subsequent amendments, this document was referred to as the “1972 TAL”. The 1972 TAL adopted the Commonwealth’s Standard Conditions for the Determination of the Costs of Contracts and contained a provision that any dispute arising between the Commonwealth and Codock should be…
Keep reading for free
Create a free CaseChat account to read Commonwealth of Australia v Cockatoo Dockyard Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] NSWCA 322
- Decision Date
CaseChat Overview and Summary
The central legal issues before the Court of Appeal were whether the primary judge erred in finding that the Commonwealth was not estopped from pursuing certain defences against Codock's claims. This involved determining whether the prior arbitration had definitively resolved the issues Codock sought to raise in the current proceedings, and whether the terms of a deed of settlement between the parties precluded the operation of estoppel. The Court also considered whether the primary judge had denied the Commonwealth procedural fairness by identifying an estoppel substantially different from that alleged by the Commonwealth.
The Court of Appeal, in a joint judgment, dismissed the Commonwealth's appeal. The judges reasoned that the principles of issue estoppel and cause of action estoppel, as established in cases like *Jackson v Goldsmith* and *Blair v Curran*, require a clear and solemn finding on a point distinctly put in issue. They found that the prior arbitration did not necessarily involve such definitive findings on the specific issues Codock sought to recover for in the present proceedings, particularly concerning workers' compensation costs incurred after the expiry of the 1972 TAL. The Court also considered the effect of a deed of settlement, concluding that it did not prevent the operation of estoppel in this context, nor did it find that the primary judge had denied the Commonwealth procedural fairness.
The appeal was dismissed with costs.
Orders
Orders of the court
Appeal dismissed with costs
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
In June 1990, the Commonwealth announced its decision to decommission the Dockyard. The 1972 Lease expired on 31 December 1992 whereupon Codock ceased occupation of the Dockyard. The 1972 TAL also expired or terminated on that date.(c) The disputes between the parties leading to the arbitration It was a term of the Wartime Agreement, the 1956 Agreement and the 1963 Agreement that if any dispute or difference arose between the Commonwealth and Codock, it should be referred to arbitration. The 1954 Lease and the 1972 TAL contained a similar provision. A number of disputes arose between the parties upon the expiry of the 1972 TAL on 31 December 1992. These arose from the Australian Government’s announcement that it intended to sell Cockatoo Island and allocate the refitting of two of the Navy’s submarines, HMAS Onslow and HMAS Otama, to the Garden Island Dockyard. Codock contended that this decision gave rise to its main contractual claim against the Commonwealth because of its incompatibility with an alleged collateral agreement whereby, in consideration of Codock’s entry into the 1972 TAL, the Commonwealth had undertaken to place orders with Codock for the carrying out by it of all refits of Oberon Class submarines until the completion of any program for such refits. Codock also made an unrelated claim against the Commonwealth in which it sought to recover monies it had paid, up to and in October 1995. Those monies were said to have arisen out of common law claims made by Codock’s former employees in respect of asbestos-related injuries they had suffered and which arose out of their employment at the Dockyard (the Claims). Codock maintained that these amounts (to the extent to which they had not been wholly or partially paid by its insurers) constituted “overhead expenses” in respect of which it was entitled to be reimbursed by the Commonwealth. The expression “overhead expenses” was alleged to encompass the indirect costs attributable to the work Codock had undertaken for the Commonwealth where those expenses were attributable to what was known as “costs-plus work” performed by Codock for the Commonwealth and which constituted the predominant operations of Codock at the Dockyard. Relevantly, those costs were said to include not only the costs of defending and settling personal injury actions by former employees of Codock where those injuries were asbestos related (such as asbestosis and mesothelioma) but also the net amount of damages paid to those ex-employees in respect of which Codock had not been indemnified either in whole or in part by its insurers. The principal basis upon which this claim was propounded by Codock was founded upon the terms of the 1972 TAL. In particular, Codock relied upon cll 2(3) and 2(4) of the 1972 TAL which provided as follows:“2(3)The Commonwealth shall pay the Company for work ordered under this Agreement on the price basis specified in each order. … Where payment under any order is calculated on a cost plus profit or incentive basis, costs shall not include rent and the profit for work done on a cost plus basis shall be 5% of the cost of direct labour, direct material, direct expense (including subcontracts) and overhead. In this clause, ‘cost’ or ‘costs’ shall mean and shall be the cost as determined in accordance with the Department of Supply Standard Conditions Applicable to Contracts on a Cost Plus Profit Basis, as revised from time to time.2(4)The Company shall not increase the overhead rate as agreed from time to time chargeable to cost plus profit or cost incentive price orders without the prior approval of the Commonwealth.”