SUPREME COURT OF QUEENSLAND
CITATION:
Cape Byron Power 1 Pty Ltd & Ors v Downer Energy Systems Pty Ltd & Ors [2022] QSC 294
PARTIES:
CAPE BYRON POWER I PTY LTD ACN 074 408 923 (formerly known as Delta Electricity Australia Pty Ltd) and CAPE BYRON POWER II PTY LTD ACN 095 991 638 (formerly known as Sunshine Renewable Energy Pty Ltd) as joint venturers in the Sunshine Electricity Joint Venture
(first plaintiffs)
CAPE BYRON POWER II PTY LTD ACN 095 991 638 (formerly known as Sunshine Renewable Energy Pty Ltd)
(second plaintiff)
NEW SOUTH WALES SUGAR MILLING CO-OPERATIVE LIMITED ACN 051 052 209
(third plaintiff)
v
DOWNER ENERGY SYSTEMS PTY LIMITED ACN 067 158 954(first defendant)
DMH PLANT SERVICES PTY LTD ACN 010 975 256 (formerly known as MHPS Plant Services Pty Ltd and Clyde Babcock-Hitachi Pty Ltd)
(second defendant)
DOWNER EDI LIMITED ACN 003 872 848
(third defendant)
FILE NO/S:
BS 11011 of 2014
DIVISION:
Trial Division
PROCEEDING:
Trial
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
22 December 2022
DELIVERED AT:
Brisbane
HEARING DATE:
30 and 31 May 2022 and 1, 2, 3, 6, 7, 8, 9, 10, 13, 14, 15, 16, 20, 21, 22 and 23 June 2022 and 31 August 2022 and 1 September 2022
JUDGE:
Applegarth J
ORDER:
1. The plaintiffs have any further leave that may be required pursuant to rule 376(4) of the Uniform Civil Procedure Rules 1999 (Qld) in addition to the leave granted by paragraph two of the order of Douglas J made 19 September 2017 to amend paragraph 72, 73, 74 and 75 of their pleading in accordance with the Further Amended Statement of Claim filed 31 October 2017.
2. The defendants have leave to further amend their defence by reinstating those parts of their defence to the plaintiffs’ negligence claim that were deleted in the Amended Defence to the Further Amended Statement of Claim, particularly the matters deleted in sub-paragraph 69(b) and 71 of the Amended Defence filed on 15 December 2017.
3. The plaintiffs bring in draft minutes of judgment to reflect the judgments indicated in the reasons for judgment published on 22 December 2022.
4. The matter be adjourned to a date to be fixed not before 30 January 2023 for the purpose of pronouncing judgment and making directions about submissions in relation to interest on the judgment sums and costs.
CATCHWORDS:
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – DISCHARGE, BREACH AND DEFENCES TO ACTION FOR BREACH – where the first plaintiffs contracted for the first and second defendants to design, engineer, procure, construct, test and commission two practically identical co-generation plants at Broadwater and Condong (“the EPC Contract”) – where each plant was operated by the third plaintiff – where each plant contained a boiler system that would produce steam to generate electricity – where, in constructing the boiler at Broadwater, the first and second defendants erroneously installed and programmed a damper that controls the flow of air to the boiler’s oil burner in reverse…
Keep reading for free
Create a free CaseChat account to read Cape Byron Power 1 Pty Ltd v Downer Energy Systems Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] QSC 294
- Decision Date
CaseChat Overview and Summary
The court found that the reverse operation of the damper was a substantial cause of the overheating and damage. The plaintiffs' evidence, supported by expert reports and boiler operators' testimonies, demonstrated that the boiler operated differently and did not overheat as frequently after the damper was corrected. The court rejected the defendants' argument that overheating was due to factors other than the reverse operation of the damper. Regarding the Deed of Release, the court held that the plaintiffs were not aware of the reverse operation at the time of execution and could not have become aware of it by making reasonable enquiries. The court also found that the limitation period for the breach of contract claims did not start from the installation of the defective damper but from the date of practical completion of the works.
The court concluded that the defendants were liable for the breach of contract and awarded damages to the plaintiffs. The court granted the plaintiffs leave to amend their pleadings and directed the parties to bring in draft minutes of judgment and set a date for pronouncing judgment and making directions about submissions in relation to interest on the judgment sums and costs.
Orders
Orders of the court
1. The plaintiffs have any further leave that may be required pursuant to rule 376(4) of the Uniform Civil Procedure Rules 1999 (Qld) in addition to the leave granted by paragraph two of the order of Douglas J made 19 September 2017 to amend paragraph 72, 73, 74 and 75 of their pleading in accordance with the Further Amended Statement of Claim filed 31 October 2017.
2. The defendants have leave to further amend their defence by reinstating those parts of their defence to the plaintiffs’ negligence claim that were deleted in the Amended Defence to the Further Amended Statement of Claim, particularly the matters deleted in sub-paragraph 69(b) and 71 of the Amended Defence filed on 15 December 2017.
3. The plaintiffs bring in draft minutes of judgment to reflect the judgments indicated in the reasons for judgment published on 22 December 2022.
4. The matter be adjourned to a date to be fixed not before 30 January 2023 for the purpose of pronouncing judgment and making directions about submissions in relation to interest on the judgment sums and costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
There is no dispute that in constructing and programming the boiler so that the ATO Damper operated in reverse, and then not identifying that it did, the first and second defendants breached their contract with the first plaintiffs. Was the reverse operation of the ATO Damper a substantial cause of the overheating that resulted in damage to the grate? The central issue in the case is about causation. The causation question stated above involves important factual questions about the practical consequences of the ATO Damper operating in reverse. In particular, did it:1. deprive the grate of undergrate air, and thereby:(a) reduce the intended cooling effect of undergrate air;(b) reduce combustion of unburnt fuel on the grate and lead to increased piling? 2. redirect air that should have entered through the grate via the ATO Damper to a higher location in the boiler, and thereby affect combustion in the furnace?3. by a combination of 1 and 2: (a) affect the intended distribution of air and fuel within the furnace;(b) reduce efficient combustion; and(c) cause an excessive accumulation of unburnt fuel (“piling”) on the grate?4. result in overheating of the grate over a prolonged period? These questions require consideration of a large body of lay and expert evidence. Predictably, the plaintiffs rely on the noticeable difference in the operation of the boiler after the defective operation of the ATO Damper was corrected. After the ATO Damper was reprogrammed by Mr Ironside so that it operated correctly, boiler operators at the Broadwater mill noticed that it operated very differently. Some of their evidence describes it as operating as a completely different boiler. Their evidence, which I accept, is that it did not overheat as frequently as it did when the ATO Damper operated in reverse. The plaintiffs also rely on expert evidence about the effect of the ATO Damper operating in reverse. Also, after the reverse operation was corrected, Mr Rojo did a test of the effects of the correction. Grate temperatures reduced by 30°C in 30 minutes. The defendants, for their part, rely on expert opinion and other evidence to submit that the consequences of the ATO Damper operating in reverse were not as great as the plaintiffs suggest. As part of their defence, they say that if the reverse operation of the ATO Damper was a serious problem then overheating would have been evident in 2008 and before the handover. They submit that the grate did not overheat as often as the plaintiffs and their witnesses suggest it did during this period. This argument suggests that overheating only became a serious problem after the handover and was due to factors other than the reversal of the ATO Damper, such as the way the operators conducted themselves or the presence of bad fuel and rocks in the biofuel. However, for reasons that emerge from the evidence I will later discuss, I find that overheating was a frequent problem before the handover. Reduced to its basics, the dispute between the parties on the issue of causation goes something like this.