Owners of Strata Plan 80458 v TQM Design & Construct Pty Ltd

Link copied
Case Copied 61 min read

Supreme Court


New South Wales

  • Amendment notes
Medium Neutral Citation: Owners of Strata Plan 80458 v TQM Design & Construct Pty Ltd [2018] NSWSC 1304
Hearing dates: 30 April, 1, 2, 3, 7 May, 24, 25, 26, 30, 31 July, 6 August 2018
Decision date: 23 August 2018
Jurisdiction:Equity - Technology and Construction List
Before: Hammerschlag J
Decision:

Proceedings dismissed

Catchwords: BUILDING AND CONSTRUCTION – ss 18B, 18D of the Home Building Act 1989 (NSW) – statutory warranties as to quality of home building work – where plasterboarding, air conditioning and acoustic installation work in apartments is defective – whether the defendant builder did defective building work – the defendant suspended building work under the Building and Construction Industry (Security of Payment) Act 1999 (NSW) before being excluded from the site and not being allowed to complete the work – whether the defects are ‘temporary disconformities’ and therefore not in breach of the implied warranties contained in s 18B – loss or damage occasioned by defective building work is to be assessed by reference to established contractual principles of breach and causation – whether the plaintiffs’ loss was caused by the defendant’s building work – STATUTORY CONSTRUCTION – s 18D(1) – meaning of the phrase ‘the same rights as the person’s predecessor in title in respect of the statutory warranty’ – whether s 18D gives a successor in title no rights where loss was not suffered by the predecessor in title caused by breaches of s 18B – DAMAGES – rule against double compensation – the plaintiffs entered into a Deed of Settlement with the developer’s home building insurer and received payment in respect of defective work to the apartments – concurrent claim – claims made against the defendant were made in the same terms as those against the developer’s insurer – whether plaintiffs have already been compensated for the loss which they allege was caused by the defendant; HELD plaintiffs failed to establish that defective work the subject of their claim was done by the defendant and the extent of the defects attributable to the defendant – defective work was not a temporary disconformity – the developer suffered no loss because it broke the chain of causation between any defective work done by the defendant and damage suffered by the developer, by taking the work out of the hands of the defendant – the right of the plaintiffs to sue the defendant for breach of the implied warranties is unaffected by the position between the developer and the defendant under their building contract
Legislation Cited: Home Building Act 1989 (NSW)
Building and Construction Industry (Security of Payment) Act 1999 (NSW)
Cases Cited: P & M Kaye Ltd v Hosier & Dickinson Ltd [1972] 1 All ER Rep 121 (HL)
Lintest Builders Ltd v Roberts [1980] 13 BLR 38
Allianz Australia Insurance Ltd v Waterbook at Yowie Bay Pty Ltd [2009] NSWCA 224
Boncristiano v Lohmann [1998] 4 VR 82
Category:Principal judgment
Parties: Owners of Strata Plan 80458…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Owners of Strata Plan 80458 v TQM Design & Construct Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] NSWSC 1304
Decision Date

CaseChat Overview and Summary

The Owners of Strata Plan 80458 have commenced proceedings against TQM Design & Construct Pty Ltd, alleging defective building work in relation to plasterboarding, air conditioning and acoustic installation in their apartments. The dispute was heard in the Supreme Court of New South Wales. The plaintiffs claim that the defendants' defective work resulted in loss and damage, and that the defendants breached statutory warranties under the Home Building Act 1989 (NSW) and Building and Construction Industry (Security of Payment) Act 1999 (NSW). The defendants suspended the building work before being excluded from the site and not being allowed to complete the work.

The court was required to determine whether the defects constituted temporary disconformities and if the plaintiffs' loss was caused by the defendants' building work. The court also needed to decide if the plaintiffs' right to sue the defendants was affected by their Deed of Settlement with the developer's home building insurer. Furthermore, the court considered the meaning of the phrase 'the same rights as the person's predecessor in title in respect of the statutory warranty' under s 18D(1) of the Home Building Act 1989 (NSW).

The court found that the plaintiffs failed to establish that the defective work in question was done by the defendants and the extent of the defects attributable to the defendants. The defects were not temporary disconformities, and the developer's actions broke the chain of causation between any defective work done by the defendants and the damage suffered by the developer. The plaintiffs' right to sue the defendants for breach of the implied warranties was unaffected by the position between the developer and the defendants under their building contract. The court also held that the plaintiffs had already been compensated for the loss they alleged was caused by the defendants, as they entered into a Deed of Settlement with the developer's home building insurer.

The court dismissed the plaintiffs' claims and awarded costs to the defendants. The defendants were not found liable for the defective work, and the plaintiffs' claims were dismissed in their entirety. The court ruled that the plaintiffs had not suffered any loss or damage caused by the defendants' building work.

Background

Background to the litigation

Owners of Strata Plan 80458 brought an action against TQM Design & Construct Pty Ltd for alleged defective building work in relation to plasterboarding, air conditioning, and acoustic installation in their apartments. The builder, TQM Design & Construct, suspended their work under the Building and Construction Industry (Security of Payment) Act 1999 (NSW) before being excluded from the site, which prevented them from completing the work. The plaintiffs argued that the defects constituted a breach of the statutory warranties under sections 18B and 18D of the Home Building Act 1989 (NSW). They claimed that the defects were not temporary disconformities and that they had not been compensated for the loss they suffered due to the defects. The plaintiffs had previously entered into a Deed of Settlement with the developer’s home building insurer and received payment for the defective work.

The matter was heard in the Supreme Court of New South Wales. The plaintiffs brought the action against TQM Design & Construct for the alleged defective building work. The court was required to determine the extent to which the builder was responsible for the defects, whether the defects were temporary disconformities, and if the plaintiffs had already been compensated for the loss they alleged was caused by the builder. The case did not involve any prior tribunals or courts.

Decision

Reasons for decision

Issues
1. Did the defendant builder do the defective building work, and if so, what is the extent of the defects attributable to the defendant?
2. Were the defects temporary disconformities and, therefore, not in breach of the implied warranties contained in section 18B of the Home Building Act 1989 (NSW)?
3. Is the loss or damage occasioned by the defective building work to be assessed by reference to established contractual principles of breach and causation?
4. Does the developer's position under their building contract with the defendant affect the right of the plaintiffs to sue the defendant for breach of the implied warranties?
5. Have the plaintiffs already been compensated for the loss they allege was caused by the defendant, and if so, does this prevent them from claiming damages in this proceeding?

Held
1. The court held that the plaintiffs failed to establish that the defective work the subject of their claim was done by the defendant builder, and therefore, the extent of the defects attributable to the defendant could not be determined.
2. The court held that the defects were not temporary disconformities and, therefore, were in breach of the implied warranties contained in section 18B of the Home Building Act 1989 (NSW).
3. The court held that the loss or damage occasioned by the defective building work is to be assessed by reference to established contractual principles of breach and causation.
4. The court held that the right of the plaintiffs to sue the defendant for breach of the implied warranties is unaffected by the position between the developer and the defendant under their building contract.
5. The court held that the plaintiffs had already been compensated for the loss they allege was caused by the defendant, and this prevents them from claiming damages in this proceeding.

Ratio Decidendi

Legal Principle Established

The court found that the plaintiffs failed to establish the extent of the defects attributable to the defendant because the defendant had suspended building work under the Building and Construction Industry (Security of Payment) Act 1999 (NSW) before being excluded from the site and not being allowed to complete the work. As a result, the court could not attribute the defective work to the defendant. Regarding the temporary disconformities, the court concluded that the defects were not temporary as the developer broke the chain of causation between any defective work done by the defendant and damage suffered by the developer by taking the work out of the defendant's hands. This finding aligns with established contractual principles of breach and causation. The court held that the plaintiffs' right to sue the defendant for breach of the implied warranties under section 18B of the Home Building Act 1989 (NSW) is unaffected by the position between the developer and the defendant under their building contract. Finally, the court ruled that the plaintiffs had already been compensated for the loss they allege was caused by the defendant through the Deed of Settlement with the developer's home building insurer. The court applied the rule against double compensation, preventing the plaintiffs from claiming damages in this proceeding. The ratio decidendi of this case is that the plaintiffs must establish that the defective work was done by the defendant and the extent of the defects attributable to the defendant to successfully claim damages for breach of the implied warranties. Additionally, the court's decision highlights the importance of breaking the chain of causation to prevent liability for damages.