Supreme Court
New South Wales
- Amendment notes
Medium Neutral Citation: Icon Co (NSW) Pty Ltd v Australia Avenue Developments Pty Ltd [2020] NSWSC 178 Hearing dates: 26 February 2020; further written submissions 28 February and 3 March 2020 Date of orders: 05 March 2020 Decision date: 05 March 2020 Jurisdiction: Equity - Technology and Construction List Before: Stevenson J Decision: Proceedings dismissed.
Catchwords: BUILDING AND CONSTRUCTION – contracts – performance bond – condition precedent to beneficiary’s entitlement to call on bond – whether security recourse event has occurred
CONTRACTS – remedies – application for injunction to restrain a breach of contract – whether damages an adequate remedyCases Cited: Abergeldie Contractors Pty Limited v Fairfield City Council [2017] NSWCA 113
Barclay Mowlem Construction Ltd v Simon Engineering (Aust) Pty Ltd (1991) 23 NSWLR 451
FMT Aircraft Gate Support Systems v Sydney Ports Corporation [2010] NSWSC 1108
Lucas Stuart Pty Ltd v Hemmes Hermitage Pty Ltd [2010] NSWCA 283
Maggbury Pty Limited v Hafale Australia Pty Limited (2001) 210 CLR 181; [2001] HCA 70
Owners of Strata Plan 80458 v TQM Design & Construct Pty Ltd [2018] NSWSC 1304
Reed Construction Services Pty Ltd v Kheng Seng (Australia) Pty Ltd (1999) 15 BCL 158
Universal Publishers Pty Ltd v Australian Executor Trustees Ltd [2013] NSWSC 2021Category: Principal judgment Parties: Icon Co (NSW) Pty Ltd (Plaintiff)
Australia Avenue Developments Pty Ltd (Defendant)Representation: Counsel:
Solicitors:
D T Miller SC with M Smith (Plaintiff)
P S Braham SC with S Gray (Defendant)
MinterEllison (Plaintiff)
HWL Ebsworth Lawyers (Defendant)
File Number(s): 2020/41060
Judgment
-
By a design and construct contract (“the Contract”) dated 29 October 2015 between the plaintiff, Icon Co (NSW) Pty Ltd (“the Builder”), and the defendant, Australia Avenue Developments Pty Ltd (“the Principal”), the Builder agreed to design and construct the high-rise mixed residential and commercial development known as “Opal Towers” located at Sydney Olympic Park.
-
On 4 February 2020 the Principal gave the Builder notice that it proposed to call on an unconditional and irrevocable bank guarantee (“the Guarantee”) in a sum in the order of $3.9 million established by the Builder under the Contract.
-
The Builder seeks to restrain the Principal from calling on the Guarantee.
-
It is common ground that, were I to conclude that the Principal should not be so restrained, the Principal will accept an equivalent cash payment from the Builder in lieu of calling on the Guarantee and undertakes not to call on the Guarantee if such cash payment is made. There is no suggestion that the Builder is unable to make such a payment.
Decision
-
The Builder has not established that the Principal is not entitled to call on the Guarantee.
-
In any event, in the particular circumstances of this case, I am not satisfied that damages would not be an adequate remedy for the Builder.
-
Accordingly the proceedings should be dismissed.
The cracking at Opal Towers
-
On 24 December 2018 damage was identified on a level of Opal Towers. The building was…
Keep reading for free
Create a free CaseChat account to read Icon Co (NSW) Pty Ltd v Australia Avenue Developments Pty Lt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] NSWSC 178
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the security recourse event had indeed occurred, thereby entitling Icon Co (NSW) Pty Ltd to call on the performance bond. Furthermore, the court had to consider whether the remedy of damages would be sufficient in this case, or if an injunction was necessary to prevent a breach of contract. The court carefully examined the terms of the performance bond and the circumstances surrounding the construction project to ascertain whether the conditions for calling on the bond had been met. The court also evaluated the nature of the breach and the potential consequences to determine if an injunction was warranted.
The court found that the security recourse event had not occurred, as certain conditions specified in the performance bond had not been met. Consequently, Icon Co (NSW) Pty Ltd was not entitled to call on the bond at that time. The court also determined that damages would be an adequate remedy for the breach of contract, and thus declined to grant the injunction sought by Icon Co (NSW) Pty Ltd. The decision was based on the specific terms of the performance bond and the circumstances of the construction project, as well as the nature of the breach and the potential consequences.
The court's final orders were that Icon Co (NSW) Pty Ltd's application to call on the performance bond was dismissed, and the application for an injunction was also dismissed. The court found that damages would be an appropriate remedy for the breach of contract, and no further action was required in relation to the performance bond or the injunction.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.