Supreme Court
New South Wales
Medium Neutral Citation: Heavy Plant Leasing Pty Ltd (In Liquidation) v McConnell Dowell Constructors (Aust) Pty Ltd (No 3) [2023] NSWSC 634 Hearing dates: 5 June 2023 Date of orders: 14 June 2023 Decision date: 14 June 2023 Jurisdiction: Equity - Technology and Construction List Before: Stevenson J Decision: Settlement received by defendant from its principal to be deducted from defendant’s claim against plaintiff for overheads and management
Catchwords: DAMAGES – defendant’s claim against plaintiff for cost to complete – where defendant settled claim against its principal – whether a component of that settlement duplicated defendant’s claim against plaintiff – whether now open to plaintiff to contend that the entire settlement amount be deducted from defendant’s claim against it – how the settlement amount is to be taken into account
Cases Cited: BCI Finances Pty Ltd (in liq) v Binnetter (No 4) (2016) 348 ALR 227; [2016] FCA 1351
Boncristiano and Another v Lohmann and Others [1998] 4 VR 82; [1998] VSC 228
Ewin v Vergara (No 3) [2013] FCA 1311
Heavy Plant Leasing Pty Ltd (In Liquidation) v McConnell Dowell Constructors (Aust) Pty Ltd (No 2) [2022] NSWSC 1775
Kimberley Developments Pty Ltd v Bale [2023] NSWCA 25
Mainteck Services Pty Ltd v Stein Heurtey SA (2014) 89 NSWLR 633; [2014] NSWCA 184
Miletich v Merchie [2012] FCA 1013
Mills v Walsh [2022] NSWCA 255
Owners of Strata Plan 80458 v TQM Design & Construct Pty Ltd [2018] NSWSC 1304
Robinson v Harman (1848) 154 ER 363
SAS Trustee Corporation v Budd [2005] NSWCA 366
The Owners Corporation Strata Plan 70579 v Midwest Constructions Pty Ltd & Ors [2012] NSWSC 644
Townsend v Stone Toms & Partners (1984) 27 BLR 26
Category: Consequential orders Parties: Heavy Plant Leasing Pty Ltd (In Liquidation) (Plaintiff/Cross-Defendant)
McConnell Dowell Constructors (Aust) Pty Ltd (Defendant/Cross-Claimant)Representation: Counsel:
Solicitors:
M Dempsey SC with M E Sheldon and W Marshall (Plaintiff/Cross-Defendant)
D L Cook SC with T J Cogley and J A Wright (Defendant/Cross-Claimant)
Banton Group (Plaintiff/Cross-Defendant)
Norton Rose Fulbright (Defendant/Cross-Claimant)
File Number(s): 2017/51274
JUDGMENT
-
I gave judgment in this matter on 21 December 2022. [1] These reasons assume familiarity with that judgment. I will use the same abbreviations.
1. Heavy Plant Leasing Pty Ltd (In Liquidation) v McConnell Dowell Constructors (Aust) Pty Ltd (No 2) [2022] NSWSC 1775.
-
I will refer to paragraphs of my 21 December 2022 judgment thus: “[Jxxx]”.
-
I concluded that MacDow was entitled to terminate the Contract.
-
It was common ground that, in that event, MacDow was entitled to damages calculated in accordance with cl 26.5 of the Contract and that:
the cost to complete the works was to be determined and assessed against the unpaid balance of the Contract sum;
if the cost to complete exceeded the unpaid balance, then HPL owed MacDow the difference;
if that cost was less than the Contract sum, then MacDow owed HPL the difference;
consistent with Robinson v Harman,[2] the effect of this…
Keep reading for free
Create a free CaseChat account to read Heavy Plant Leasing Pty Ltd (In Liquidation) v McConnell Dow... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NSWSC 634
- Decision Date
CaseChat Overview and Summary
The central legal issue was whether the plaintiff could argue that the entire settlement amount should be deducted from the defendant's claim against it, given that part of the settlement overlapped with the claim against the plaintiff. The court had to consider whether the plaintiff's position was prejudiced by the defendant's earlier settlement with its principal, and if so, how the settlement amount should be treated in the context of the defendant's claim against the plaintiff.
The court found that the plaintiff's position was indeed prejudiced by the defendant's settlement with its principal, as the settlement included costs that duplicated the claim against the plaintiff. However, the court held that the plaintiff could not contend that the entire settlement amount be deducted from the defendant's claim against it. Instead, the court determined that the settlement amount should be apportioned between the claim against the plaintiff and the settlement with the principal, and only the appropriate portion should be deducted from the defendant's claim. This approach ensured that the plaintiff's rights were protected while also considering the overlap in the settlement amounts.
The court's decision clarified that the plaintiff could not claim the entire settlement amount as a deduction from the defendant's claim. Instead, the settlement amount was to be apportioned, with only the relevant portion deducted from the defendant's claim against the plaintiff. The final orders reflected this approach, ensuring that both parties' rights were appropriately balanced in light of the settlement with the defendant's principal.