Foresight Construction Pty Ltd v MRW Plumbing Group Pty Ltd; MRW Plumbing Group Pty Ltd v Foresight Construction Pty Ltd

Link copied
Case Copied 46 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Foresight Construction Pty Ltd v MRW Plumbing Group Pty Ltd; MRW Plumbing Group Pty Ltd v Foresight Construction Pty Ltd [2022] NSWCATCD 6
Hearing dates: 24 August 2021
Date of orders: 31 January 2022 [amended 15 February 2022]
Decision date: 31 January 2022
Jurisdiction:Consumer and Commercial Division
Before:

J A Ringrose, General Member

Pursuant to Section 63 of the Civil and Administrative Tribunal Act 2013, orders published on 31 January 2022 are amended on 15 February 2022 to read as follows:
Decision:

1. In matter HB 20/12607 the respondent is to pay the applicant the sum of $12,339.24, being compensation for defective or incomplete work

2. In matter HB 20/36334 the respondent is to pay the applicant the sum of $39,975.00, being retention payments found to be due and owing by the respondent to the applicant. Such sum is to be reduced by monies owing by the respondent to the applicant in matter No. HB 20/12607

3. Foresight Construction Pty Ltd is to pay MRW Plumbing Group Pty Ltd the sum of $27,635.76, being the monies found to be owing in matter HB 20/36334 less the monies found to be owing by MRW Plumbing Group Pty Ltd to Foresight Construction Pty Ltd in matter HB 20/12607. The net sum owing is to be paid within 30 days of the date of these orders.

4. Any party seeking an order for costs is to file an application including submissions and any necessary evidence within 21 days of the date of these orders.

5. Any party opposing an order for costs is to file evidence and submissions within 42 days of the date of these orders.

6. Any application for costs will be determined on the papers provided that both parties agree to that course.

Catchwords:

BUILDING AND CONSTRUCTION — Home Building — Claims between builder and sub-contractor —Builders claim for defective and/or incomplete works — Sub contractors claim for payment of retention monies — Whether the contract has been validly terminated by the builder

Legislation Cited:

Home Building Act 1989 (NSW)

Cases Cited:

Bailey v Plasterfix Australia Pty Ltd [2015] NSWCATAP140 at para [21] (fix this)

Cohen v Zanzoul t/as Uniq Building Group [2020] NSWSC 592

Gagner Pty Ltd v Canturi Corporation Pty Ltd [2009] NSWCA 413

Meriton Apartments Pty Ltd v the Owners Strata Plan 72381 (No. 2) [2016] NSWSC 189

The Owners Strata Plan 80458 v TQM Design and Construct Pty Ltd [2018] NSWSC 1304

Texts Cited:

Nil

Category:Principal judgment
Parties:

Foresight Construction Pty Ltd (Applicant and cross-respondent)

MRW Plumbing Group Pty Ltd (Respondent and applicant in cross claim)
Representation:

Counsel:
Mr Rizk (Respondent/ Cross Applicant)

Solicitors:
Darby Jones Lawyers (Respondent/ Cross Applicant)

Mr De Marcellis (Applicant/Cross Respondent)
File Number(s): HB 20/12607
HB 20/36334
Publication restriction: Nil

reasons for decision

Background

  1. On or about 11 March 2018 Foresight Construction Pty Ltd engaged MRW Plumbing Group to provide plumbing installations and services to a site at XXX –…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Foresight Construction Pty Ltd v MRW Plumbing Group Pty Ltd;... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2022] NSWCATCD 6
Decision Date

CaseChat Overview and Summary

Foresight Construction Pty Ltd and MRW Plumbing Group Pty Ltd were parties to a building project in which both engaged in disputes over the quality of work and payment. Foresight Construction alleged that MRW Plumbing had performed defective and incomplete work, while MRW Plumbing claimed it was owed retention monies by Foresight Construction. The dispute came before the Court, which had to decide whether Foresight Construction had validly terminated the contract and, if so, whether MRW Plumbing was liable for defective work and whether Foresight Construction owed MRW Plumbing retention monies. The court examined the terms of the contract and the evidence presented by both parties to determine the validity of the termination and the respective liabilities.

The court found that Foresight Construction had validly terminated the contract and that MRW Plumbing was liable for defective work to the extent of $12,339.24. Conversely, the court found that Foresight Construction owed MRW Plumbing $39,975.00 in retention payments, which was to be reduced by the $12,339.24 owed by MRW Plumbing to Foresight Construction. The court's decision was based on a detailed analysis of the contract terms, the nature of the defects, and the evidence provided by both parties. The court's reasoning focused on the specific obligations under the contract and the performance of those obligations by the parties.

In conclusion, the court ordered that Foresight Construction was to be paid $12,339.24 for defective work by MRW Plumbing, while MRW Plumbing was to be paid $39,975.00 in retention monies by Foresight Construction, reduced by the amount owed in the opposite direction. The net sum of $27,635.76 was to be paid by Foresight Construction to MRW Plumbing within 30 days. The court also set out the procedures for any party seeking an order for costs, allowing for applications to be made on the papers if both parties agreed. This decision highlights the importance of clear contractual terms and the consequences of failing to meet those terms in construction disputes.

Orders

Orders of the court

1. In matter HB 20/12607 the respondent is to pay the applicant the sum of $12,339.24, being compensation for defective or incomplete work

2. In matter HB 20/36334 the respondent is to pay the applicant the sum of $39,975.00, being retention payments found to be due and owing by the respondent to the applicant. Such sum is to be reduced by monies owing by the respondent to the applicant in matter No. HB 20/12607

3. Foresight Construction Pty Ltd is to pay MRW Plumbing Group Pty Ltd the sum of $27,635.76, being the monies found to be owing in matter HB 20/36334 less the monies found to be owing by MRW Plumbing Group Pty Ltd to Foresight Construction Pty Ltd in matter HB 20/12607. The net sum owing is to be paid within 30 days of the date of these orders.

4. Any party seeking an order for costs is to file an application including submissions and any necessary evidence within 21 days of the date of these orders.

5. Any party opposing an order for costs is to file evidence and submissions within 42 days of the date of these orders.

6. Any application for costs will be determined on the papers provided that both parties agree to that course.

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established