Barrett Property Group Ltd v Metricon Homes Pty Ltd (No 2)

Link copied
Case Copied 20 min read

FEDERAL COURT OF AUSTRALIA

Barrett Property Group Ltd v Metricon Homes Pty Ltd (No 2)
[2007] FCA 1823  

COSTS – indemnity costs – misconduct of respondents – undue prolongation of defence.

COSTS – time for taxation of costs – departure from general rule in Federal Court Rules Order 62 r 3(3) – time for payment of costs – O 62 r 3(2) – costs to be paid forthwith.

ORDERS – stay of orders for taxation and payment of costs pending disposition of application for leave to appeal and any appeal.

Copyright Act 1968 (Cth)
Trade Practices Act 1974 (Cth)

Access For All Alliance (Hervey Bay) Inc v Hervey Bay City Council [2007] FCA 974 applied

Allstate Life Insurance Co v ANZ Banking Group Ltd [1995] FCA 660 referred to
Barrett v Metricon [2007] FCA 1509 referred to

Cirillo v Consolidated Press Property Ltd (No 2) [2007] FCA 179 cited
Colgate-Palmolive Company v Cussons Pty Limited (1993) 46 FCR 225 applied

Compagnie Industrielle de Precontrainte et D’Equipment des Constructions SA v First Melbourne Securities Pty Ltd [1999] FCA 660 discussed

Courtney v Medtel Pty Limited (No 3) [2004] FCA 347 referred to

Dias Aluminium Products Pty Ltd v Ullrich Aluminium Pty Ltd (No 2) [2005] FCA 1400 referred to
Ian Duncan v Secretary, Department of Family and Community Services [2007] FCA 507 referred to
Dunstan v Orr [2007] FCA 873 referred to
Hamod v New South Wales (2002) 188 ALR 659 cited
Hurst and Devlin v Education Queensland (No 2) [2005] FCA 793 cited
Jianshe Southern Pty Ltd v Turnbull Cooktown Pty Ltd (No 2) [2007] FCA 903 referred to
John S Hayes & Associates Pty Limited v Kimberley-Clarke Australia Pty Limited (1994) 52 FCR 210 referred to

Life Airbag Co of Australia Pty Ltd v Life Airbag Co (New Zealand) Ltd [1998] FCA 545 referred to
McKellar v Container Terminal Management Services Ltd [1999] FCA 1639 referred to

Pacific Publications Pty Ltd v Next Publishing Pty Ltd [2005] FCA 971 applied

Readymix Holdings International Pte Ltd v Wieland Process Equipment Pty Ltd [2006] FCA 1297 referred to

Re Wilcox; ex parte Ventura Industries Pty Ltd (No 2) (1996) 72 FCR 152 applied

Trumpet Software Pty Ltd v OzEmail Pty Ltd [1996] FCA 560 discussed

United Insurance Advisers Pty Ltd v United Insurance Advisers (National) Pty Ltd [2006] FCA 440 cited
Universal Music Australia Pty Ltd v Cooper [2005] FCA 1878 discussed
Anthony Vasyli v AOL International Pty Limited [1996] FCA 804 referred to
Walker v Citygroup Global Markets Pty Ltd [2005] FCA 1866 referred to
Yap v Granich & Associates [2001] FCA 1735 cited

BARRETT PROPERTY GROUP PTY LTD (ACN 088 015 267) AND SRS PROPERTY GROUP PTY LTD v METRICON HOMES PTY LTD (ACN 005 108 752), ROSS PALAZZESI AND ADRIAN POPPLE

VID 833 OF 2005

GILMOUR J
23 NOVEMBER 2007
PERTH (HEARD BY VIDEO-LINK TO MELBOURNE)

IN THE FEDERAL COURT OF AUSTRALIA

WESTERN AUSTRALIA DISTRICT REGISTRY

VID 833 OF 2005

BETWEEN:

BARRETT PROPERTY GROUP PTY LTD
(ACN 088…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Barrett Property Group Ltd v Metricon Homes Pty Ltd (No 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2007] FCA 1823
Decision Date

CaseChat Overview and Summary

The case of Barrett Property Group Ltd v Metricon Homes Pty Ltd (No 2) involved a dispute over alleged copyright infringement in residential home designs. The plaintiffs, Barrett Property Group, claimed that Metricon Homes had copied substantial parts of their architectural designs without permission. The matter was heard in the Federal Court of Australia. The primary issue before the court was whether Metricon Homes had reproduced a substantial part of Barrett’s copyright works by copying. This issue was central to the trial, consuming more than half of the trial time and forming the bulk of the judgment.

The court considered the evidence presented by both parties, focusing on whether there was actual copying of the architectural designs. The respondents' expert witness, Mr John Permewan, provided significant evidence which was later found to be misdirected by Metricon. His opinions were based on incorrect assumptions, leading to wasted costs for both parties. The court concluded that the respondents' conduct led to the misdirection of Mr Permewan and that this conduct warranted indemnity costs. The trial judge found that approximately 50% of the trial preparation and trial time was devoted to the derivation and copying issues.

Following the court's findings, the judge ordered that the respondents, Metricon Homes, pay the applicants' costs to be taxed and paid forthwith, with 50% of the trial preparation and trial costs to be taxed on an indemnity basis. The operation of these orders was stayed pending the disposition of any appeal by the respondents. The court also ordered that the respondents pay the costs of the motion for special costs orders.

This decision underscores the importance of accurate and truthful evidence in copyright infringement cases and the potential for indemnity costs when parties act in a manner that leads to significant wasted costs.

Orders

Orders of the court

1. The respondents pay the applicants’ costs to be taxed and paid forthwith.

2. Such costs, in respect of 50% of trial preparation from 10 April 2006 and the trial, be taxed on an indemnity basis.

3. The respondents pay the costs on the motion for special costs orders to be taxed and paid forthwith.

4. The operation of Orders 1 and 3 above be stayed pending the disposition of the respondents’ application for leave to appeal and any appeal.

5. The parties have liberty to apply in respect to these orders.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

GILMOUR J
In any event, the claim for infringement of the whole, was as I found, not seriously pressed by the applicants at trial. Rather, as I found, the case concerned whether, in respect of each plan and home, a substantial part had been reproduced by copying. [10] CONCLUSION AS TO INDEMNITY COSTS Indemnity costs ought be awarded in respect to preparation for and the conduct of the trial, going to the issue of derivation of the accused plans and homes and whether or not there was actual copying of the Copyright Works. The applicants say that a fair albeit conservative assessment is that 50% of the cost of preparation and trial should be subject to an order for indemnity costs. The respondents say that those issues were taken up by no more than 4 out of the 13 days at trial and that this ratio should also inform the period of preparation for trial. This produces a range of between approximately 30-50%. My own assessment of the trial was that the derivation and copying issues were absolutely central in the evidence and, I estimate, consumed more than half of the trial time involved. A further indicator is that approximately two-thirds of my reasons for judgment are concerned with those issues. Such matters are generally not capable of precise arithmetical calculation or analysis and are to a considerable extent matters of impression and judgment. See by analogy Dias Aluminium Products Pty Ltd v Ullrich Aluminium Pty Ltd (No 2) [2005] FCA 1400 at [7]. I also consider that this conduct led to wasted costs in relation to much of the evidence of the respondents’ expert Mr John Permewan. I did not afford his evidence any weight, because as I found, he was significantly misdirected by Metricon on a number of significant matters and was not told in the witness box before giving evidence about significant revisions to Metricon’s witness statements. As a result, his opinions as to independent derivation were founded upon significantly incorrect assumptions and were of no real assistance to the Court. One example of this was that he incorrectly assumed that the Tyrell, Connolly and Streeton designs and homes were not designed by reference to the Prada 35. In fact, as I found, they were. He did not deal expressly in his report with the actual design drawings from which, according to the respondents, Prototypes 20A and 20B were derived. He assumed that certain evidence given by Bugeja, but which was disavowed by him at trial, was correct and he relied upon it. He accepted that Gallery 32 was used in the derivation of Prada 35. It was not. [252]-[256] Furthermore the applicants put the respondents on notice that Mr Permewan had been misinstructed. The solicitors for the applicants wrote to the respondents’ solicitors by letter dated 9 October 2006 stating amongst other things that: Mr Permewan has proffered views about whether or not copying occurred by reference to his beliefs based on the untested evidence of Metricon's witnesses. It is clear from his report that Mr Permewan has taken as truthful, and without qualification, the evidence of Metricon’s lay witnesses. I accept that consideration of Mr Permewan’s affidavit evidence would have required significant amount of time before analysis on the part of the applicants’ solicitors and counsel and indeed also by Dr John Cooke the expert architect obtained by the applicants. The matters deposed to by these lay witnesses may be overridden by the impressions formed by the Court following cross-examination.

Ratio Decidendi

Legal Principle Established

Established by: GILMOUR J