Australian Energy Regulator v Hornsdale Power Reserve Pty Ltd

Link copied
Case Copied 40 min read

FEDERAL COURT OF AUSTRALIA

Australian Energy Regulator v Hornsdale Power Reserve Pty Ltd [2022] FCA 738

File number: SAD 176 of 2021
Judgment of: BESANKO J
Date of judgment: 28 June 2022
Catchwords: CONSUMER LAW — application for declarations of contraventions of National Electricity Rules (NER) pursuant to s 44AAG(1) of Competition and Consumer Act 2010 (Cth) (CC Act) and order for payment of civil penalty pursuant to s 44AAG(2)(a) of CC Act — where respondent “Registered Participant” in National Electricity Market (NEM) and registered with Australian Energy Market Operator (AEMO) as “Market Generator” and “Market Customer” with respect to Hornsdale Power Reserve (HPR) — where during relevant period, respondent made market ancillary service offers to AEMO for contingency frequency control ancillary services (FCAS), being services procured by AEMO to ensure that when frequency of NEM goes outside of “normal operating frequency band”, frequency recovers — where to qualify for registration to participate in trading markets for contingency FCAS, respondent required to have generating unit or load approved by AEMO, including by providing parameters about generating unit — where “droop”, being amount or proportionality of response to variation in frequency, agreed to with AEMO at time of registration was 1.7% — where on 23 July 2019, update on firmware for HPR performed by respondent’s contractor assisting in operation and maintenance of HPR, with effect of altering settings such that droop was 3.7% and reducing maximum response capacity of generating unit and load compared to classification by AEMO — where on 9 October 2019, unplanned outage event in response to which power system frequency fell and respondent required to deliver particular contingency FCAS — where respondent’s FCAS response less than expected, caused by change in settings as a result of firmware update on 23 July 2019 — where respondent not aware of change until informed by AEMO on 12 November 2019 and on 14 November 2019, relevant settings effecting droop for HPR corrected to 1.7% — where respondent did not comply with cl 4.9.8(a) of NER in respect of 185,738 dispatch instructions given by AEMO for respondent to be ready and capable of providing service stated at nominated range — where respondent did not comply with cl 4.9.8(d) of NER in respect of latest market ancillary service offer during 32,602 trading intervals, because offers for response capability exceeding maximum dispatch capability of HPR — where respondent did not comply with cl 3.8.7A(l) of NER in respect of 690 market ancillary service offers, because response capability did not reflect technical characteristics of generating units — where respondent agrees orders sought by applicant should be made — whether appropriate to make declarations sought — consideration of matters in s 64 of National Electricity Law for which there must be regard in determining civil penalty and other relevant matters — consideration of relevance of statutory maximum in fixing civil penalty in accordance with Australian Building and Construction Commissioner v Pattinson [2022] HCA 13; (2022) 399 ALR 599 — where among other things, parties…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Australian Energy Regulator v Hornsdale Power Reserve Pty Lt... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] FCA 738
Decision Date

CaseChat Overview and Summary

In the case of Australian Energy Regulator v Hornsdale Power Reserve Pty Ltd, the Australian Energy Regulator (AER) sought declarations and a pecuniary penalty from Hornsdale Power Reserve Pty Ltd (the respondent) for contraventions of the National Electricity Rules (NER). The respondent, a participant in the National Electricity Market (NEM), was registered with the Australian Energy Market Operator (AEMO) as both a Market Generator and Market Customer. The dispute arose from the respondent's failure to comply with certain NER clauses during a period when it offered contingency frequency control ancillary services (FCAS) to AEMO.

The legal issues centred on whether the declarations sought by the AER were appropriate under the Competition and Consumer Act 2010 (Cth) and the National Electricity Law (NEL). Additionally, the court had to determine whether the imposition of a pecuniary penalty was warranted and, if so, the appropriate amount. The court considered the nature and extent of the breaches, the loss or damage caused by the breaches, and the respondent's compliance history and any existing compliance programs.

The court found that the declarations were appropriate for several reasons. The declarations, in conjunction with the pecuniary penalty, would serve as a deterrent not only to the respondent but also to other participants in the NEM. The public interest in the proper functioning of the electricity market supported the making of the declarations. Furthermore, the severity of the breaches and the statutory maximum penalties indicated a strong disapproval from Parliament, which the court should reflect in its decision. The court concluded that the declarations clearly identified the contraventions and were appropriately framed.

Regarding the pecuniary penalty, the court considered the relevant matters outlined in section 64 of the NEL, including the nature and extent of the breaches, any loss or damage caused, and the respondent's compliance history. The court decided on a penalty of $900,000, reflecting the seriousness of the conduct and the need to deter similar breaches in the future.

The court ordered the respondent to pay the penalty within 28 days and also ordered the respondent to pay the AER's costs of the proceeding, which were agreed upon. All remaining claims in the originating application were dismissed.

Orders

Orders of the court

4. Pursuant to s 44AAG(2)(a) of the Competition and Consumer Act 2010 (Cth), within 28 days of the making of this order, the respondent pay to the Commonwealth of Australia a pecuniary penalty of $900,000 in respect of the contraventions of NER clauses 3.8.7A(l), 4.9.8(a) and 4.9.8(d) referred to in the Declarations.

5. Pursuant to s 43 of the Federal Court of Australia Act 1976 (Cth), within 28 days of the making of this order, the respondent pay the applicant’s costs of and incidental to this proceeding, agreed in the amount of $30,000.

6. All of the remaining claims in the Originating Application are dismissed.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

In addition to these orders, the parties seek an order that all of the remaining claims in the Originating application be dismissed. THE FACTS The following facts are taken from the statement of agreed facts. A Glossary, insofar as it relates to expressions in the NER, is included in these reasons as Appendix A. The “relevant period” for the purposes of the alleged breaches is the period from 10.05 am on 23 July 2019 (AEST) until 5.10 pm on 14 November 2019 (AEST). The applicant is a body corporate established pursuant to s 44AE of the CC Act and has the functions and powers referred to in s 15 of the NEL. The respondent is and was at all material times a company registered under the Corporations Act 2001 (Cth) and the owner and operator of the Hornsdale Power Reserve (the HPR). The respondent has been, since 14 November 2017, a Registered Participant in the National Electricity Market (the NEM) and was registered with the Australian Energy Market Operator (AEMO) as a Market Generator and Market Customer in relation to the HPR. At all times, including during the relevant period, AEMO was the independent market and system operator for the NEM. The NEM is an interconnected power system across eastern and south-eastern Australia. AEMO’s statutory functions are identified in s 49 of the NEL and they include to operate and administer the wholesale exchange where electricity and services are traded and to maintain and improve power system security (s 49(1)(a) and (e)). AEMO’s obligations include using reasonable endeavours to control the frequency of the NEM within the normal operating frequency band, which was within a range of 49.85Hz to 50.15Hz 99% of the time, and 49.75Hz to 50.25Hz 1% of the time. It is agreed between the parties that while the normal operating frequency band specified in the NER is the range 49.9Hz to 50.1Hz, this range has been altered by specification in the power system security standards approved by the Reliability Panel (a panel established under s 38 of the NEL) on the advice of AEMO (which, during the relevant period, were the Frequency Operating Standards set out in the Reliability Panel’s final report dated 15 April 2009) to the range of 49.85Hz to 50.15Hz 99% of the time and 49.75Hz to 50.25Hz 1% of the time. Maintaining the frequency within the normal operating frequency band is necessary for the security of the power system. As a general proposition, if power generation increases, the frequency will rise and if demand for electricity increases, the frequency will fall. Therefore, maintaining equilibrium between demand and supply is necessary to keep the power system frequency within the normal operating frequency bands. If the frequency goes outside of this range, the NEM can face significant issues. AEMO procures frequency control ancillary services (FCAS) to ensure that when frequency does go outside of the normal operating frequency band, the frequency recovers. Under the Frequency Operating Standards that applied during the relevant period, AEMO was required to use reasonable endeavours to ensure that following most events, the system frequency should not exceed the normal operating frequency band for more than five minutes.

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

I turn now to the relief sought by the applicant.THE DECLARATIONS The applicant seeks three declarations, each relating to a contravention of a particular clause of the NER. The source of the Court’s power to make the declarations in this case is contained in s 44AAG(1) of the CC Act and s 21 of the Federal Court of Australia Act 1976 (Cth). The respondent consents to the making of the declarations. Nevertheless, the Court must be satisfied that the making of the declarations is appropriate. I discussed the principles which are relevant to the making of declarations for contraventions of the NER in my recent decision in Australian Energy Regulator v AGL HP 1 Pty Ltd [2022] FCA 737 (AER v AGL) (at [35]–[39]). The circumstances of this case are such that it is an appropriate case for declarations because: (1) the declarations coupled with the pecuniary penalty will act as a deterrent, both to the respondent and other Registered Participants in the NEM and, therefore, there is utility in granting the declarations; (2) there is a public interest in the declarations as all members of the community have an interest in a properly functioning electricity market; (3) Parliament has indicated the extent of its disapproval of the conduct by the size of the maximum penalties. This is serious conduct and the Court should indicate its disapproval of it, not only by imposing a pecuniary penalty, but also by making declarations; and (4) the proposed declarations clearly identify the contraventions and are appropriate in their terms. THE PECUNIARY PENALTY The applicant seeks an order that the respondent pay a pecuniary penalty of $900,000 in respect of the contraventions. The Court’s power to order that a person pay a pecuniary penalty is contained in s 44AAG(2)(a) of the CC Act. The penalty to be imposed is to be determined “in accordance with the law”. Each of the clauses contravened as identified in the declarations carries a civil penalty. The NEL is the schedule to the National Electricity (South Australia) Act and s 2AA of the NEL provides that a provision of the NEL or the NER is a civil penalty provision if prescribed to be such by the Regulations. The National Electricity (South Australia) Regulations identify the three clauses referred to in the declarations as civil penalty provisions. Section 64 of the NEL identifies the matters for which there must be regard in determining the amount of a civil penalty. The section provides:Every civil penalty ordered to be paid by a person declared to be in breach of a provision of this Law, the Regulations or the Rules must be determined having regard to all relevant matters, including—(a)the nature and extent of the breach; and(b)the nature and extent of any loss or damage suffered as a result of the breach; and(c)the circumstances in which the breach took place; and(d)whether the person has engaged in any similar conduct and been found to be in breach of a provision of this Law, the Rules or the Regulations in respect of that conduct; and(e)whether the service provider had in place a compliance program approved by the AER or required under the Rules, and if so, whether the service provider has been complying with that program.